AI insight
No early warning on this project
Only a 0% chance of a further slip on current trends.
One booking service for beneficiary desks in the courts, with reminders and instant feedback.
Budget (BAC)
Actual cost
97% of budget
Progress
Planned 100%
Estimate at completion
SPI · CPI
Forecast finish
20 days behind baseline
Benefits RealizationPhase 11 of 11
A weighted index, not just percent complete; each dimension leads to the tab that explains it.
Health index
88
Solid
Index over the last six reports
May to October 2026
No material change in the health dimensions over the period.
AI insight
Only a 0% chance of a further slip on current trends.
Generated from the live project data
The project is close to plan: 100% done against 100% planned.
SPI 1.00, CPI 1.03.
5 of 5 milestones complete
Earned-value curve
Planned, earned and actual to the data date, cumulative, with the forecast cost tail
Commitments are 98% of budget
0 approvals and 0 open actions on this project
0 open risks, exposure SAR 0
Impact
0 escalated
4 of 4 approved
1 member