AI insight
Advanced Construction Co. Ltd’s index fell 13 points in a year
Weakest on Schedule adherence, while holding SAR 1.6B of live contracts. A written corrective plan and a monthly review are advised before any new award.
Grade 1 — Roads & Bridges
Entity average 77
of 3 contracts on 3 projects
Paid across all its contracts: SAR 629M
of 3 logged
SAR 14.5M
The seven axes the vendor is rated on each quarter, and its index across all its projects against the entity average.
Latest evaluation: Q3 2026 · 2026-10-05
| Category | Advanced Construction Co. Ltd | Entity average |
|---|---|---|
| Quality | 72 | 80 |
| Delivery | 60 | 74 |
| Schedule adherence | 54 | 70 |
| Compliance | 74 | 81 |
| Safety | 70 | 85 |
| Responsiveness | 62 | 74 |
| Financial standing | 66 | 75 |
Change since the Q2 2026 evaluation
Contractor performance index across its projects
Eight quarters, against the entity average and the target
AI insight
Weakest on Schedule adherence, while holding SAR 1.6B of live contracts. A written corrective plan and a monthly review are advised before any new award.
Every contract of the vendor with its own performance and its project’s health — the index is built from these.
WRDA/2024/011In progress
Northern Ring Road Phase 2 — construction
Northern Ring Road Development — Phase 2Off track
Performance
WRDA/2024/017In progress
Wadi Al-Rummah Bridge — construction
Wadi Al-Rummah BridgeOff track
Performance
WRDA/2025/025In progress
Northern logistics zone — infrastructure works
Northern Logistics Zone InfrastructureAt risk
Performance
Logged: 3 · open: 2
Updated programme submitted late
DelayMedium2026-10-09WRDA/2025/025
Under-strength concrete at pier 9
QualityHigh2026-09-03WRDA/2024/017
Work at height without fall protection at interchange 3
SafetyHigh2026-08-14WRDA/2024/011
Vendor risks, contractual risks on its projects, and its open claims
120-day extension claim with compensation
High · Eng. Ahmed Y. Asiri
Contractor claim for a 120-day extension with compensation
RSK-0017 · Northern Ring Road Development — Phase 2
120-day extension with compensation — utility relocation
Extension of time · In review
Registration and compliance documents with their expiry, contact details and the evaluation history.
Documents expiring within 60 days: 1
| Document | Number | Expiry | |
|---|---|---|---|
| Commercial registration | 1010248731 | 2027-02-15Expires in 110 days | |
| VAT registration certificate | 310102487310003 | 2028-12-31Expires in 795 days | |
| Zakat certificate | ZK-2026-41113 | 2027-04-30Expires in 184 days | |
| GOSI certificate | GS-880977 | 2027-01-31Expires in 95 days | |
| Nitaqat (Saudisation) certificate | NT-52061 | 2027-03-31Expires in 154 days | |
| Chamber of Commerce membership | CC-310211 | 2027-06-30Expires in 245 days | |
| Contractor classification | MC-7417 | 2027-08-31Expires in 307 days | |
| ISO 9001 certificate | ISO9001-20389 | 2026-12-20Expires in 53 days |
Quarterly evaluation by the project manager or finance
Q3 2026
2026-10-05 · Eng. Ibrahim A. Al-Ghamdi
Q2 2026
2026-07-01 · Eng. Ibrahim A. Al-Ghamdi
Q1 2026
2026-04-01 · Eng. Ibrahim A. Al-Ghamdi
Q4 2025
2026-01-01 · Eng. Ibrahim A. Al-Ghamdi
Issue: Eng. Ibrahim A. Al-Ghamdi logged a violation Updated programme submitted late
2026-10-09 09:00Edit: Eng. Ibrahim A. Al-Ghamdi evaluated the vendor for Q3 2026
2026-10-05 10:00Issue: Eng. Ibrahim A. Al-Ghamdi logged a violation Under-strength concrete at pier 9
2026-09-03 09:00Issue: Eng. Ibrahim A. Al-Ghamdi logged a violation Work at height without fall protection at interchange 3
2026-08-14 09:00Edit: Eng. Ibrahim A. Al-Ghamdi evaluated the vendor for Q2 2026
2026-07-01 10:00Edit: Eng. Ibrahim A. Al-Ghamdi evaluated the vendor for Q1 2026
2026-04-01 10:00