Jeddah Administrative Courts Complex
Remove from watchlistA new complex for the Jeddah administrative and appeal courts, with 40 courtrooms and offices for the judicial circuits.
Budget (BAC)
Actual cost
44% of budget
Progress
Planned 50%
Estimate at completion
SAR +35.3M
SPI · CPI
Forecast finish
95 days behind baseline
ExecutionPhase 7 of 11
Next gate:Monitoring & Control19 November 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate15 March 2024Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionConditional goDate3 July 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate1 September 2024Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionGoDate18 October 2024Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate15 November 2024Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionGoDate30 January 2025Execution · Current phaseExecution · Current phase
- Gate into «Monitoring & Control»DecisionNot held yetDate19 November 2026Monitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Project lifecycle and its gates
Current phase: Execution. Pick a gate on the track to review it.
- Gate into «Feasibility»DecisionGoDate15 March 2024All criteria and required documents met.IdeaComplete
- Gate into «Initiation»DecisionConditional goDate3 July 2024Mandatory criteria met, with points to close during the next phase.FeasibilityComplete
- Gate into «Planning»DecisionGoDate1 September 2024All criteria and required documents met.InitiationComplete
- Gate into «Approval»DecisionGoDate18 October 2024All criteria and required documents met.PlanningComplete
- Gate into «Procurement»DecisionGoDate15 November 2024All criteria and required documents met.ApprovalComplete
- Gate into «Execution»DecisionGoDate30 January 2025All criteria and required documents met.ProcurementComplete
- Gate into «Monitoring & Control»DecisionNot held yetDate19 November 2026ExecutionCurrent phaseCurrent phase
- Gate into «Handover»DecisionNot held yet8Monitoring & ControlNot started
- Gate into «Closure»DecisionNot held yet9HandoverNot started
- Gate into «Benefits Realization»DecisionNot held yet10ClosureNot started
- 11Benefits RealizationNot started
Operational readiness gate — into hypercare & monitoring
Gate readiness
Enough for a conditional go only
Automated control: no move until the criteria are met
- 4 mandatory checklist items open
- 1 required document not approved
- 2 mandatory criteria under 70 points
- Weighted score 67 under the pass mark 75
Checklist
3 of 7 done
- All in-scope services builtMandatory
- User acceptance testing passedMandatory
- Penetration test passed — no critical/high findingsMandatory
- Data migrated and reconciledMandatory
- Operations & support plan, SLAMandatory
- Users trained — judges, clerks and staff
- Launch rollback plan
Required documents
3 of 4 approved
- UAT reportNot submitted
- Penetration test reportApproved · V1
- Operations & support planApproved · V1
- Data migration reconciliationApproved · V1
Criteria and score
Go from 75, conditional from 60; a mandatory criterion is met from 70.
Deliverables completeweight 30%Not met
Awaiting evidence from the project team.
Quality & securityweight 30%Not met
Awaiting evidence from the project team.
Operations & support readinessweight 20%Met
Awaiting evidence from the project team.
User & change readinessweight 20%
Awaiting evidence from the project team.
Approvers
Projects Steering Committee
- Dr. Abdullah S. Al-QahtaniSteering Committee chairVote pending
- Eng. Turki A. Al-AnaziProject sponsorVote pending
- Dr. Noura M. Al-OtaibiEPMO directorVote pending
- Eng. Abdulrahman S. Al-HarbiBusiness ownerVote pending