10My actionsNotifications
PRJ-2026-014At risk7ExecutionHybrid

Unified Digital Services Platform

Remove from watchlist

One platform bringing 68 of the authority’s services into a single journey — Nafath sign-in and SADAD payments.

Early warning: ⁦74%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SAR 86.4M

Actual cost

SAR 52.2M

⁦60%⁩ of budget

Progress

⁦58%⁩

Planned ⁦67%⁩

Estimate at completion

SAR 90M

SAR +3.6M

SPI · CPI

0.87Schedule performance index · 0.870.96Cost performance index · 0.96

Forecast finish

⁦2027-05-12⁩

42 days behind baseline

ExecutionPhase ⁦7⁩ of ⁦11⁩

Next gate:Monitoring & Control15 February 2027

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate16 June 2024Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate22 September 2024Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionConditional goDate5 January 2025Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate16 February 2025Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate2 March 2025Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionConditional goDate27 April 2025Execution · Current phaseExecution · Current phase
  8. Gate into «Monitoring & Control»DecisionNot held yetDate15 February 2027Monitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Project health across eight dimensions

A weighted index, not just percent complete; each dimension leads to the tab that explains it.

Index over the last six reports

−12

May to October 2026

  • Resources from at risk to off track after two integration engineers left⁦2026-10-11⁩
  • Schedule to at risk as the ⁦wave-1⁩ milestone passed its date⁦2026-10-01⁩
  • Stakeholders back on track after the committee approved the recovery plan⁦2026-09-15⁩

AI insight

⁦74%⁩ chance of a further slip within ⁦45⁩ days

From the SPI trend (⁦0.87⁩), the task closure rate and the open risks, the early-warning engine expects another slip unless the resource gap is closed.

Confidence⁦82%⁩

Copilot summary

Generated from the live project data

The project is at risk: ⁦58%⁩ done against ⁦67%⁩ planned; official launch now forecast for ⁦12⁩ May ⁦2027⁩ instead of ⁦31⁩ March.

The main cause is the vendor’s integration-engineer gap and a nine-day Nafath test-environment outage, which pushed back the ⁦wave-1⁩ and integration milestones.

Cost is broadly in control (CPI ⁦0.96⁩); EAC SAR ⁦90.0M⁩, SAR ⁦3.6M⁩ over.

Needed: approve ⁦CR-2026-012⁩ for extra integration capacity — it recovers ⁦12⁩ days.

Progress & earned value

⁦6⁩ of ⁦12⁩ milestones complete

Earned-value curve

Planned, earned and actual to the data date, cumulative, with the forecast cost tail

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Budget & commitments

Commitments are ⁦83%⁩ of budget

52.2M/ 86.4M3.6Mprojected overrun(⁦4.2%⁩)
Actual spend
52.2M
Committed
71.8M
Approved budget
86.4M
Estimate at completion
90M

Next milestones

  • Wave 1 development complete (24 services)⁦2026-11-12⁩was ⁦2026-09-30⁩Late
  • Nafath & SADAD integration complete⁦2026-12-10⁩was ⁦2026-10-31⁩Late
  • Penetration test passed, security sign-off⁦2027-01-28⁩was ⁦2026-12-15⁩At risk
  • User acceptance testing complete⁦2027-03-14⁩was ⁦2027-01-31⁩At risk
  • Official platform launch⁦2027-04-15⁩was ⁦2027-03-01⁩At risk

Waiting on someone

⁦10⁩ approvals and ⁦6⁩ open actions on this project

Approvals & requests

From «My actions» for this project

Actions

⁦6⁩ open

  • Vendor to submit a replacement plan for integration engineers within a weekEng. Sultan F. Al-GhamdiIn 5 days2026-11-0222 Jumada I 1448 AHHigh
  • Write to the DGA to extend the Nafath test environmentEng. Reem K. Al-DosariDue tomorrow2026-10-2918 Jumada I 1448 AHHigh
  • Lift automated test coverage to ⁦75%⁩ before UATJoud N. Al-AhmadiIn 23 days2026-11-2010 Jumada II 1448 AHMedium
  • Reconcile licence-issuance requirements in a joint workshopLama S. Al-HarbiIn 2 days2026-10-3019 Jumada I 1448 AHMedium
  • Prepare a load-test plan for the hosting environmentEng. Saad M. Al-DosariIn 18 days2026-11-155 Jumada II 1448 AHMedium
  • Update the recovery plan and present it to the Steering CommitteeEng. Sultan F. Al-GhamdiIn 4 days2026-11-0121 Jumada I 1448 AHHigh

