PRJ-2026-031On track11Benefits RealizationScrum

Court Appointment Booking Service

Add to watchlist

One booking service for beneficiary desks in the courts, with reminders and instant feedback.

Budget (BAC)

SAR 8.2M

Actual cost

SAR 8M

⁦97%⁩ of budget

Progress

⁦100%⁩

Planned ⁦100%⁩

Estimate at completion

SAR 8M

SPI · CPI

1.00Schedule performance index · 1.001.03Cost performance index · 1.03

Forecast finish

⁦2025-07-20⁩

20 days behind baseline

Benefits RealizationPhase ⁦11⁩ of ⁦11⁩

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate20 October 2023Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate7 February 2024Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate7 April 2024Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate29 April 2024Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate13 May 2024Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionGoDate18 June 2024Execution · CompleteExecution · Complete
  8. Gate into «Monitoring & Control»DecisionGoDate28 April 2025Monitoring & Control · CompleteMonitoring & Control · Complete
  9. Gate into «Handover»DecisionGoDate25 May 2025Handover · CompleteHandover · Complete
  10. Gate into «Closure»DecisionGoDate30 June 2025Closure · CompleteClosure · Complete
  11. Gate into «Benefits Realization»DecisionGoDate29 August 2025Benefits Realization · Current phaseBenefits Realization · Current phase

Schedule & Gantt

The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.

Finish-date drift

⁦+20⁩ days vs approved

Original baseline⁦2025-06-30⁩
Approved baseline⁦2025-06-30⁩
Current forecast⁦2025-07-20⁩
By earned schedule⁦2025-07-30⁩
Critical activities
0
of ⁦0⁩ open activities
Late activities
0
past their baseline finish
Schedule performance
1.00
earned ÷ planned value
Breached constraints
0
binding dates that will be missed
Expand allCollapse all
Activity
Court Appointment Booking ServicePlanned: ⁦2024-04-07⁩ → ⁦2025-06-30⁩Actual: ⁦2024-04-07⁩ → ⁦2025-07-20⁩
Management & governancePlanned: ⁦2024-04-07⁩ → ⁦2024-07-17⁩Actual: ⁦2024-04-07⁩ → ⁦2024-07-21⁩
Project plan & baselinePlanned: ⁦2024-04-07⁩ → ⁦2024-06-08⁩Actual: ⁦2024-04-07⁩ → ⁦2024-06-11⁩
Monitoring & reportingPlanned: ⁦2024-05-16⁩ → ⁦2024-07-17⁩Actual: ⁦2024-05-17⁩ → ⁦2024-07-21⁩
Project plan approvedPlanned: ⁦2024-07-17⁩ → ⁦2024-07-17⁩Actual: ⁦2024-07-21⁩ → ⁦2024-07-21⁩Project plan approved
Analysis & designPlanned: ⁦2024-06-23⁩ → ⁦2024-10-02⁩Actual: ⁦2024-06-27⁩ → ⁦2024-10-10⁩
Business requirementsPlanned: ⁦2024-06-23⁩ → ⁦2024-08-24⁩Actual: ⁦2024-06-27⁩ → ⁦2024-08-31⁩
Solution designPlanned: ⁦2024-08-01⁩ → ⁦2024-10-02⁩Actual: ⁦2024-08-06⁩ → ⁦2024-10-10⁩
Designs approvedPlanned: ⁦2024-10-02⁩ → ⁦2024-10-02⁩Actual: ⁦2024-10-10⁩ → ⁦2024-10-10⁩Designs approved
BuildPlanned: ⁦2024-09-09⁩ → ⁦2025-01-26⁩Actual: ⁦2024-09-16⁩ → ⁦2025-02-08⁩
Release 1Planned: ⁦2024-09-09⁩ → ⁦2024-11-10⁩Actual: ⁦2024-09-16⁩ → ⁦2024-11-19⁩
Release 2Planned: ⁦2024-10-18⁩ → ⁦2024-12-18⁩Actual: ⁦2024-10-26⁩ → ⁦2024-12-30⁩
IntegrationsPlanned: ⁦2024-11-25⁩ → ⁦2025-01-26⁩Actual: ⁦2024-12-06⁩ → ⁦2025-02-08⁩
Build completePlanned: ⁦2025-01-26⁩ → ⁦2025-01-26⁩Actual: ⁦2025-02-08⁩ → ⁦2025-02-08⁩Build complete
Testing & acceptancePlanned: ⁦2025-01-03⁩ → ⁦2025-04-14⁩Actual: ⁦2025-01-15⁩ → ⁦2025-04-30⁩
System testingPlanned: ⁦2025-01-03⁩ → ⁦2025-03-06⁩Actual: ⁦2025-01-15⁩ → ⁦2025-03-21⁩
User acceptance testingPlanned: ⁦2025-02-11⁩ → ⁦2025-04-14⁩Actual: ⁦2025-02-24⁩ → ⁦2025-04-30⁩
Testing & acceptance completePlanned: ⁦2025-04-14⁩ → ⁦2025-04-14⁩Actual: ⁦2025-04-30⁩ → ⁦2025-04-30⁩Testing & acceptance complete
Launch & handoverPlanned: ⁦2025-03-21⁩ → ⁦2025-06-30⁩Actual: ⁦2025-04-06⁩ → ⁦2025-07-20⁩
Training & changePlanned: ⁦2025-03-21⁩ → ⁦2025-05-22⁩Actual: ⁦2025-04-06⁩ → ⁦2025-06-10⁩
Go-live & handoverPlanned: ⁦2025-04-29⁩ → ⁦2025-06-30⁩Actual: ⁦2025-05-16⁩ → ⁦2025-07-20⁩
Final handoverPlanned: ⁦2025-06-30⁩ → ⁦2025-06-30⁩Actual: ⁦2025-07-20⁩ → ⁦2025-07-20⁩Final handover
  • Activities (forecast)
  • Baseline
  • Slip past baseline
  • Critical
  • Milestone
  • Phase / element
  • Today

⁦22⁩ rows shown · Data date ⁦2026-10-28⁩

AI schedule analysis

Computed from the current plan: ⁦0⁩ open activities, data date ⁦2026-10-28⁩

Slippage pattern⁦84%⁩ confidence

Milestones slip 12 days on average — and it is getting worse

Each milestone’s slip in days, in date order; the later ones slip more than the early ones.

4
8
13
16
20
G1G2G3G4G5

The critical chain

In date order, to final acceptance

No open critical activities