Contracts
The contract register with values, variation orders and payments.
- Live contracts
- 31
- Current value
- SAR 3.7B
- Paid to date
- SAR 2B
- Retention held
- SAR 187M
- Ending within 90 days
- 13
of 33 in the register
Original SAR 3.6B before variations
53% of the current value
Released after final acceptance
Guarantees or policies expiring: 7
Expiry horizon
The year ahead on one line: contract end dates, bank guarantee and insurance expiries — so nothing lapses without a decision.
What ends in the next 12 months
Ending within 90 days: 26 — click any point to open the contract
Contract end · Oct 2026
Contract end · Nov 2026
Contract end · Dec 2026
Contract end · Jan 2027
Contract end · Feb 2027
Contract end · Mar 2027
Contract end · Apr 2027
Contract end · May 2027
Contract end · Jun 2027
Contract end · Aug 2027
Contract end · Sep 2027
Guarantees · Oct 2026
Guarantees · Nov 2026
Guarantees · Dec 2026
Guarantees · Jan 2027
Guarantees · Mar 2027
Guarantees · Apr 2027
Guarantees · May 2027
Guarantees · Jun 2027
Guarantees · Jul 2027
Guarantees · Aug 2027
Guarantees · Sep 2027
Insurance · Oct 2026
Insurance · Dec 2026
Insurance · Jan 2027
Insurance · Feb 2027
Insurance · Mar 2027
Insurance · May 2027
Insurance · Jun 2027
Insurance · Jul 2027
Insurance · Aug 2027
Insurance · Sep 2027
Value by contract type
Live contracts
SAR 3.7B
Current value
- Lump sumSAR 1.4B38%
- RemeasuredSAR 2.1B58%
- Time & materialsSAR 96.7M3%
- Framework agreementSAR 38M1%
- Service contractSAR 14.1M0%
Contract register
Each contract with its original and current value, paid and retained, its dates, securities and performance.
Display options
| Actions | |||||||||
|---|---|---|---|---|---|---|---|---|---|
| WRDA/2024/011Northern Ring Road Phase 2 — construction | Advanced Construction Co. Ltd | 1.1B+3.8%Original SAR 1B, approved variations SAR 38.5M | 41%438.2M | 43.8M10% | 2027-06-30Expires in 245 days | Guarantee2027-07-30Expires in 275 days | 61 | In progress | |
| WRDA/2024/006Government Offices Complex — civil & MEP works | Gulf General Contracting Co. | 584M+4.3%Original SAR 560M, approved variations SAR 24M | 64%371.5M | 37.2M10% | 2026-12-31Expires in 64 days | Guarantee2027-01-30Expires in 94 days | 52 | Escalated | |
| WRDA/2024/003Design & build — East Waha wastewater treatment plant | United Water & Environment Co. | 373.4M+6.1%Original SAR 352M, approved variations SAR 21.4M | 72%268.9M | 26.9M10% | 2026-09-30Expired 28 days ago | Guarantee2026-10-30Expires in 2 days | 48 | Escalated | |
| WRDA/2024/017Wadi Al-Rummah Bridge — construction | Advanced Construction Co. Ltd | 298MNo variations | 43%128.1M | 12.8M10% | 2027-05-31Expires in 215 days | Guarantee2027-06-30Expires in 245 days | 66 | In progress | |
| WRDA/2024/019Waterfront rehabilitation — civil & marine protection works | Coastline Urban Development Co. | 237.6M+4.2%Original SAR 228M, approved variations SAR 9.6M | 41%98.4M | 9.8M10% | 2027-03-31Expires in 154 days | Guarantee2027-04-30Expires in 184 days | 63 | In progress | |
| WRDA/2025/025Northern logistics zone — infrastructure works | Advanced Construction Co. Ltd | 196MNo variations | 32%62.7M | 6.3M10% | 2027-08-31Expires in 307 days | Guarantee2027-09-30Expires in 337 days | 69 | In progress | |
| WRDA/2025/023Al-Waha Central Park — construction | Coastline Urban Development Co. | 118MNo variations | 55%64.9M | 6.5M10% | 2027-02-28Expires in 123 days | Guarantee2027-03-30Expires in 153 days | 74 | In progress | |
| WRDA/2025/020Fibre network roll-out — government buildings | Smart Infrastructure Telecom Co. | 108MNo variations | 55%59.4M | 5.9M10% | 2027-01-31Expires in 95 days | Guarantee2027-03-02Expires in 125 days | 68 | In progress | |
| WRDA/2025/006Backup data centre — civil & MEP works | Gulf General Contracting Co. | 95.1M+3.4%Original SAR 92M, approved variations SAR 3.1M | 75%71.8M | 7.2M10% | 2026-11-30Expires in 33 days | Guarantee2026-12-30Expires in 63 days | 62 | In progress | |
| WRDA/2025/005Solar PV supply & installation — government buildings | Sustainable Energy Contracting Est. | 81MNo variations | 55%44.3M | 4.4M10% | 2027-04-30Expires in 184 days | Guarantee2027-05-30Expires in 214 days | 86 | In progress | |
| WRDA/2025/002Supply & install smart lighting and control system | Smart Infrastructure Telecom Co. | 61.5MNo variations | 82%50.2M | 5M10% | 2026-10-31Expires in 3 days | Insurance2026-10-31Expires in 3 days | 70 | In progress | |
| WRDA/2024/022Small dams & recharge channels — construction | United Water & Environment Co. | 56MNo variations | 95%53.2M | 5.3M10% | 2026-10-31Expires in 3 days | Guarantee2026-11-30Expires in 33 days | 82 | In progress | |
