“United Water & Environment Co.” is 95 days late and it affects “East Waha Wastewater Treatment Plant” and “Al-Waha Central Park” and 1 more
Dependencies between projects, programmes and vendors, and knock-on delay.
across 36 items
beyond their float
half the float used
outside the authority’s control
through delay propagation
When a party’s delay exceeds the float, it carries on to whatever depends on it — these are the chains that need action now
“United Water & Environment Co.” is 95 days late and it affects “East Waha Wastewater Treatment Plant” and “Al-Waha Central Park” and 1 more
“Saudi Electricity Company” is 75 days late and it affects “Northern Ring Road Development — Phase 2” and “Northern Logistics Zone Infrastructure” and 1 more
“Digital Solutions Group” is 43 days late and it affects “Unified Digital Services Platform” and “Services Mobile App” and 1 more
“National Information Center (Nafath)” is 40 days late and it affects “Unified Digital Services Platform” and “Services Mobile App” and 1 more
Tasks, projects, programmes, vendors and external entities — hover an item to see what it depends on and what depends on it, click it for its details
Delay simulator
What if an item slips further? Pick it and a number of days to see how far the effect travels.
Extra delay30 days
Each dependency: who waits on whom, for what, by when, with how much float, and the delay it carries now
Display options
DEP-029 Trial operation passed before handover | Plant trial operationTask | East Waha Wastewater Treatment PlantProject | Finish-to-start | 2026-09-30 | 0 days | 126 days | 126 days | Late | Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Utilities & Public ServicesP-021w.aljuhani@alwaha.gov.sa |
DEP-031 60% treated-water reuse | East Waha Wastewater Treatment PlantProject | Energy & Water Efficiency ProgrammeProgramme | Programme outcome | 2027-03-31 | 30 days | 126 days | 96 days | Late | Eng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & EnvironmentP-028m.alotaibi@alwaha.gov.sa |
DEP-027 Electro-mechanical works complete | United Water & Environment Co.Vendor | Plant trial operationTask | Deliverable | 2026-08-31 | 0 days | 95 days | 95 days | Late | Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Utilities & Public ServicesP-021w.aljuhani@alwaha.gov.sa |
DEP-018 HV line diversion in section 4 | Saudi Electricity CompanyExternal entity | Northern Ring Road Development — Phase 2Project | Service | 2026-09-30 | 0 days | 75 days | 75 days | Late | Eng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector General, Roads & BridgesP-020a.asiri@alwaha.gov.sa |
DEP-021 The ring road completed | Northern Ring Road Development — Phase 2Project | Regional Road Network ProgrammeProgramme | Programme outcome | 2027-06-30 | 0 days | 75 days | 75 days | Late | Eng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector General, Roads & BridgesP-020a.asiri@alwaha.gov.sa |
DEP-022 Both wadi banks connected | Wadi Al-Rummah BridgeProject | Regional Road Network ProgrammeProgramme | Programme outcome | 2027-05-31 | 0 days | 64 days | 64 days | Late | Eng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector General, Roads & BridgesP-020a.asiri@alwaha.gov.sa |
DEP-016 Automated financial processes | Enterprise Resource Planning (ERP) SystemProject | Enterprise Systems ProgrammeProgramme | Programme outcome | 2026-12-31 | 0 days | 58 days | 58 days | Late | Dana S. Al-SalehDana S. Al-SalehDirector, Enterprise ApplicationsP-025d.alsaleh@alwaha.gov.sa |
DEP-019 Foundations complete before deck works | Foundations of piers 12 to 16Task | Wadi Al-Rummah BridgeProject | Finish-to-start | 2026-12-15 | 0 days | 55 days | 55 days | Late | Eng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector General, Roads & BridgesP-020a.asiri@alwaha.gov.sa |
DEP-020 Access road to the logistics zone | Northern Ring Road Development — Phase 2Project | Northern Logistics Zone InfrastructureProject | Finish-to-start | 2027-07-31 | 20 days | 75 days | 55 days | Late | Eng. Ibrahim A. Al-GhamdiEng. Ibrahim A. Al-GhamdiDirector, Engineering SupervisionP-036i.alghamdi@alwaha.gov.sa |
DEP-003 Wave 1 service package | Digital Solutions GroupVendor | Wave 1 development (24 services)Task | Deliverable | 2026-09-30 | 0 days | 43 days | 43 days | Late | Eng. Sultan F. Al-GhamdiEng. Sultan F. Al-GhamdiProject Manager, Unified Digital Services PlatformP-005s.alghamdi@alwaha.gov.sa |
DEP-006 UAT passed before the official launch | User acceptance testingTask | Unified Digital Services PlatformProject | Finish-to-start | 2027-01-31 | 0 days | 42 days | 42 days | Late | Eng. Sultan F. Al-GhamdiEng. Sultan F. Al-GhamdiProject Manager, Unified Digital Services PlatformP-005s.alghamdi@alwaha.gov.sa |
DEP-011 Programme target: 85% of services digital | Unified Digital Services PlatformProject | Digital Government Services ProgrammeProgramme | Programme outcome | 2027-03-31 | 0 days | 42 days | 42 days | Late | Eng. Reem K. Al-DosariEng. Reem K. Al-DosariProgramme Manager, Digital Government ServicesP-004r.aldosari@alwaha.gov.sa |
DEP-001 A dedicated Nafath test environment | National Information Center (Nafath)External entity | Nafath & SADAD integration completeTask | Service | 2026-10-31 | 0 days | 40 days | 40 days | Late | Hussam T. Al-QurashiHussam T. Al-QurashiSenior Software Engineer – IntegrationP-030h.alqurashi@alwaha.gov.sa |
