PRJ-2026-006Off track7ExecutionConstruction

Jeddah Administrative Courts Complex

Remove from watchlist

A new complex for the Jeddah administrative and appeal courts, with 40 courtrooms and offices for the judicial circuits.

Early warning: ⁦84%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SAR 286M

Actual cost

SAR 125.3M

⁦44%⁩ of budget

Progress

⁦39%⁩

Planned ⁦50%⁩

Estimate at completion

SAR 321.3M

SAR +35.3M

SPI · CPI

0.78Schedule performance index · 0.780.89Cost performance index · 0.89

Forecast finish

⁦2027-07-04⁩

95 days behind baseline

ExecutionPhase ⁦7⁩ of ⁦11⁩

Next gate:Monitoring & Control19 November 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate15 March 2024Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionConditional goDate3 July 2024Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate1 September 2024Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate18 October 2024Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate15 November 2024Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionGoDate30 January 2025Execution · Current phaseExecution · Current phase
  8. Gate into «Monitoring & Control»DecisionNot held yetDate19 November 2026Monitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Milestones

Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.

Milestone runway

2Achieved
0On track
2At risk
1Late
Average delay206 days
Apr 25Jul 25Oct 25Jan 26Apr 26Jul 26Oct 26Jan 27Apr 27Jul 27
Contractual
Build completePlanned: ⁦2026-03-23⁩Forecast / actual: ⁦2027-01-11⁩Delay: 294 daysG3 +294
Executive
Project plan approvedPlanned: ⁦2025-03-14⁩Forecast / actual: ⁦2025-09-02⁩Delay: 172 daysG1 +172
Payment
Final handoverPlanned: ⁦2027-03-31⁩Forecast / actual: ⁦2027-06-30⁩Delay: 91 daysG5 +91
Regulatory
Testing & acceptance completePlanned: ⁦2026-11-02⁩Forecast / actual: ⁦2027-04-23⁩Delay: 172 daysG4 +172
Project
Designs approvedPlanned: ⁦2025-08-11⁩Forecast / actual: ⁦2026-06-10⁩Delay: 303 daysG2 +303

The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay

Milestone register

⁦5⁩ results
Export CSV
Project plan approvedMS-G1Executive⁦2025-03-14⁩⁦2025-09-02⁩⁦+172⁩ daysEng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiDirector, Design & Fit-outP-023f.alsulami@bog.gov.saAchieved1Approved
Designs approvedMS-G2Project⁦2025-08-11⁩⁦2026-06-10⁩⁦+303⁩ daysEng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiDirector, Design & Fit-outP-023f.alsulami@bog.gov.saAchieved1Approved
Build completeMS-G3Contractual⁦2026-03-23⁩⁦2027-01-11⁩⁦+294⁩ daysEng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiDirector, Design & Fit-outP-023f.alsulami@bog.gov.saLate0Not requested
Testing & acceptance completeMS-G4Regulatory⁦2026-11-02⁩⁦2027-04-23⁩⁦+172⁩ daysEng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiDirector, Design & Fit-outP-023f.alsulami@bog.gov.saAt risk0Not requested
Final handoverMS-G5Payment⁦2027-03-31⁩⁦2027-06-30⁩⁦+91⁩ daysEng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiDirector, Design & Fit-outP-023f.alsulami@bog.gov.saAt risk0Not requested
⁦1⁩–⁦5⁩ of ⁦5⁩

Deliverables register

Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.

Deliverable flow

Pick a stage to filter the register
⁦6⁩ results
Export CSV
Deliverable: Project plan & baseline006-D1ApprovedEng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiDirector, Design & Fit-outP-023f.alsulami@bog.gov.saEng. Abdulrahman S. Al-Harbi⁦2024-12-29⁩V1⁦2⁩ of ⁦2⁩
Deliverable: Monitoring & reporting006-D2ApprovedEng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDirector General, Engineering ProjectsP-014ab.alharbi@bog.gov.saEng. Abdulrahman S. Al-Harbi⁦2025-03-14⁩V1⁦2⁩ of ⁦2⁩
Deliverable: Detailed design006-D3ApprovedEng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDirector General, Engineering ProjectsP-014ab.alharbi@bog.gov.saEng. Abdulrahman S. Al-Harbi⁦2025-05-28⁩V1⁦2⁩ of ⁦2⁩
Deliverable: Permits & approvals006-D4ApprovedEng. Turki A. Al-AnaziEng. Turki A. Al-AnaziAssistant President, Projects & FacilitiesP-010t.alanazi@bog.gov.saEng. Abdulrahman S. Al-Harbi⁦2025-08-11⁩V1⁦2⁩ of ⁦2⁩
Deliverable: Site works & excavation006-D5ApprovedEng. Turki A. Al-AnaziEng. Turki A. Al-AnaziAssistant President, Projects & FacilitiesP-010t.alanazi@bog.gov.saEng. Abdulrahman S. Al-Harbi⁦2025-10-24⁩V1⁦2⁩ of ⁦2⁩
Deliverable: Structure006-D6Under reviewEng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiDirector, Design & Fit-outP-023f.alsulami@bog.gov.saEng. Abdulrahman S. Al-Harbi⁦2026-01-07⁩V1⁦1⁩ of ⁦2⁩