Hussam T. Al-QurashiLeave on critical workHussam’s leave falls in the last two weeks of the “SADAD integration” package, on the critical pathRecommendation
Eng. Waleed O. Al-JuhaniLeave on critical workWaleed is away during the treatment plant’s commissioning tests with no named deputy
Reallocation recommendations
Copilot proposes them from skills, loads and the critical path — apply one to see the effect at once
Reassigning Eng. Saad Al-Dosari cuts the platform’s delay by 12 days
Raise Saad’s platform allocation from 15% to 50% for 10 weeks and move internal-integration tasks to him from Hussam Al-Qurashi — Hussam returns to 100% and “SADAD integration” on the critical path speeds up.
Rakan Al-Mohammadi starts the analytics platform’s data warehouse
Rakan is at 70% with data engineering (4/5). Giving 25% of him to the analytics platform from December covers half an open seat and pulls the build start forward by nine days.
Deferring the operations-centre study a month eases the January peak
Eng. Omar Bawazir runs three live projects and reaches 107% in January if the proposed study starts alongside them. Moving its start to February brings him to 84% that month with no effect on his running projects.