PRJ-2026-006Off track7ExecutionConstruction

Waterfront Rehabilitation

Remove from watchlist

6.5 km of waterfront rebuilt with a promenade, green space, leisure and investment plots.

Early warning: ⁦84%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SAR 286M

Actual cost

SAR 125.3M

⁦44%⁩ of budget

Progress

⁦39%⁩

Planned ⁦50%⁩

Estimate at completion

SAR 321.3M

SAR +35.3M

SPI · CPI

0.78Schedule performance index · 0.780.89Cost performance index · 0.89

Forecast finish

⁦2027-07-04⁩

95 days behind baseline

ExecutionPhase ⁦7⁩ of ⁦11⁩

Next gate:Monitoring & Control19 November 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate15 March 2024Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionConditional goDate3 July 2024Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate1 September 2024Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate18 October 2024Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate15 November 2024Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionGoDate30 January 2025Execution · Current phaseExecution · Current phase
  8. Gate into «Monitoring & Control»DecisionNot held yetDate19 November 2026Monitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Project health across eight dimensions

A weighted index, not just percent complete; each dimension leads to the tab that explains it.

Index over the last six reports

−21

May to October 2026

No material change in the health dimensions over the period.

AI insight

⁦84%⁩ chance of a further slip within ⁦45⁩ days

From the SPI trend (⁦0.78⁩), the task closure rate and the open risks, the early-warning engine expects another slip unless the resource gap is closed.

Confidence⁦82%⁩

Copilot summary

Generated from the live project data

The project is behind plan: ⁦39%⁩ done against ⁦50%⁩ planned.

SPI ⁦0.78⁩, CPI ⁦0.89⁩.

Progress & earned value

⁦3⁩ of ⁦5⁩ milestones complete

Earned-value curve

Planned, earned and actual to the data date, cumulative, with the forecast cost tail

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Budget & commitments

Commitments are ⁦89%⁩ of budget

125.3M/ 286M35.3Mprojected overrun(⁦12.4%⁩)
Actual spend
125.3M
Committed
254M
Approved budget
286M
Estimate at completion
321.3M

Next milestones

  • Provisional acceptance⁦2027-03-27⁩was ⁦2027-01-15⁩Late
  • Closure⁦2027-07-04⁩was ⁦2027-03-31⁩Late

Waiting on someone

⁦0⁩ approvals and ⁦1⁩ open actions on this project

Approvals & requests

From «My actions» for this project

  • No approvals pending

Actions

⁦1⁩ open

  • Chase the marine-works permitsEng. Fahad T. Al-SulamiIn 6 days2026-11-0323 Jumada I 1448 AHHigh

Risks & issues

2 open risks, exposure SAR 28.5M

Risk map

Probability
5Probability: Almost certain · Impact: NegligibleLow · Score ⁦5⁩Probability: Almost certain · Impact: MinorMedium · Score ⁦10⁩Probability: Almost certain · Impact: ModerateHigh · Score ⁦15⁩Probability: Almost certain · Impact: MajorCritical · Score ⁦20⁩Probability: Almost certain · Impact: SevereCritical · Score ⁦25⁩
4Probability: Likely · Impact: NegligibleLow · Score ⁦4⁩Probability: Likely · Impact: MinorMedium · Score ⁦8⁩1Probability: Likely · Impact: ModerateMedium · Score ⁦12⁩RSK-0025Late marine-works permits from the competent authorities1Probability: Likely · Impact: MajorHigh · Score ⁦16⁩RSK-0024Marine protection costs up after the hydrographic surveyProbability: Likely · Impact: SevereCritical · Score ⁦20⁩
3Probability: Possible · Impact: NegligibleLow · Score ⁦3⁩Probability: Possible · Impact: MinorLow · Score ⁦6⁩Probability: Possible · Impact: ModerateMedium · Score ⁦9⁩Probability: Possible · Impact: MajorMedium · Score ⁦12⁩Probability: Possible · Impact: SevereHigh · Score ⁦15⁩
2Probability: Unlikely · Impact: NegligibleLow · Score ⁦2⁩Probability: Unlikely · Impact: MinorLow · Score ⁦4⁩Probability: Unlikely · Impact: ModerateLow · Score ⁦6⁩Probability: Unlikely · Impact: MajorMedium · Score ⁦8⁩Probability: Unlikely · Impact: SevereMedium · Score ⁦10⁩
1Probability: Rare · Impact: NegligibleLow · Score ⁦1⁩Probability: Rare · Impact: MinorLow · Score ⁦2⁩Probability: Rare · Impact: ModerateLow · Score ⁦3⁩Probability: Rare · Impact: MajorLow · Score ⁦4⁩Probability: Rare · Impact: SevereLow · Score ⁦5⁩
12345

Impact

  • Critical0
  • High1
  • Medium1
  • Low0

Deliverables

⁦2⁩ of ⁦4⁩ approved

  • Project management planDLV-006-1 · V1Eng. Fahad T. Al-Sulami⁦2024-10-09⁩2024-10-096 Rabiʻ II 1446 AHApproved
  • Main deliverable — stage 1DLV-006-2 · V1Eng. Abdulrahman S. Al-Harbi⁦2025-12-25⁩2025-12-255 Rajab 1447 AHApproved
  • Main deliverable — final stageDLV-006-3 · V1Eng. Abdulrahman S. Al-HarbiIn 22 days2026-11-199 Jumada II 1448 AHIn progress
  • Final reportDLV-006-4 · V0Eng. Abdulrahman S. Al-HarbiIn 154 days2027-03-3123 Shawwal 1448 AHDraft

Team, contracts & documents

Team

2 members

Eng. Fahad T. Al-Sulami · Director, Urban DevelopmentEng. Abdulrahman S. Al-Harbi · Deputy, Capital Projects
  • Eng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiDirector, Urban DevelopmentProject managerP-023f.alsulami@alwaha.gov.sa⁦55%⁩
  • Eng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDeputy, Capital ProjectsProject sponsorP-014ab.alharbi@alwaha.gov.sa⁦25%⁩
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close