PRJ-2026-007Critical7ExecutionConstruction

Government Offices Complex

Remove from watchlist

A 92,000 m² complex housing 14 agencies — ending leased buildings and co-locating services.

Early warning: ⁦97%⁩ chance of slipping within ⁦30⁩ days

Budget (BAC)

SAR 640M

Actual cost

SAR 444.9M

⁦70%⁩ of budget

Progress

⁦57%⁩

Planned ⁦82%⁩

Estimate at completion

SAR 780.5M

SAR +140.5M

SPI · CPI

0.70Schedule performance index · 0.700.82Cost performance index · 0.82

Forecast finish

⁦2027-06-01⁩

152 days behind baseline

ExecutionPhase ⁦7⁩ of ⁦11⁩

Next gate:Monitoring & Control4 August 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate18 August 2023Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate6 December 2023Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate4 February 2024Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate28 March 2024Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate29 April 2024Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionConditional goDate23 July 2024Execution · Current phaseExecution · Current phase
  8. Gate into «Monitoring & Control»DecisionNot held yetDate4 August 2026Monitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Project health across eight dimensions

A weighted index, not just percent complete; each dimension leads to the tab that explains it.

Index over the last six reports

−24

May to October 2026

No material change in the health dimensions over the period.

AI insight

⁦97%⁩ chance of a further slip within ⁦30⁩ days

From the SPI trend (⁦0.70⁩), the task closure rate and the open risks, the early-warning engine expects another slip unless the resource gap is closed.

Confidence⁦82%⁩

Copilot summary

Generated from the live project data

The project is behind plan: ⁦57%⁩ done against ⁦82%⁩ planned.

SPI ⁦0.70⁩, CPI ⁦0.82⁩.

Progress & earned value

⁦3⁩ of ⁦5⁩ milestones complete

Earned-value curve

Planned, earned and actual to the data date, cumulative, with the forecast cost tail

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Budget & commitments

Commitments are ⁦97%⁩ of budget

444.9M/ 640M140.5Mprojected overrun(⁦22.0%⁩)
Actual spend
444.9M
Committed
618M
Approved budget
640M
Estimate at completion
780.5M

Next milestones

  • Provisional acceptance⁦2027-01-29⁩was ⁦2026-10-07⁩Late
  • Closure⁦2027-06-01⁩was ⁦2026-12-31⁩Late

Waiting on someone

⁦3⁩ approvals and ⁦3⁩ open actions on this project

Approvals & requests

From «My actions» for this project

Actions

⁦3⁩ open

  • Prepare the claims file for the dispute boardEng. Shahad M. Al-MalkiIn 9 days2026-11-0626 Jumada I 1448 AHHigh
  • Approve or reject the façade samples with reasonsEng. Ibrahim A. Al-Ghamdi13 days overdue2026-10-154 Jumada I 1448 AHCritical
  • Commission an independent engineer to assess the ⁦150-day⁩ extensionEng. Abdulrahman S. Al-HarbiIn 7 days2026-11-0424 Jumada I 1448 AHHigh

Risks & issues

3 open risks, exposure SAR 65.5M

Risk map

Probability
5Probability: Almost certain · Impact: NegligibleLow · Score ⁦5⁩Probability: Almost certain · Impact: MinorMedium · Score ⁦10⁩Probability: Almost certain · Impact: ModerateHigh · Score ⁦15⁩1Probability: Almost certain · Impact: MajorCritical · Score ⁦20⁩RSK-0026Contractor financial claims piling up over unapproved variationsProbability: Almost certain · Impact: SevereCritical · Score ⁦25⁩
4Probability: Likely · Impact: NegligibleLow · Score ⁦4⁩Probability: Likely · Impact: MinorMedium · Score ⁦8⁩Probability: Likely · Impact: ModerateMedium · Score ⁦12⁩1Probability: Likely · Impact: MajorHigh · Score ⁦16⁩RSK-0027Late delivery of curtain-wall glazing from the overseas factoryProbability: Likely · Impact: SevereCritical · Score ⁦20⁩
3Probability: Possible · Impact: NegligibleLow · Score ⁦3⁩Probability: Possible · Impact: MinorLow · Score ⁦6⁩Probability: Possible · Impact: ModerateMedium · Score ⁦9⁩Probability: Possible · Impact: MajorMedium · Score ⁦12⁩1Probability: Possible · Impact: SevereHigh · Score ⁦15⁩RSK-0028Possible removal of the MEP subcontractor
2Probability: Unlikely · Impact: NegligibleLow · Score ⁦2⁩Probability: Unlikely · Impact: MinorLow · Score ⁦4⁩Probability: Unlikely · Impact: ModerateLow · Score ⁦6⁩Probability: Unlikely · Impact: MajorMedium · Score ⁦8⁩Probability: Unlikely · Impact: SevereMedium · Score ⁦10⁩
1Probability: Rare · Impact: NegligibleLow · Score ⁦1⁩Probability: Rare · Impact: MinorLow · Score ⁦2⁩Probability: Rare · Impact: ModerateLow · Score ⁦3⁩Probability: Rare · Impact: MajorLow · Score ⁦4⁩Probability: Rare · Impact: SevereLow · Score ⁦5⁩
12345

Impact

  • Critical1
  • High2
  • Medium0
  • Low0

Deliverables

⁦2⁩ of ⁦4⁩ approved

  • Project management planDLV-007-1 · V1Eng. Shahad M. Al-Malki⁦2024-03-17⁩2024-03-177 Ramadan 1445 AHApproved
  • Main deliverable — stage 1DLV-007-2 · V1Eng. Abdulrahman S. Al-Harbi⁦2025-07-29⁩2025-07-294 Safar 1447 AHApproved
  • Main deliverable — final stageDLV-007-3 · V1Eng. Abdulrahman S. Al-Harbi85 days overdue2026-08-0421 Safar 1448 AHIn review
  • Final reportDLV-007-4 · V1Eng. Abdulrahman S. Al-HarbiIn 64 days2026-12-3122 Rajab 1448 AHIn progress

Team, contracts & documents

Team

4 members

Eng. Shahad M. Al-Malki · Director, Government Buildings & FacilitiesEng. Abdulrahman S. Al-Harbi · Deputy, Capital ProjectsKhalid N. Al-Mutairi · Senior Finance & Contracts SpecialistEng. Adel S. Al-Amoudi · Senior Site Engineer (Contractor)
  • Eng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiDirector, Government Buildings & FacilitiesProject managerP-022s.almalki@alwaha.gov.sa⁦90%⁩
  • Eng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDeputy, Capital ProjectsProject sponsorP-014ab.alharbi@alwaha.gov.sa⁦25%⁩
  • Khalid N. Al-MutairiKhalid N. Al-MutairiSenior Finance & Contracts SpecialistComplex contract & certificatesP-007k.almutairi@alwaha.gov.sa⁦20%⁩
  • Eng. Adel S. Al-AmoudiEng. Adel S. Al-AmoudiSenior Site Engineer (Contractor)Site engineer (MEP)P-043a.alamoudi@alwaha.gov.sa⁦40%⁩