Projects
The project register by status, phase, health and variance.
Working on:Al-Waha Region Development Authority
- Projects in scope
- 36
- Approved budget
- SAR 5.2B
- Off track or critical
- 6
- On the watchlist
- 7
30 active
Forecast at completion SAR 5.6B
plus 10 at risk
Followed closely by leadership
Try:
Ready-made views
36 resultsExport CSV
Display options
Add to watchlist Energy Retrofit of Existing Buildings (ESCO) PRJ-2026-026Sustainability Portfolio | On hold | 6Procurement | 8% | 33M | 33M | 0.89Schedule performance index · 0.891.00Cost performance index · 1.00 | 2027-10-31123 days late | 1 | Data quality · Good | Eng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & EnvironmentP-028m.alotaibi@alwaha.gov.sa | |
Add to watchlist Regional Emergency & Safety Centre PRJ-2026-033Capital Projects Portfolio | On hold | 4Planning | 2% | 210M | 210M | 1.00Schedule performance index · 1.001.00Cost performance index · 1.00 | 2028-12-31184 days late | 1 | Data quality · Excellent | Eng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiDirector, Government Buildings & FacilitiesP-022s.almalki@alwaha.gov.sa | |
Remove from watchlist East Waha Wastewater Treatment Plant PRJ-2026-004Sustainability Portfolio | Critical | 7Execution | 68% | 412M | 490.5M−78.5M | 0.74Schedule performance index · 0.740.84Cost performance index · 0.84 | 2027-02-03126 days late | 3 | Data quality · Good | Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Utilities & Public ServicesP-021w.aljuhani@alwaha.gov.sa | |
Remove from watchlist Government Offices Complex PRJ-2026-007Capital Projects Portfolio | Critical | 7Execution | 57% | 640M | 780.5M−140.5M | 0.70Schedule performance index · 0.700.82Cost performance index · 0.82 | 2027-06-01152 days late | 3 | Data quality · Good | Eng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiDirector, Government Buildings & FacilitiesP-022s.almalki@alwaha.gov.sa | |
Remove from watchlist Enterprise Resource Planning (ERP) System PRJ-2026-001Technology Projects Portfolio | Off track | 7Execution | 61% | 64.5M | 73.3M−8.8M | 0.82Schedule performance index · 0.820.88Cost performance index · 0.88 | 2027-02-2758 days late | 3 | Data quality · Excellent | Dana S. Al-SalehDana S. Al-SalehDirector, Enterprise ApplicationsP-025d.alsaleh@alwaha.gov.sa | |
Remove from watchlist Northern Ring Road Development — Phase 2 PRJ-2026-002Infrastructure Portfolio | Off track | 7Execution | 42% | 1.2B | 1.3B−88.8M | 0.82Schedule performance index · 0.820.93Cost performance index · 0.93 | 2027-09-1274 days late | 4 | Data quality · Excellent | Eng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector General, Roads & BridgesP-020a.asiri@alwaha.gov.sa | |
Remove from watchlist Waterfront Rehabilitation PRJ-2026-006Capital Projects Portfolio | Off track | 7Execution | 39% | 286M | 321.3M−35.3M | 0.78Schedule performance index · 0.780.89Cost performance index · 0.89 | 2027-07-0495 days late | 2 | Data quality · Excellent | Eng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiDirector, Urban DevelopmentP-023f.alsulami@alwaha.gov.sa | |
Remove from watchlist Wadi Al-Rummah Bridge PRJ-2026-020Infrastructure Portfolio | Off track | 7Execution | 44% | 345M | 363.2M−18.2M | 0.80Schedule performance index · 0.800.95Cost performance index · 0.95 | 2027-08-0364 days late | 2 | Data quality · Excellent | Eng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector General, Roads & BridgesP-020a.asiri@alwaha.gov.sa | |
Add to watchlist National Backup Data Centre PRJ-2026-003Technology Projects Portfolio | At risk | 7Execution | 72% | 148M | 162.6M−14.6M | 0.90Schedule performance index · 0.900.91Cost performance index · 0.91 | 2027-01-0738 days late | 2 | Data quality · Excellent | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@alwaha.gov.sa | |
Add to watchlist Migration to the Government Cloud PRJ-2026-009Technology Projects Portfolio | At risk | 7Execution | 47% | 52M | 53.6M−1.6M | 0.89Schedule performance index · 0.890.97Cost performance index · 0.97 | 2027-03-2121 days late | 1 | Data quality · Excellent | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@alwaha.gov.sa | |
| Total · 36 | 5.2B | 5.6B |
1–10 of 36