AI insight
55% chance of a further slip within 60 days
From the SPI trend (0.89), the task closure rate and the open risks, the early-warning engine expects another slip unless the resource gap is closed.
Internal roads and utility networks for a 12 km² logistics zone at the northern gateway.
Budget (BAC)
Actual cost
34% of budget
Progress
Planned 37%
Estimate at completion
SAR +9.9M
SPI · CPI
Forecast finish
28 days behind baseline
ExecutionPhase 7 of 11
Next gate:Monitoring & Control13 May 2027
A weighted index, not just percent complete; each dimension leads to the tab that explains it.
Health index
81
Solid
Index over the last six reports
May to October 2026
No material change in the health dimensions over the period.
AI insight
From the SPI trend (0.89), the task closure rate and the open risks, the early-warning engine expects another slip unless the resource gap is closed.
Generated from the live project data
The project is close to plan: 33% done against 37% planned.
SPI 0.89, CPI 0.96.
3 of 5 milestones complete
Earned-value curve
Planned, earned and actual to the data date, cumulative, with the forecast cost tail
Commitments are 86% of budget
0 approvals and 1 open actions on this project
1 open risk, exposure SAR 14M
Impact
1 of 4 approved
2 members