Jeddah Administrative Courts Complex
Remove from watchlistA new complex for the Jeddah administrative and appeal courts, with 40 courtrooms and offices for the judicial circuits.
Budget (BAC)
Actual cost
44% of budget
Progress
Planned 50%
Estimate at completion
SAR +35.3M
SPI · CPI
Forecast finish
95 days behind baseline
ExecutionPhase 7 of 11
Next gate:Monitoring & Control19 November 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate15 March 2024Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionConditional goDate3 July 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate1 September 2024Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionGoDate18 October 2024Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate15 November 2024Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionGoDate30 January 2025Execution · Current phaseExecution · Current phase
- Gate into «Monitoring & Control»DecisionNot held yetDate19 November 2026Monitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2025-03-14 | 2025-09-02 | +172 days | Eng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiDirector, Design & Fit-outP-023f.alsulami@bog.gov.sa | Achieved | 1 | Approved |
| Designs approvedMS-G2 | Project | 2025-08-11 | 2026-06-10 | +303 days | Eng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiDirector, Design & Fit-outP-023f.alsulami@bog.gov.sa | Achieved | 1 | Approved |
| Build completeMS-G3 | Contractual | 2026-03-23 | 2027-01-11 | +294 days | Eng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiDirector, Design & Fit-outP-023f.alsulami@bog.gov.sa | Late | 0 | Not requested |
| Testing & acceptance completeMS-G4 | Regulatory | 2026-11-02 | 2027-04-23 | +172 days | Eng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiDirector, Design & Fit-outP-023f.alsulami@bog.gov.sa | At risk | 0 | Not requested |
| Final handoverMS-G5 | Payment | 2027-03-31 | 2027-06-30 | +91 days | Eng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiDirector, Design & Fit-outP-023f.alsulami@bog.gov.sa | At risk | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Deliverable flow
Display options
| Deliverable: Project plan & baseline006-D1 | Approved | Eng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiDirector, Design & Fit-outP-023f.alsulami@bog.gov.sa | Eng. Abdulrahman S. Al-Harbi | 2024-12-29 | V1 | 2 of 2 |
| Deliverable: Monitoring & reporting006-D2 | Approved | Eng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDirector General, Engineering ProjectsP-014ab.alharbi@bog.gov.sa | Eng. Abdulrahman S. Al-Harbi | 2025-03-14 | V1 | 2 of 2 |
| Deliverable: Detailed design006-D3 | Approved | Eng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDirector General, Engineering ProjectsP-014ab.alharbi@bog.gov.sa | Eng. Abdulrahman S. Al-Harbi | 2025-05-28 | V1 | 2 of 2 |
| Deliverable: Permits & approvals006-D4 | Approved | Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziAssistant President, Projects & FacilitiesP-010t.alanazi@bog.gov.sa | Eng. Abdulrahman S. Al-Harbi | 2025-08-11 | V1 | 2 of 2 |
| Deliverable: Site works & excavation006-D5 | Approved | Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziAssistant President, Projects & FacilitiesP-010t.alanazi@bog.gov.sa | Eng. Abdulrahman S. Al-Harbi | 2025-10-24 | V1 | 2 of 2 |
| Deliverable: Structure006-D6 | Under review | Eng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiDirector, Design & Fit-outP-023f.alsulami@bog.gov.sa | Eng. Abdulrahman S. Al-Harbi | 2026-01-07 | V1 | 1 of 2 |