Portfolio · PF-CAP

Capital Projects Portfolio

Off track

Government buildings, public facilities and flagship urban projects.

What-if scenarios
Approved budget
SAR 1.3B

incl. SAR 46M unallocated reserve

Actual spend
SAR 658.2M

⁦49%⁩ of budget

EAC
SAR 1.5B+9.9%

Estimate at completion

Expected value
SAR 1.9B

⁦1%⁩ realised

Health score
52−9

was ⁦61⁩ in May

Manager

Eng. Abdulrahman S. Al-Harbi

Deputy, Capital Projects

Owner

Eng. Turki A. Al-Anazi

VP, Projects & Infrastructure

AI insight

⁦3⁩ projects in this portfolio are pulling its health down

Most of it comes from “Government Offices Complex” (SPI ⁦0.70⁩) and “Waterfront Rehabilitation” (SPI ⁦0.78⁩). Fixing those two lifts the portfolio towards ⁦61⁩ within two quarters.

Confidence⁦81%⁩

Portfolio health & performance

The health score from eight weighted dimensions (§61), and the schedule and cost indices over six months.

Health-score breakdown

Score × weight = points

52Off track
DimensionScoreWeightPoints
Schedule42⁦20%⁩8.4
Cost50⁦20%⁩10.0
Risk30⁦15%⁩4.5
Scope64⁦10%⁩6.4
Quality75⁦10%⁩7.5
Resources58⁦10%⁩5.8
Stakeholders60⁦5%⁩3.0
Benefits64⁦10%⁩6.4
Total52

Health-score trend

May – October 2026

6152

Financial & schedule performance

May – October 2026

Both indices over time

  • Schedule performance index
  • Cost performance index

Portfolio project map

§133 — risk across, strategic value up, bubble size by budget. Click a bubble for a quick look at the project.

Portfolio project map

  • At risk
  • Off track
  • Critical
  • On hold
Approved budget · SAR 640M

Funding priority order

Rank the projects for funding; your order is kept and goes to the 2027 planning cycle.

  1. 1Government Offices ComplexPRJ-2026-007·Priority score 81Critical
  2. 2Waterfront RehabilitationPRJ-2026-006·Priority score 79Off track
  3. 3Al-Waha Central ParkPRJ-2026-019·Priority score 73At risk
  4. 4Regional Emergency & Safety CentrePRJ-2026-033·Priority score 61On hold

Portfolio priorities 2026–2027

  • Stop the schedule bleed on the Government Offices ComplexSPI at 0.70 and the contractor’s claims are open before the steering committee.
  • End government leases by 2028The portfolio’s largest return — recurring annual lease savings.
  • Hand over the waterfront before winter 2027A public commitment to residents and investors.

Objectives & KPIs

Why the portfolio exists: the strategic objectives it serves and the KPIs its projects move.

Budget & value

Where the budget goes, why the forecast differs from it, and the value it returns.

From approved budget to estimate at completion

Each programme’s gap between its projects’ budget and their forecast

From approved budget to estimate at completion
  • Total
  • Increase
  • Decrease
From approved budget to estimate at completion
CategoryChangeRunning total
Approved budgetSAR 1.3BSAR 1.3B
Unallocated reserve−SAR 46MSAR 1.3B
Government Buildings & Facilities Programme+SAR 140.5MSAR 1.4B
Waterfronts & Urban Landscape Programme+SAR 38.6MSAR 1.5B
Estimate at completionSAR 1.5BSAR 1.5B

Budget use

658.2M/ 1.3B133.1Mprojected overrun(⁦9.9%⁩)
Actual spend
658.2M
Committed
1B
Approved budget
1.3B
Estimate at completion
1.5B

Expected-value mix

Expected-value mix

SAR 1.9B

Expected value

  • Cost savingSAR 874M⁦46%⁩
  • Beneficiary satisfactionSAR 570M⁦30%⁩
  • Sustainability (ESG)SAR 266M⁦14%⁩
  • RevenueSAR 190M⁦10%⁩
Expected-value mix
CategoryValueShare
Cost savingSAR 874M⁦46%⁩
Beneficiary satisfactionSAR 570M⁦30%⁩
Sustainability (ESG)SAR 266M⁦14%⁩
RevenueSAR 190M⁦10%⁩
TotalSAR 1.9B⁦100%⁩

SAR 21.5M

Expected value SAR 1.9B

⁦34%⁩ of what was planned by today

Programmes & projects

A programme’s performance is computed from its projects (§6). Click a project for a quick look.

⁦4⁩ results
Export CSV
Government Offices ComplexPRJ-2026-007PG-057ExecutionCritical⁦57%⁩640M780.5M⁦+22.0%⁩0.70Schedule performance index · 0.700.82Cost performance index · 0.82Risk score · Weak
Waterfront RehabilitationPRJ-2026-006PG-067ExecutionOff track⁦39%⁩286M321.3M⁦+12.4%⁩0.78Schedule performance index · 0.780.89Cost performance index · 0.89Risk score · Weak
Regional Emergency & Safety CentrePRJ-2026-033PG-054PlanningOn hold⁦2%⁩210M210M⁦0.0%⁩1.00Schedule performance index · 1.001.00Cost performance index · 1.00Risk score · Weak
Al-Waha Central ParkPRJ-2026-019PG-067ExecutionAt risk⁦52%⁩158M161.2M⁦+2.0%⁩0.93Schedule performance index · 0.930.98Cost performance index · 0.98Risk score · Good
Total · 41.3B1.5B
⁦1⁩–⁦4⁩ of ⁦4⁩

Portfolio risks

Open threats across the portfolio’s projects. Click a cell on the map to filter the list.

Latest on this portfolio

Yesterday27 October 2026

  1. Approval: Bid Evaluation & Award Committee Approved DEC-2026-043Replacement bank guarantee for the waterfront contractor accepted

    2026-10-27 10:00

22 October 2026

  1. Rejection: PMO Committee Hold DEC-2026-041Regional Emergency Centre on hold until the land is handed over

    2026-10-22 10:00

21 October 2026

13 October 2026

  1. Approval: Projects Steering Committee Approved DEC-2026-037Government Offices Complex claims referred to dispute resolution

    2026-10-13 10:00

8 September 2026

  1. Rejection: Executive Committee Cancel DEC-2026-044Temporary office-building option cancelled in favour of the complex

    2026-09-08 10:00

21 April 2026

  1. Approval: Change Control Board Approved DEC-2026-033Variation to re-route the marina promenade approved