CR-2026-013National Backup Data Centre

Replace the cooling-unit supplier

ContractApproved

Justification and the cost, schedule and risk impact, with a recommendation.

Impact analysis

Before and after — as it will show in the baseline if approved

Cost

+SAR 3.1M

Current budgetSAR 144.9M

After the changeSAR 148M

+2.1%

Schedule

+⁦14⁩ d
  • Baseline finish2026-11-16
  • New finish2026-11-30

Risk

−4

Benefits

+2%

8% better energy efficiency

⁦+2⁩% of expected benefits

Reason for change

The original cooling supplier defaulted

Business justification

The alternative delivers in 14 weeks with a longer warranty

PMO recommendation

Approve

The PMO recommends approval

Approval workflow

  1. Submitted

    Eng. Omar H. Bawazir

    Done2026-05-17

  2. PM review

    Eng. Omar H. Bawazir

    Done2026-05-18

  3. Impact analysis

    Karim Haddad

    Done2026-05-22

  4. Board decision

    Dr. Mohammed I. Al-Subaie

    Done2026-05-28

  5. Sponsor sign-off

    Eng. Majed S. Al-Rasheed

    Done2026-05-30

  6. Baseline updated

    Eng. Omar H. Bawazir

    Done2026-06-01

Board vote

Members vote before or during the session; the decision is taken once quorum is met

  • Dr. Mohammed I. Al-SubaieVP, Planning & StrategyDr. Mohammed I. Al-SubaieVP, Planning & StrategyP-009m.alsubaie@alwaha.gov.saChairApprove
  • Dr. Noura M. Al-OtaibiDirector, Enterprise PMODr. Noura M. Al-OtaibiDirector, Enterprise PMOP-002n.alotaibi@alwaha.gov.saYouApprove
  • Khalid N. Al-MutairiSenior Finance & Contracts SpecialistKhalid N. Al-MutairiSenior Finance & Contracts SpecialistP-007k.almutairi@alwaha.gov.saApprove
  • Munirah A. Al-KhalidiDeputy, Financial AffairsMunirah A. Al-KhalidiDeputy, Financial AffairsP-018m.alkhalidi@alwaha.gov.saApprove
  • Eng. Asma S. Al-HamdanEnterprise ArchitectEng. Asma S. Al-HamdanEnterprise ArchitectP-031a.alhamdan@alwaha.gov.saApprove
  • Eng. Ibrahim A. Al-GhamdiDirector, Engineering SupervisionEng. Ibrahim A. Al-GhamdiDirector, Engineering SupervisionP-036i.alghamdi@alwaha.gov.saApprove
6/6Quorum met
  • Approve6
  • Approve with conditions0
  • Reject0
  • Abstain0

Decided by the board on 28 May 2026The decision in the log · DEC-2026-014

Baseline

Baseline updated on 1 June 2026