PRJ-2026-031On track11Benefits RealizationScrum

Court Appointment Booking Service

Add to watchlist

One booking service for beneficiary desks in the courts, with reminders and instant feedback.

Budget (BAC)

SAR 8.2M

Actual cost

SAR 8M

⁦97%⁩ of budget

Progress

⁦100%⁩

Planned ⁦100%⁩

Estimate at completion

SAR 8M

SPI · CPI

1.00Schedule performance index · 1.001.03Cost performance index · 1.03

Forecast finish

⁦2025-07-20⁩

20 days behind baseline

Benefits RealizationPhase ⁦11⁩ of ⁦11⁩

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate20 October 2023Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate7 February 2024Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate7 April 2024Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate29 April 2024Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate13 May 2024Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionGoDate18 June 2024Execution · CompleteExecution · Complete
  8. Gate into «Monitoring & Control»DecisionGoDate28 April 2025Monitoring & Control · CompleteMonitoring & Control · Complete
  9. Gate into «Handover»DecisionGoDate25 May 2025Handover · CompleteHandover · Complete
  10. Gate into «Closure»DecisionGoDate30 June 2025Closure · CompleteClosure · Complete
  11. Gate into «Benefits Realization»DecisionGoDate29 August 2025Benefits Realization · Current phaseBenefits Realization · Current phase

Finance & earned value

The full budget structure, cost broken down by eight dimensions, cash flow with its S-curve, and earned-value indicators with an automatic end-of-project forecast.

Budget anatomy

The approved SAR 8.2M split into spent, committed and left, with the estimate at completion

EAC SAR 8M
Revised request SAR 8.2M
  • Actual spendSAR 8M
  • Committed, not spentSAR 39K
  • Allotted, uncommittedSAR 0
  • Contingency availableSAR 246K

Budget

Original budgetwhen the first baseline was approved
SAR 8.2M
Approved budgetafter approved change requests
SAR 8.2M
Current budgetavailable to spend now
SAR 8.2M
Revised budgetif the pending changes are approved
SAR 8.2M

Commitments

Commitmentssigned contracts and purchase orders
SAR 8M
Contracts1 active contract
SAR 6.9M
Purchase orders⁦0⁩ orders
SAR 1.1M
Remaining budgetapproved less actual
SAR 239K

Spend & outlook

Actual costincluding accruals
SAR 8M
Accrualswork done, not yet invoiced
SAR 318K
Estimate at completionthe PM’s bottom-up forecast
SAR 8M
ContingencySAR 164K drawn of SAR 410K
SAR 246K

Budget bridge

From the original to the revised request

  • Total
  • Increase
  • Decrease

Contingency draw-downs

SAR 164K drawn of SAR 410K

  • Covering realised delivery risks⁦2026-08-29⁩SAR 164K

Cost breakdown structure

Every dimension adds up to the same totals

Cost breakdown structure — WBS
ItemBudgetSAR MCommittedSAR MActualSAR MEACSAR MVarianceSAR MConsumption
1Management & governance0.640.640.640.61⁦+0.02⁩
2Analysis & design1.351.361.351.33⁦+0.02⁩
3Build3.183.193.183.16⁦+0.02⁩
4Testing & acceptance1.591.601.591.57⁦+0.02⁩
5Launch & handover1.191.201.191.17⁦+0.02⁩
Unallocated contingency0.250.000.000.12⁦+0.12⁩
Total8.208.007.967.96⁦+0.24⁩

Budget split

WBS

SAR 8.2M

Budget

  • Management & governanceSAR 636.3K⁦8%⁩
  • Analysis & designSAR 1.4M⁦16%⁩
  • BuildSAR 3.2M⁦39%⁩
  • Testing & acceptanceSAR 1.6M⁦19%⁩
  • Launch & handoverSAR 1.2M⁦15%⁩
  • Unallocated contingencySAR 246K⁦3%⁩

Cash flow

Planned, committed, actual and forecast

Spend per period

SAR millions

  • Planned
  • Actual
  • Forecast

Cumulative S-curve

Cumulative to close

  • Actual, then forecast
  • Planned, cumulative
  • Committed, cumulative

Earned value management

At the data date ⁦2026-10-28⁩

Planned value, earned value and actual cost

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Finish by earned schedule

⁦2025-07-30⁩+30

SPI(t) ⁦0.94⁩ against the approved finish ⁦2025-06-30⁩

Planned valuePV
SAR 8.2M
The value of the work that should be done by today.
PV
Earned valueEV
SAR 8.2M
The value of the work actually done, at plan prices.
EV = % complete × BAC
Actual costAC
SAR 8M
What has actually been spent on the work done.
AC
Budget at completionBAC
SAR 8.2M
The approved budget for the whole project.
BAC
Cost varianceCV
⁦+0.24⁩ SAR M
Earned less actual; negative means paying more than the value.
CV = EV − AC
Schedule varianceSV
⁦+0.00⁩ SAR M
Earned less planned; negative means behind, in value.
SV = EV − PV
Cost performance indexCPI
1.03
Value produced per riyal spent; under 1 is an overrun.
CPI = EV ÷ AC
Schedule performance indexSPI
1.00
Work done over work planned; under 1 is behind.
SPI = EV ÷ PV
Estimate at completionEAC
SAR 8M
What the project will cost when it finishes, as forecast.
EAC = BAC ÷ CPI
Estimate to completeETC
SAR 0
What is still to be spent to completion.
ETC = EAC − AC
Variance at completionVAC
⁦+0.24⁩ SAR M
Budget less the estimate; negative is an overrun.
VAC = BAC − EAC
To-complete performance indexTCPI
0.00
The cost efficiency the rest must reach to stay on budget.
TCPI = (BAC − EV) ÷ (BAC − AC)

Automatic end-of-project forecast

Four ways to estimate the final cost, and the date earned schedule points to

  • At today’s cost performanceSAR 8M
  • If the rest goes to planSAR 8M
  • At cost and schedule performanceSAR 8M
  • The PM’s bottom-up estimateSAR 8M
  • The performance needed on the rest is below what has been achieved; the budget holds.

Estimate at completion at that performance

SAR 8M

Variance at completion: ⁦+0.24⁩ SAR M