Change requests, their impact analysis and the CCB approval path.
of 16 this year
session 42 — tomorrow
all open requests
extra days on projects
worth SAR 75M
29 October 2026 · 13:00Meeting Room 3 — 5th floor
Agenda
From submission to the board’s decision — click a stage to filter the list
Cost impact by kind of change
All requests this year
SAR 137.5M
Total
Any change to scope, budget, schedule, deliverables, contract or resources comes through here.
Display options
| Unified Digital Services Platform | Resources | +SAR 980K | −12 d | Eng. Sultan F. Al-GhamdiEng. Sultan F. Al-GhamdiProject Manager, Unified Digital Services PlatformP-005s.alghamdi@alwaha.gov.sa | 2026-10-26 | In 12 days2026-11-0929 Jumada I 1448 AH | 0/6 | Submitted | |
| Unified Digital Services Platform | Contract | +SAR 1.2M | None | Eng. Sultan F. Al-GhamdiEng. Sultan F. Al-GhamdiProject Manager, Unified Digital Services PlatformP-005s.alghamdi@alwaha.gov.sa | 2026-10-20 | In 6 days2026-11-0323 Jumada I 1448 AH | — | Submitted | |
CR-2026-014 Re-route the fibre in Al-Rawdah district | Fibre Optic Network Expansion | Scope | +SAR 1.2M | +20 d | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@alwaha.gov.sa | 2026-10-19 | In 5 days2026-11-0222 Jumada I 1448 AH | — | Submitted |
| Unified Digital Services Platform | Scope | +SAR 1.9M | +21 d | Eng. Reem K. Al-DosariEng. Reem K. Al-DosariProgramme Manager, Digital Government ServicesP-004r.aldosari@alwaha.gov.sa | 2026-10-15 | Due tomorrow2026-10-2918 Jumada I 1448 AH | 4/6 | In review | |
| Enterprise Resource Planning (ERP) System | Budget | +SAR 6.8M | +45 d | Dana S. Al-SalehDana S. Al-SalehDirector, Enterprise ApplicationsP-025d.alsaleh@alwaha.gov.sa | 2026-10-09 | In 2 days2026-10-3019 Jumada I 1448 AH | 2/6 | In review | |
| Waterfront Rehabilitation | Scope | +SAR 22.5M | +75 d | Eng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiDirector, Urban DevelopmentP-023f.alsulami@alwaha.gov.sa | 2026-10-06 | 1 day overdue2026-10-2716 Jumada I 1448 AH | 0/6 | Submitted | |
CR-2026-006 Extend the contract by 150 days | Government Offices Complex | Schedule | — | +150 d | Eng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiDirector, Government Buildings & FacilitiesP-022s.almalki@alwaha.gov.sa | 2026-10-01 | 6 days overdue2026-10-2211 Jumada I 1448 AH | 0/6 | In review |
CR-2026-010 Redesign the foundations of piers 12 to 16 | Wadi Al-Rummah Bridge | Scope | +SAR 8.4M | +55 d | Eng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector General, Roads & BridgesP-020a.asiri@alwaha.gov.sa | 2026-09-28 | 9 days overdue2026-10-198 Jumada I 1448 AH | 4/6 | In review |
| Services Mobile App | Deliverables | +SAR 320K | +10 d | Karim HaddadKarim HaddadSenior Digital Delivery ConsultantP-041k.haddad@alwaha.gov.sa | 2026-09-14 | 2026-09-282026-09-2817 Rabiʻ II 1448 AH | 6/6 | Deferred | |
CR-2026-005 Variation 7: revise the central HVAC system | Government Offices Complex | Contract | +SAR 18.6M | +40 d | Eng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiDirector, Government Buildings & FacilitiesP-022s.almalki@alwaha.gov.sa | 2026-08-20 | 55 days overdue2026-09-0321 Rabiʻ I 1448 AH | 6/6 | Escalated |
CR-2026-015 Add a classified-correspondence module | Document & Correspondence Management Platform | Deliverables | +SAR 650K | +30 d | Dana S. Al-SalehDana S. Al-SalehDirector, Enterprise ApplicationsP-025d.alsaleh@alwaha.gov.sa | 2026-08-11 | 2026-08-252026-08-2512 Rabiʻ I 1448 AH | 6/6 | Rejected |
CR-2026-013 Replace the cooling-unit supplier | National Backup Data Centre | Contract | +SAR 3.1M | +14 d | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@alwaha.gov.sa | 2026-05-17 | 2026-05-312026-05-3114 Dhuʻl-Hijjah 1447 AH | 6/6 | Approved |
CR-2026-011 Re-route the promenade at the marina | Waterfront Rehabilitation | Scope | +SAR 9.6M | +20 d | Eng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiDirector, Urban DevelopmentP-023f.alsulami@alwaha.gov.sa | 2026-04-12 | 2026-04-262026-04-269 Dhuʻl-Qiʻdah 1447 AH | 6/6 | Approved |
| Northern Ring Road Development — Phase 2 | Scope | +SAR 38.5M | +60 d | Eng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector General, Roads & BridgesP-020a.asiri@alwaha.gov.sa | 2026-03-02 | 2026-03-232026-03-234 Shawwal 1447 AH | 6/6 | Approved | |
CR-2026-001 Add a Nafath for Business integration | Unified Digital Services Platform | Scope | +SAR 2.4M | +18 d | Eng. Sultan F. Al-GhamdiEng. Sultan F. Al-GhamdiProject Manager, Unified Digital Services PlatformP-005s.alghamdi@alwaha.gov.sa | 2026-02-10 | 2026-02-242026-02-247 Ramadan 1447 AH | 6/6 | Approved |
CR-2026-003 Add a membrane tertiary-treatment stage | East Waha Wastewater Treatment Plant | Scope | +SAR 21.4M | +45 d | Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Utilities & Public ServicesP-021w.aljuhani@alwaha.gov.sa | 2026-01-18 | 2026-02-082026-02-0820 Shaʻban 1447 AH | 6/6 | Approved |