Jeddah Administrative Courts Complex
Remove from watchlistA new complex for the Jeddah administrative and appeal courts, with 40 courtrooms and offices for the judicial circuits.
Budget (BAC)
Actual cost
44% of budget
Progress
Planned 50%
Estimate at completion
SAR +35.3M
SPI · CPI
Forecast finish
95 days behind baseline
ExecutionPhase 7 of 11
Next gate:Monitoring & Control19 November 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate15 March 2024Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionConditional goDate3 July 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate1 September 2024Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionGoDate18 October 2024Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate15 November 2024Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionGoDate30 January 2025Execution · Current phaseExecution · Current phase
- Gate into «Monitoring & Control»DecisionNot held yetDate19 November 2026Monitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Scope statement
What the project delivers, what it does not, and when a deliverable counts as accepted.
A new complex for the Jeddah administrative and appeal courts, with 40 courtrooms and offices for the judicial circuits.
In scope
- A new complex for the Jeddah administrative and appeal courts, with 40 courtrooms and offices for the judicial circuits.
- Saudi Building Code compliance
- Consultant-approved drawings
Out of scope
- Operation and maintenance after the warranty period
- Work outside the approved site or system boundary
Acceptance criteria
- Main deliverable — stage 1Meets the approved specification, signed off by the business owner
- Main deliverable — final stageMeets the approved specification, signed off by the business owner
Scope baseline
Every approved change creates a new baseline
- 1
SB-1Current2024-10-13
Baseline approved at the planning gate
Budget286MFinish2027-03-31
Requirements register
6 requirements of five kinds, with the trace status of each
By type
- Business1
- Functional1
- Technical1
- Regulatory2
- Security1
Fully traced
100%
6/6 · linked to a deliverable, task and test
Test passed
33%
2/6 · test result is a pass
Accepted
33%
2/6 · signed off by the business owner
Display options
| REQ-006-01 | A building ready for hearings | Business | Must | In progress | Eng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDirector General, Engineering ProjectsP-014ab.alharbi@bog.gov.sa | SB-1 | |
| REQ-006-02 | Match the approved drawings | Technical | Must | In progress | Eng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiDirector, Design & Fit-outP-023f.alsulami@bog.gov.sa | SB-1 | |
| REQ-006-03 | Smart building systems | Functional | Must | Approved | Eng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDirector General, Engineering ProjectsP-014ab.alharbi@bog.gov.sa | SB-1 | |
| REQ-006-04 | Saudi Building Code | Regulatory | Could | Approved | Eng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiDirector, Design & Fit-outP-023f.alsulami@bog.gov.sa | SB-1 | |
| REQ-006-05 | Health & safety | Regulatory | Should | In progress | Eng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDirector General, Engineering ProjectsP-014ab.alharbi@bog.gov.sa | SB-1 | |
| REQ-006-06 | CCTV and access control | Security | Should | In progress | Eng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiDirector, Design & Fit-outP-023f.alsulami@bog.gov.sa | SB-1 |
Traceability matrix
Requirement → deliverable → task → test → acceptance. No requirement has a gap.