PRJ-2026-034At risk7ExecutionConstruction

Northern Logistics Zone Infrastructure

Add to watchlist

Internal roads and utility networks for a 12 km² logistics zone at the northern gateway.

Early warning: ⁦55%⁩ chance of slipping within ⁦60⁩ days

Budget (BAC)

SAR 238M

Actual cost

SAR 81.8M

⁦34%⁩ of budget

Progress

⁦33%⁩

Planned ⁦37%⁩

Estimate at completion

SAR 247.9M

SAR +9.9M

SPI · CPI

0.89Schedule performance index · 0.890.96Cost performance index · 0.96

Forecast finish

⁦2027-09-28⁩

28 days behind baseline

ExecutionPhase ⁦7⁩ of ⁦11⁩

Next gate:Monitoring & Control13 May 2027

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate17 January 2025Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate7 May 2025Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate6 July 2025Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate14 August 2025Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate7 September 2025Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionGoDate9 November 2025Execution · Current phaseExecution · Current phase
  8. Gate into «Monitoring & Control»DecisionNot held yetDate13 May 2027Monitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Project health across eight dimensions

A weighted index, not just percent complete; each dimension leads to the tab that explains it.

Index over the last six reports

−8

May to October 2026

No material change in the health dimensions over the period.

AI insight

⁦55%⁩ chance of a further slip within ⁦60⁩ days

From the SPI trend (⁦0.89⁩), the task closure rate and the open risks, the early-warning engine expects another slip unless the resource gap is closed.

Confidence⁦82%⁩

Copilot summary

Generated from the live project data

The project is close to plan: ⁦33%⁩ done against ⁦37%⁩ planned.

SPI ⁦0.89⁩, CPI ⁦0.96⁩.

Progress & earned value

⁦3⁩ of ⁦5⁩ milestones complete

Earned-value curve

Planned, earned and actual to the data date, cumulative, with the forecast cost tail

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Budget & commitments

Commitments are ⁦86%⁩ of budget

81.8M/ 238M9.9Mprojected overrun(⁦4.2%⁩)
Actual spend
81.8M
Committed
205M
Approved budget
238M
Estimate at completion
247.9M

Next milestones

  • Provisional acceptance⁦2027-07-20⁩was ⁦2027-06-29⁩Late
  • Closure⁦2027-09-28⁩was ⁦2027-08-31⁩Late

Waiting on someone

⁦0⁩ approvals and ⁦1⁩ open actions on this project

Approvals & requests

From «My actions» for this project

  • No approvals pending

Actions

⁦1⁩ open

  • Complete the August and September progress reportsEng. Ibrahim A. Al-Ghamdi13 days overdue2026-10-154 Jumada I 1448 AHMedium

Change requests

Cost and schedule impact

  • No change requests

Risks & issues

1 open risk, exposure SAR 14M

Risk map

Probability
5Probability: Almost certain · Impact: NegligibleLow · Score ⁦5⁩Probability: Almost certain · Impact: MinorMedium · Score ⁦10⁩Probability: Almost certain · Impact: ModerateHigh · Score ⁦15⁩Probability: Almost certain · Impact: MajorCritical · Score ⁦20⁩Probability: Almost certain · Impact: SevereCritical · Score ⁦25⁩
4Probability: Likely · Impact: NegligibleLow · Score ⁦4⁩Probability: Likely · Impact: MinorMedium · Score ⁦8⁩Probability: Likely · Impact: ModerateMedium · Score ⁦12⁩1Probability: Likely · Impact: MajorHigh · Score ⁦16⁩RSK-0036Logistics developer late on its infrastructure investment shareProbability: Likely · Impact: SevereCritical · Score ⁦20⁩
3Probability: Possible · Impact: NegligibleLow · Score ⁦3⁩Probability: Possible · Impact: MinorLow · Score ⁦6⁩Probability: Possible · Impact: ModerateMedium · Score ⁦9⁩Probability: Possible · Impact: MajorMedium · Score ⁦12⁩Probability: Possible · Impact: SevereHigh · Score ⁦15⁩
2Probability: Unlikely · Impact: NegligibleLow · Score ⁦2⁩Probability: Unlikely · Impact: MinorLow · Score ⁦4⁩Probability: Unlikely · Impact: ModerateLow · Score ⁦6⁩Probability: Unlikely · Impact: MajorMedium · Score ⁦8⁩Probability: Unlikely · Impact: SevereMedium · Score ⁦10⁩
1Probability: Rare · Impact: NegligibleLow · Score ⁦1⁩Probability: Rare · Impact: MinorLow · Score ⁦2⁩Probability: Rare · Impact: ModerateLow · Score ⁦3⁩Probability: Rare · Impact: MajorLow · Score ⁦4⁩Probability: Rare · Impact: SevereLow · Score ⁦5⁩
12345

Impact

  • Critical0
  • High1
  • Medium0
  • Low0

Deliverables

⁦1⁩ of ⁦4⁩ approved

  • Project management planDLV-034-1 · V1Eng. Ibrahim A. Al-Ghamdi⁦2025-08-06⁩2025-08-0612 Safar 1447 AHApproved
  • Main deliverable — stage 1DLV-034-2 · V1Yousef A. Al-Omari78 days overdue2026-08-1128 Safar 1448 AHIn review
  • Main deliverable — final stageDLV-034-3 · V0Yousef A. Al-OmariIn 197 days2027-05-137 Dhuʻl-Hijjah 1448 AHDraft
  • Final reportDLV-034-4 · V0Yousef A. Al-OmariIn 307 days2027-08-3129 Rabiʻ I 1449 AHDraft

Team, contracts & documents

Team

2 members

Eng. Ibrahim A. Al-Ghamdi · Director, Engineering SupervisionEng. Adel S. Al-Amoudi · Senior Site Engineer (Contractor)
  • Eng. Ibrahim A. Al-GhamdiEng. Ibrahim A. Al-GhamdiDirector, Engineering SupervisionProject managerP-036i.alghamdi@alwaha.gov.sa⁦70%⁩
  • Eng. Adel S. Al-AmoudiEng. Adel S. Al-AmoudiSenior Site Engineer (Contractor)Site engineerP-043a.alamoudi@alwaha.gov.sa⁦60%⁩

Documents

  • No documents yet

Meetings

  • No meetings scheduled