DEP-005 Developed services ready for testing | Wave 1 development (24 services)Task | User acceptance testingTask | Finish-to-start | 2026-12-01 | 4 days | 43 days | 39 days | Late | Joud N. Al-AhmadiJoud N. Al-AhmadiQA & Testing SpecialistP-033j.alahmadi@alwaha.gov.sa |
DEP-010 Unified service APIs for the mobile app | Unified Digital Services PlatformProject | Services Mobile AppProject | Data | 2027-01-15 | 6 days | 42 days | 36 days | Late | Karim HaddadKarim HaddadSenior Digital Delivery ConsultantP-041k.haddad@alwaha.gov.sa |
DEP-030 Treated water to irrigate the Central Park | East Waha Wastewater Treatment PlantProject | Al-Waha Central ParkProject | Service | 2026-12-31 | 92 days | 126 days | 34 days | Late | Eng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiDirector, Urban DevelopmentP-023f.alsulami@alwaha.gov.sa |
DEP-004 UAT cannot start before integration is complete | Nafath & SADAD integration completeTask | User acceptance testingTask | Finish-to-start | 2026-12-01 | 10 days | 40 days | 30 days | Late | Joud N. Al-AhmadiJoud N. Al-AhmadiQA & Testing SpecialistP-033j.alahmadi@alwaha.gov.sa |
DEP-013 Etimad e-link certification | Etimad (Ministry of Finance)External entity | Enterprise Resource Planning (ERP) SystemProject | Service | 2026-10-31 | 0 days | 28 days | 28 days | Late | Dana S. Al-SalehDana S. Al-SalehDirector, Enterprise ApplicationsP-025d.alsaleh@alwaha.gov.sa |
DEP-015 Fixed-asset register from the ERP | Enterprise Resource Planning (ERP) SystemProject | Smart Asset Management SystemProject | Data | 2027-03-01 | 30 days | 58 days | 28 days | Late | Dana S. Al-SalehDana S. Al-SalehDirector, Enterprise ApplicationsP-025d.alsaleh@alwaha.gov.sa |
DEP-023 Trenching permits in the districts | Al-Waha Region MunicipalityExternal entity | Fibre Optic Network ExpansionProject | Approval | 2026-10-15 | 15 days | 40 days | 25 days | Late | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@alwaha.gov.sa |
DEP-007 Disaster-recovery site for the cloud | National Backup Data CentreProject | Migration to the Government CloudProject | Service | 2026-12-31 | 14 days | 38 days | 24 days | Late | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@alwaha.gov.sa |
DEP-002 Updated SADAD interface specification | SADAD Payment SystemExternal entity | Nafath & SADAD integration completeTask | Deliverable | 2026-10-20 | 25 days | 23 days | — | At risk | Eng. Sultan F. Al-GhamdiEng. Sultan F. Al-GhamdiProject Manager, Unified Digital Services PlatformP-005s.alghamdi@alwaha.gov.sa |
DEP-008 Production environment on the government cloud | Migration to the Government CloudProject | Unified Digital Services PlatformProject | Service | 2027-01-31 | 30 days | 24 days | — | At risk | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@alwaha.gov.sa |
DEP-009 UX standards compliance approval | Digital Government AuthorityExternal entity | Unified Digital Services PlatformProject | Approval | 2027-02-15 | 10 days | 0 days | — | On track | Lama S. Al-HarbiLama S. Al-HarbiSenior Business AnalystP-006l.alharbi@alwaha.gov.sa |
DEP-012 The mobile channel in the programme KPIs | Services Mobile AppProject | Digital Government Services ProgrammeProgramme | Programme outcome | 2027-01-31 | 40 days | 36 days | — | At risk | Eng. Reem K. Al-DosariEng. Reem K. Al-DosariProgramme Manager, Digital Government ServicesP-004r.aldosari@alwaha.gov.sa |
DEP-014 Financial module customisations | Integrated Business Systems Co.Vendor | Enterprise Resource Planning (ERP) SystemProject | Deliverable | 2026-11-15 | 30 days | 21 days | — | At risk | Dana S. Al-SalehDana S. Al-SalehDirector, Enterprise ApplicationsP-025d.alsaleh@alwaha.gov.sa |
DEP-017 Data governance policies (gate condition) | Data Governance & Master Data ManagementProject | Analytics & AI PlatformProject | Approval | 2027-01-31 | 20 days | 18 days | — | At risk | Rahaf I. Al-NefaieRahaf I. Al-NefaieDirector, Data & AIP-027r.alnefaie@alwaha.gov.sa |
DEP-024 Fibre links for the traffic cameras | Fibre Optic Network ExpansionProject | Intelligent Traffic Monitoring SystemProject | Service | 2027-06-30 | 60 days | 33 days | — | At risk | Eng. Yasser M. Al-ZahraniEng. Yasser M. Al-ZahraniDirector, CybersecurityP-026y.alzahrani@alwaha.gov.sa |
DEP-025 Network for the operations centre | Fibre Optic Network ExpansionProject | Smart City Integrated Operations CentreProject | Service | 2027-09-30 | 90 days | 33 days | — | On track | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@alwaha.gov.sa |
DEP-026 Lighting control system feed | Smart Street LightingProject | Smart City Integrated Operations CentreProject | Data | 2027-06-30 | 60 days | 45 days | — | At risk | Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Utilities & Public ServicesP-021w.aljuhani@alwaha.gov.sa |
DEP-028 Environmental operating permit | National Center for Environmental ComplianceExternal entity | Plant trial operationTask | Approval | 2026-12-31 | 0 days | 0 days | — | On track | Eng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & EnvironmentP-028m.alotaibi@alwaha.gov.sa |