Board of GrievancesMunjaz10My actionsNotifications
PRJ-2026-006Off track7ExecutionConstruction

Jeddah Administrative Courts Complex

Remove from watchlist

A new complex for the Jeddah administrative and appeal courts, with 40 courtrooms and offices for the judicial circuits.

Early warning: ⁦84%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SAR 286M

Actual cost

SAR 125.3M

⁦44%⁩ of budget

Progress

⁦39%⁩

Planned ⁦50%⁩

Estimate at completion

SAR 321.3M

SAR +35.3M

SPI · CPI

0.78Schedule performance index · 0.780.89Cost performance index · 0.89

Forecast finish

⁦2027-07-04⁩

95 days behind baseline

ExecutionPhase ⁦7⁩ of ⁦11⁩

Next gate:Monitoring & Control19 November 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate15 March 2024Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionConditional goDate3 July 2024Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate1 September 2024Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate18 October 2024Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate15 November 2024Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionGoDate30 January 2025Execution · Current phaseExecution · Current phase
  8. Gate into «Monitoring & Control»DecisionNot held yetDate19 November 2026Monitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Baselines

The original, the approved revised and the working baseline, with any two versions compared on dates and cost. An approved baseline is locked and moves only through a change request; every version is kept.

  1. Original

    Original baseline

    v1.0Approved & lockedVersion A
    Finish
    ⁦2027-03-31⁩
    Budget
    SAR 276.4M
    ⁦17⁩ activities

    Approved with the project plan at the planning gate.

    Approved ⁦2024-09-01⁩ · by Eng. Turki A. Al-Anazi

  2. Working

    Working baseline

    v2.0-draftWorking draftVersion B
    Finish
    ⁦2027-06-30⁩
    ⁦+91⁩ days
    Budget
    SAR 308.5M
    ⁦17⁩ activities

    Follows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.

    Created ⁦2026-10-28⁩ · by Eng. Fahad T. Al-Sulami

    Edit in the schedule

Compare two versions

What changed from version A to version B

Finish

⁦2027-03-31⁩⁦2027-06-30⁩

⁦+91⁩ days

Budget

SAR 276.4MSAR 308.5M

⁦+32.10⁩ SAR M

Milestones moved

5 / 5

Milestones: A to B

Each line starts at the milestone’s date in A and ends at its date in B

2025-072026-012026-072027-012027-07
  • Project plan approved⁦+172⁩
  • Designs approved⁦+303⁩
  • Build complete⁦+294⁩
  • Testing & acceptance complete⁦+172⁩
  • Final handover⁦+91⁩

Version AVersion B

Cost by WBS element

Difference in SAR millions from A to B

  • 1Management & governance⁦+2.62⁩
  • 2Design & permits⁦+5.25⁩
  • 3Civil works⁦+13.25⁩
  • 4MEP works⁦+16.53⁩
  • 5Handover⁦+7.71⁩

Version history

Every saved version with its reason and reference

  1. Working baselinev2.0-draftWorking draftFollows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.⁦2026-10-28⁩by Eng. Fahad T. Al-Sulami
  2. Original baselinev1.0Approved & lockedApproved with the project plan at the planning gate.⁦2024-09-01⁩by Eng. Turki A. Al-Anazi
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close