AI insight
74% chance of a further slip within 45 days
From the SPI trend (0.87), the task closure rate and the open risks, the early-warning engine expects another slip unless the resource gap is closed.
One platform bringing 68 of the authority’s services into a single journey — Nafath sign-in and SADAD payments.
Budget (BAC)
Actual cost
60% of budget
Progress
Planned 67%
Estimate at completion
SAR +3.6M
SPI · CPI
Forecast finish
42 days behind baseline
ExecutionPhase 7 of 11
Next gate:Monitoring & Control15 February 2027
A weighted index, not just percent complete; each dimension leads to the tab that explains it.
Health index
69
Needs watching
Index over the last six reports
May to October 2026
AI insight
From the SPI trend (0.87), the task closure rate and the open risks, the early-warning engine expects another slip unless the resource gap is closed.
Generated from the live project data
The project is at risk: 58% done against 67% planned; official launch now forecast for 12 May 2027 instead of 31 March.
The main cause is the vendor’s integration-engineer gap and a nine-day Nafath test-environment outage, which pushed back the wave-1 and integration milestones.
Cost is broadly in control (CPI 0.96); EAC SAR 90.0M, SAR 3.6M over.
Needed: approve CR-2026-012 for extra integration capacity — it recovers 12 days.
6 of 12 milestones complete
Earned-value curve
Planned, earned and actual to the data date, cumulative, with the forecast cost tail
Commitments are 83% of budget
10 approvals and 6 open actions on this project
From «My actions» for this project
6 open
Cost and schedule impact
11 open risks, exposure SAR 10.4M
Impact
2 escalated
3 of 11 approved
15 members
Team
15 members
3 contracts