PMO dashboardMunjazPMO PLATFORMCommand center

Live· Updated just now

Executive operations room

The enterprise portfolio as it moves: strategy, major projects, risks, budget and decisions.

--:--:--

17 Jumada I 1448 AH

28 October 2026

Projects

36

⁦18⁩ on track · ⁦6⁩ delayed or critical

Progress

⁦43%⁩

Planned ⁦52%⁩

Spent to date

SAR 2.4B

of SAR 5.2B (⁦47%⁩)

Estimate at completion

SAR 5.6B

Forecast overrun SAR 407.7M

Performance indices

0.85SPI0.93CPI

Needs attention

18high risks8decisions

Open high risks · decisions and gates waiting

Strategy

Selected KPIs

  • Infrastructure projects delivered to plan73%
  • Systems hosted on the government cloud47%
  • Treated wastewater reused43%
  • Approved budget executed77%

Project map

Pick a region or a project
Riyadh · 20Makkah · 2Madinah · 2Eastern · 2Qassim · 2Asir · 2Tabuk · 1Hail · 1Northern Borders · 1Jazan · 1Najran · 1Al-BahaAl-Jouf · 1Northern Ring Road Development — Phase 2
  • On track18
  • At risk10
  • Off track4
  • Critical2
  • On hold2

Major projects

Off trackPRJ-2026-002

Northern Ring Road Development — Phase 2

38 km of the Northern Ring Road, three lanes each way, with six grade-separated interchanges.

Progress⁦42%⁩

⁦42%⁩
Budget
SAR 1.2B
EAC
SAR 1.3B
Forecast slip
⁦74⁩ days
Region
Riyadh
SPI0.82Schedule performance index · 0.82CPI0.93Cost performance index · 0.93⁦88%⁩ chance of slipping within ⁦60⁩ days
Open the project workspace

Off track

Critical risks

18
  • 25Main contractor cash-flow distress and unpaid subcontractorsEast Waha Wastewater Treatment PlantSAR 36M
  • 20Steel and asphalt price rises driving price-adjustment claimsNorthern Ring Road Development — Phase 2SAR 48M
  • 20Contractor financial claims piling up over unapproved variationsGovernment Offices ComplexSAR 41M
  • 20Late land acquisition and utility diversions in sections 3 and 4Northern Ring Road Development — Phase 2SAR 31M
  • 20Unforeseen ground conditions at the pier foundations in the wadi bedWadi Al-Rummah BridgeSAR 27M

Budget by portfolio

  • Digital Transformation PortfolioSAR 183.9M

  • Capital Projects PortfolioSAR 1.5B

  • Technology Projects PortfolioSAR 376M

  • Sustainability PortfolioSAR 726M

  • Infrastructure PortfolioSAR 2.8B

  • Institutional Development PortfolioSAR 30.5M

  • Bar: spent · tick: budget · figure: EAC

Decisions needed

8
  • ⁦26⁩ h lateApprove the October Steering Committee minutes
  • ⁦22⁩ h leftPay subcontractors directly at the wastewater treatment plant
  • ⁦50⁩ h leftRefer the Government Offices Complex claims to arbitration
  • ⁦96⁩ h leftApprove the updated recovery plan for the Unified Digital Services Platform
  • ⁦140⁩ h leftRelease SAR 22M of infrastructure reserve to speed up land acquisition
Decide on the executive dashboard
LIVE
  1. 10:42New escalation: five pier foundations to redesign — Wadi Al-Rummah Bridge
  2. 10:15Certificate 27 approved on the Northern Ring Road — SAR 31.6M
  3. 09:5014 government buildings now connected to solar
  4. 09:20Nafath / SADAD integration risk raised to 16
  5. 08:40Beneficiary satisfaction updated: 74% (+2 pts)