The objective’s weakest KPI, “Services fully available online”, is at 86% of its target, and its heaviest project, “Unified Digital Services Platform”, is At risk. Fixing that one path lifts the objective more than any other action.
What we are doing to bring the KPI back on track, who owns it, and by when.
Speed up the Nafath integration with a dedicated integration squad
Hussam T. Al-QurashiHussam T. Al-QurashiSenior Software Engineer – IntegrationP-030·h.alqurashi@alwaha.gov.saDue 2026-10-226 days overdue2026-10-22·11 Jumada I 1448 AHK-3.1.1Unified Digital Services Platform
Overdue
Fix the five biggest beneficiary-journey complaints, starting with re-keyed data
Eng. Sultan F. Al-GhamdiEng. Sultan F. Al-GhamdiProject Manager, Unified Digital Services PlatformP-005·s.alghamdi@alwaha.gov.saDue 2026-11-30In 33 days2026-11-30·20 Jumada II 1448 AHK-3.1.1Unified Digital Services Platform
In progress
Ship 6 priority services before year end in an interim release
Faisal A. Al-ShehriFaisal A. Al-ShehriDigital Transformation Portfolio ManagerP-003·f.alshehri@alwaha.gov.saDue 2026-12-20In 53 days2026-12-20·11 Rajab 1448 AHK-3.1.2Unified Digital Services Platform
Open
Challenges & notes
What holds the objective back and what leadership should know.
Challenge
Satisfaction has been flat at 74% since August; top complaints are slow Nafath integration and re-keying data.
Eng. Reem K. Al-Dosari · 2026-10-22
Challenge
The unified platform is 42 days behind baseline, delaying 18 services planned for this year.
Faisal A. Al-Shehri · 2026-10-19
Note
The digital committee put investor services first in the next release.