CR-2026-005Government Offices Complex

Variation 7: revise the central HVAC system

ContractEscalated55 days overdue2026-09-0321 Rabiʻ I 1448 AH

Justification and the cost, schedule and risk impact, with a recommendation.

Impact analysis

Before and after — as it will show in the baseline if approved

Cost

+SAR 18.6M

Current budgetSAR 640M

After the changeSAR 658.6M

+2.9%

Schedule

+⁦40⁩ d
  • Baseline finish2026-12-31
  • New finish2027-02-09

Risk

−4

Benefits

+4%

14% less energy a year

⁦+4⁩% of expected benefits

Reason for change

Central HVAC loads insufficient after the main conference hall was added

Business justification

Without it the building fails the Saudi Energy Code

PMO recommendation

Defer

The pricing dispute was referred to the steering committee

Approval workflow

  1. Submitted

    Eng. Shahad M. Al-Malki

    Done2026-08-20

  2. PM review

    Eng. Shahad M. Al-Malki

    Done2026-08-21

  3. Impact analysis

    Karim Haddad

    Done2026-08-25

  4. 4

    Board decision

    Dr. Mohammed I. Al-Subaie

    Escalated2026-10-13

  5. 5

    Sponsor sign-off

    Eng. Turki A. Al-Anazi

    Later

  6. 6

    Baseline updated

    Eng. Shahad M. Al-Malki

    Later

Board vote

Members vote before or during the session; the decision is taken once quorum is met

Steering Committee — October13 October 2026 10:00Boardroom — Main Building
  • Dr. Mohammed I. Al-SubaieVP, Planning & StrategyDr. Mohammed I. Al-SubaieVP, Planning & StrategyP-009m.alsubaie@alwaha.gov.saChairApprove with conditions
  • Dr. Noura M. Al-OtaibiDirector, Enterprise PMODr. Noura M. Al-OtaibiDirector, Enterprise PMOP-002n.alotaibi@alwaha.gov.saYouApprove
  • Khalid N. Al-MutairiSenior Finance & Contracts SpecialistKhalid N. Al-MutairiSenior Finance & Contracts SpecialistP-007k.almutairi@alwaha.gov.saReject
  • Munirah A. Al-KhalidiDeputy, Financial AffairsMunirah A. Al-KhalidiDeputy, Financial AffairsP-018m.alkhalidi@alwaha.gov.saReject
  • Eng. Asma S. Al-HamdanEnterprise ArchitectEng. Asma S. Al-HamdanEnterprise ArchitectP-031a.alhamdan@alwaha.gov.saApprove
  • Eng. Ibrahim A. Al-GhamdiDirector, Engineering SupervisionEng. Ibrahim A. Al-GhamdiDirector, Engineering SupervisionP-036i.alghamdi@alwaha.gov.saApprove with conditions
6/6Quorum met
  • Approve2
  • Approve with conditions2
  • Reject2
  • Abstain0

Awaiting the impact analysis

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close