Procurement
The procurement plan: packages, methods, evaluation and award.
Working on:Al-Waha Region Development Authority
- Packages in the plan
- 18
- Estimated value
- SAR 787M
- In the market now
- 8
- Awaiting award
- 3
- Award savings
- SAR 600K
FY2026: 14 · FY2027: 4
FY2027 plan: SAR 145.4M
SAR 529.8M
With the procurement committee
7.1% below estimate
Ready-made views
Procurement timeline
Bars: planned spans of each step; diamonds: actual dates; gold line: today
Package
2025 Oct 2026Jan Apr Jul Oct 2027Jan Apr Jul
Prepare booklet Issue Bids close Evaluate Award Actual date Today
Etimad integration
The data is ready to exchange with Etimad; the live link starts once the permissions and interfaces are granted.
Integration-ready for Etimad
The integration layer is in place; data exchange starts once the permissions and interfaces are granted.
- Tender, bid and award fields mapped to the Etimad data model
- An Etimad reference kept for every published package
- Awards linked to contracts and certificates in Munjaz
- Awaiting the interface permissions from the competent authority
- Awaiting the integration interfaces for automatic sync
References ready to sync
Packages with an Etimad reference: 10
- Abha – Al-Baha road dualisation — main works260614031187Awaiting link
- Abha – Al-Baha road dualisation — supervision260705031244Awaiting link
- Smart asset management system — supply & implementation261004031302Awaiting link
- Identity & access management licences260914031355Awaiting link
- Strategic Plan 2027–2030 advisory260224030418Awaiting link
- Change management & internal communications251006029877Awaiting link
- Al-Waha Leadership Academy — programme provider261012031366Awaiting link