Jeddah Administrative Courts Complex

Remove from watchlist

A new complex for the Jeddah administrative and appeal courts, with 40 courtrooms and offices for the judicial circuits.

Early warning: ⁦84%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SAR 286M

Actual cost

SAR 125.3M

⁦44%⁩ of budget

Progress

⁦39%⁩

Planned ⁦50%⁩

Estimate at completion

SAR 321.3M

SAR +35.3M

SPI · CPI

0.78Schedule performance index · 0.780.89Cost performance index · 0.89

Forecast finish

⁦2027-07-04⁩

95 days behind baseline

ExecutionPhase ⁦7⁩ of ⁦11⁩

Next gate:Monitoring & Control19 November 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate15 March 2024Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionConditional goDate3 July 2024Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate1 September 2024Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate18 October 2024Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate15 November 2024Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionGoDate30 January 2025Execution · Current phaseExecution · Current phase
  8. Gate into «Monitoring & Control»DecisionNot held yetDate19 November 2026Monitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Board of Grievances

Project charter

Jeddah Administrative Courts Complex

APPROVEDV2Approved ⁦2024-08-30⁩

1Project identity

Project name
Jeddah Administrative Courts Complex
Project code
PRJ-2026-006
Sponsor
Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziAssistant President, Projects & FacilitiesP-010t.alanazi@bog.gov.sa
Project manager
Eng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiDirector, Design & Fit-outP-023f.alsulami@bog.gov.sa
Business owner
Eng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDirector General, Engineering ProjectsP-014ab.alharbi@bog.gov.sa
Portfolio & programme
Administrative Court Premises PortfolioRegional Court Premises Programme
Type & methodology
Construction · Construction
Current phase
7Execution

2Background & rationale

A new complex for the Jeddah administrative and appeal courts, with ⁦40⁩ courtrooms and offices for the judicial circuits.

3Objectives

  1. 1Raise the quality of beneficiary service and the courthouse experience
  2. 2Deliver innovative judicial services

4Scope

In scope

  • A new complex for the Jeddah administrative and appeal courts, with ⁦40⁩ courtrooms and offices for the judicial circuits.
  • Saudi Building Code compliance
  • Consultant-approved drawings

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

5High-level requirements

  1. 1Saudi Building Code compliance
  2. 2Consultant-approved drawings
  3. 3Health & safety requirements

6Deliverables

1Project management plan⁦2024-10-09⁩
2Main deliverable — stage 1⁦2025-12-25⁩
3Main deliverable — final stage⁦2026-11-19⁩
4Final report⁦2027-03-31⁩

7Key milestones

  1. Charter approved⁦2024-08-30⁩
  2. Contract signed⁦2025-01-30⁩
  3. 50% of works complete⁦2025-12-25⁩
  4. Provisional acceptance⁦2027-01-15⁩
  5. Closure⁦2027-03-31⁩

8Budget

  • Main contract⁦72.0%⁩205.9M
  • Supervision & consulting⁦14.0%⁩40.1M
  • Internal team⁦9.0%⁩25.7M
  • Contingency reserve (⁦5%⁩)⁦5.0%⁩14.3M
The owning sector’s approved budgetTotal286M

9Timeline

Start
2024-09-0128 Safar 1446 AH
Baseline finish
2027-03-3123 Shawwal 1448 AH
Duration
⁦31⁩ months

10Key risks

  • HighGround-improvement costs up after the geotechnical survey
  • MediumLate building permits from the Jeddah municipality

11Constraints

  • Stay within the approved budget
  • Comply with the Government Tenders & Procurement Law

12Assumptions

  • Named internal staff available throughout
  • Approvals land within workflow SLAs

13Stakeholders

  • Project sponsorDecisions and funding
  • Business ownerAccepts deliverables, owns benefits
  • Projects Follow-up Office (EPMO)Governance and compliance

14Success criteria

  1. 1Delivered within the approved budget
  2. 2On the approved date ⁦±5%⁩
  3. 3Target benefits within ⁦12⁩ months

15Governance structure

  • Change Control BoardApproves scope, cost and schedule changesWeekly
  • EPMO CommitteeMethodology compliance, data quality, stage gatesFortnightly
  • Project management teamDay-to-day control, risks, issues, weekly statusWeekly
Version V2 · ⁦4⁩ of ⁦4⁩ signaturesInternal — not for circulation outside the Board
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close