Risks & issues

11 open risks, exposure SAR 10.4M

Risk map

Probability
5Probability: Almost certain · Impact: NegligibleLow · Score ⁦5⁩Probability: Almost certain · Impact: MinorMedium · Score ⁦10⁩Probability: Almost certain · Impact: ModerateHigh · Score ⁦15⁩Probability: Almost certain · Impact: MajorCritical · Score ⁦20⁩Probability: Almost certain · Impact: SevereCritical · Score ⁦25⁩
4Probability: Likely · Impact: NegligibleLow · Score ⁦4⁩Probability: Likely · Impact: MinorMedium · Score ⁦8⁩Probability: Likely · Impact: ModerateMedium · Score ⁦12⁩2Probability: Likely · Impact: MajorHigh · Score ⁦16⁩RSK-0001Nafath and SADAD integration interfaces not ready on timeRSK-0002Shortage of integration and back-end engineers on the vendor teamProbability: Likely · Impact: SevereCritical · Score ⁦20⁩
3Probability: Possible · Impact: NegligibleLow · Score ⁦3⁩Probability: Possible · Impact: MinorLow · Score ⁦6⁩3Probability: Possible · Impact: ModerateMedium · Score ⁦9⁩RSK-0005Incomplete migration of beneficiary data from legacy systemsRSK-0007Staff resistance to the new digital proceduresRSK-0010Mobile-app team competing with the platform for the same people2Probability: Possible · Impact: MajorMedium · Score ⁦12⁩RSK-0003Late sign-off of licensing-service requirements by the owning departmentsRSK-0006Possible critical findings in the pre-launch penetration testProbability: Possible · Impact: SevereHigh · Score ⁦15⁩
2Probability: Unlikely · Impact: NegligibleLow · Score ⁦2⁩Probability: Unlikely · Impact: MinorLow · Score ⁦4⁩2Probability: Unlikely · Impact: ModerateLow · Score ⁦6⁩RSK-0008Late delivery of identity & access management licencesRSK-0011Updated user-experience standards from the Digital Government Authority1Probability: Unlikely · Impact: MajorMedium · Score ⁦8⁩RSK-0004Cloud hosting capacity exceeded at launchProbability: Unlikely · Impact: SevereMedium · Score ⁦10⁩
1Probability: Rare · Impact: NegligibleLow · Score ⁦1⁩Probability: Rare · Impact: MinorLow · Score ⁦2⁩Probability: Rare · Impact: ModerateLow · Score ⁦3⁩Probability: Rare · Impact: MajorLow · Score ⁦4⁩Probability: Rare · Impact: SevereLow · Score ⁦5⁩
12345

Impact

  • Critical0
  • High2
  • Medium6
  • Low2

Deliverables

⁦3⁩ of ⁦11⁩ approved

  • Business requirements documentDLV-01 · V4Lama S. Al-Harbi⁦2025-08-31⁩2025-08-318 Rabiʻ I 1447 AHApproved
  • UX prototypeDLV-02 · V3Maha F. Al-Khathami⁦2025-09-15⁩2025-09-1523 Rabiʻ I 1447 AHApproved
  • Solution & integration designDLV-03 · V5Eng. Asma S. Al-Hamdan13 days overdue2026-10-154 Jumada I 1448 AHIn review
  • Wave 1 service package (24 services)DLV-04 · V1Eng. Sultan F. Al-Ghamdi28 days overdue2026-09-3019 Rabiʻ II 1448 AHSubmitted
  • Nafath integration interfacesDLV-05 · V2Hussam T. Al-QurashiIn 3 days2026-10-3120 Jumada I 1448 AHIn progress
  • SADAD integration interfacesDLV-06 · V1Hussam T. Al-QurashiIn 18 days2026-11-155 Jumada II 1448 AHDraft
  • Data migration planDLV-07 · V2Rakan F. Al-Mohammadi18 days overdue2026-10-1029 Rabiʻ II 1448 AHReturned
  • Master test planDLV-08 · V3Joud N. Al-Ahmadi⁦2026-06-30⁩2026-06-3015 Muharram 1448 AHApproved
  • Performance & load test reportDLV-09 · V0Eng. Saad M. Al-DosariIn 53 days2026-12-2011 Rajab 1448 AHDraft
  • Change management & training planDLV-10 · V2Nouf M. Al-BalawiIn 3 days2026-10-3120 Jumada I 1448 AHSubmitted
  • User & operator guideDLV-11 · V0Lama S. Al-HarbiIn 110 days2027-02-158 Ramadan 1448 AHDraft

Team, contracts & documents

Team

15 members

Eng. Sultan F. Al-Ghamdi · Project Manager, Unified Digital Services PlatformEng. Reem K. Al-Dosari · Programme Manager, Digital Government ServicesEng. Majed S. Al-Rasheed · VP, Digital Transformation & TechnologyHussam T. Al-Qurashi · Senior Software Engineer – IntegrationLama S. Al-Harbi · Senior Business AnalystJoud N. Al-Ahmadi · QA & Testing SpecialistNouf M. Al-Balawi · Change Management Specialist
  • Eng. Sultan F. Al-GhamdiEng. Sultan F. Al-GhamdiProject Manager, Unified Digital Services PlatformProject managerP-005s.alghamdi@alwaha.gov.sa⁦100%⁩
  • Eng. Reem K. Al-DosariEng. Reem K. Al-DosariProgramme Manager, Digital Government ServicesProgramme manager (oversight)P-004r.aldosari@alwaha.gov.sa⁦20%⁩
  • Eng. Majed S. Al-RasheedEng. Majed S. Al-RasheedVP, Digital Transformation & TechnologyProject sponsorP-011m.alrasheed@alwaha.gov.sa⁦20%⁩
  • Hussam T. Al-QurashiHussam T. Al-QurashiSenior Software Engineer – IntegrationLead integration engineerP-030h.alqurashi@alwaha.gov.sa⁦100%⁩
  • Lama S. Al-HarbiLama S. Al-HarbiSenior Business AnalystSenior business analystP-006l.alharbi@alwaha.gov.sa⁦80%⁩
  • Joud N. Al-AhmadiJoud N. Al-AhmadiQA & Testing SpecialistQA & test leadP-033j.alahmadi@alwaha.gov.sa⁦70%⁩
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close