| WRDA/2025/007Unified Digital Services Platform — build & run | Digital Solutions Group | 51M+4.9%Original SAR 48.6M, approved variations SAR 2.4M | 66%33.7M | 3.4M10% | 2027-03-31Expires in 154 days | Guarantee2027-04-30Expires in 184 days | 71 | In progress | |
| WRDA/2025/003ERP supply & implementation | Integrated Business Systems Co. | 41.2MNo variations | 64%26.4M | 2.6M10% | 2026-12-31Expires in 64 days | Guarantee2027-01-30Expires in 94 days | 64 | In progress | |
| WRDA/2025/012Network & server equipment — backup data centre | Smart Infrastructure Telecom Co. | 38MNo variations | 64%24.5M | 1.2M5% | 2026-11-30Expires in 33 days | Insurance2027-02-28Expires in 123 days | 72 | In progress | |
| WRDA/2025/014Framework agreement — government cloud migration services | Kingdom Cloud IT Co. | 38MNo variations | 52%19.8M | 990K5% | 2027-02-28Expires in 123 days | Insurance2027-05-29Expires in 213 days | 84 | In progress | |
| WRDA/2025/024Tree supply, planting & irrigation — Green Waha | Green Oasis Landscaping Co. | 33MNo variations | 35%11.5M | 1.2M10% | 2027-09-30Expires in 337 days | Guarantee2027-10-30Expires in 367 days | 88 | In progress | |
| WRDA/2025/004Cybersecurity programme & SOC delivery | Cyber Shield Co. | 31.5MNo variations | 85%26.8M | 1.3M5% | 2026-12-15Expires in 48 days | Guarantee2027-01-14Expires in 78 days | 91 | In progress | |
| WRDA/2024/014Supervision — Northern Ring Road | Bait Al-Khebra Engineering Consultants | 26.8MNo variations | 45%12.1M | 605K5% | 2027-09-30Expires in 337 days | Guarantee2027-12-31Expires in 429 days | 83 | In progress | |
| WRDA/2024/008Project management & supervision — Government Offices Complex | Halbern International Project Management | 19.5MNo variations | 68%13.2M | 660K5% | 2027-06-30Expires in 245 days | Guarantee2027-09-30Expires in 337 days | 76 | In progress | |
| WRDA/2025/010Investor Portal development | Digital Solutions Group | 14.8MNo variations | 85%12.6M | 630K5% | 2026-11-30Expires in 33 days | Guarantee2026-12-30Expires in 63 days | 87 | In progress | |
| WRDA/2024/005Engineering supervision — wastewater treatment plant | Halbern International Project Management | 14.6MNo variations | 73%10.7M | 535K5% | 2027-03-31Expires in 154 days | Guarantee2027-06-30Expires in 245 days | 79 | In progress | |
| WRDA/2025/017Data governance & MDM advisory | Coopers & Lane Management Consulting | 14.2MNo variations | 75%10.7M | 532.5K5% | 2026-12-31Expires in 64 days | Guarantee2027-01-30Expires in 94 days | 80 | In progress | |
| WRDA/2025/019Document & correspondence platform — supply & implementation | Integrated Business Systems Co. | 11.6MNo variations | 90%10.4M | 1M10% | 2026-09-30Expired 28 days ago | Guarantee2026-10-30Expires in 2 days | 73 | In progress | |
| WRDA/2024/021Supervision — waterfront rehabilitation | Bait Al-Khebra Engineering Consultants | 11.2MNo variations | 41%4.6M | 230K5% | 2027-06-30Expires in 245 days | Guarantee2027-09-30Expires in 337 days | 81 | In progress | |
| WRDA/2025/015Services mobile app development | Digital Solutions Group | 9.8MNo variations | 62%6.1M | 305K5% | 2027-01-31Expires in 95 days | Insurance2027-07-30Expires in 275 days | 86 | In progress | |
| WRDA/2024/018Supervision — Wadi Al-Rummah Bridge | Bait Al-Khebra Engineering Consultants | 9.4MNo variations | 50%4.7M | 235K5% | 2027-08-31Expires in 307 days | Guarantee2027-11-30Expires in 398 days | 84 | In progress | |
| WRDA/2025/011Cloud hosting services — digital services platform | Kingdom Cloud IT Co. | 9.2MNo variations | 45%4.1M | 00% | 2027-06-30Expires in 245 days | Guarantee2027-06-30Expires in 245 days | 89 | In progress | |
| WRDA/2024/012HR self-service implementation | Integrated Business Systems Co. | 8.8MNo variations | 100%8.8M | 440K5% | 2025-09-30 | Released | 90 | Closed | |
| WRDA/2024/009Unified e-appointments platform development | Digital Solutions Group | 6.9MNo variations | 100%6.9M | 345K5% | 2025-07-31 | Released | 88 | Closed | |
| WRDA/2025/013QA & project office support — digital services platform | Coopers & Lane Management Consulting | 5.4MNo variations | 60%3.2M | 162K5% | 2027-05-31Expires in 215 days | Guarantee2027-05-31Expires in 215 days | 85 | In progress | |
| WRDA/2026/001Change management & internal communications services | Knowledge Training & Development Co. | 4.9MNo variations | 60%2.9M | 147K5% | 2026-12-31Expires in 64 days | Guarantee2027-03-31Expires in 154 days | 77 | In progress | |
| WRDA/2026/003Strategic Plan 2027–2030 advisory | Coopers & Lane Management Consulting | 2.9MNo variations | 60%1.7M | 87K5% | 2026-12-15Expires in 48 days | Guarantee2027-03-15Expires in 138 days | 90 | In progress | |
| Total · 33 | 3.7B | 2B | 187.8M |