CR-2026-007Waterfront Rehabilitation
Additional marine protection after the hydrographic survey
Justification and the cost, schedule and risk impact, with a recommendation.
Impact analysis
Before and after — as it will show in the baseline if approved
Cost
+SAR 22.5MCurrent budgetSAR 286M
After the changeSAR 308.5M
+7.9%
Schedule
+75 d- Baseline finish2027-03-31
- New finish2027-06-14
Risk
−10Treats the project’s top risk
Benefits
+5%A 50-year design life for the waterfront
+5% of expected benefits
Reason for change
The hydrographic survey showed worse shoreline erosion
Business justification
Without extra protection the promenade is damaged within two seasons
PMO recommendation
Approve with conditionsImpact analysis in progress at the PMO
Approval workflow
Submitted
Eng. Fahad T. Al-Sulami
Done2026-10-06
PM review
Eng. Fahad T. Al-Sulami
Done2026-10-07
- 3
Impact analysis
Karim Haddad
Now2026-10-11
- 4
Board decision
Dr. Mohammed I. Al-Subaie
Later2026-10-29
- 5
Sponsor sign-off
Eng. Turki A. Al-Anazi
Later
- 6
Baseline updated
Eng. Fahad T. Al-Sulami
Later
Board vote
Members vote before or during the session; the decision is taken once quorum is met
- Dr. Mohammed I. Al-SubaieVP, Planning & StrategyDr. Mohammed I. Al-SubaieVP, Planning & StrategyP-009m.alsubaie@alwaha.gov.saChairNot voted
- Dr. Noura M. Al-OtaibiDirector, Enterprise PMODr. Noura M. Al-OtaibiDirector, Enterprise PMOP-002n.alotaibi@alwaha.gov.saYouNot voted
- Khalid N. Al-MutairiSenior Finance & Contracts SpecialistKhalid N. Al-MutairiSenior Finance & Contracts SpecialistP-007k.almutairi@alwaha.gov.saNot voted
- Munirah A. Al-KhalidiDeputy, Financial AffairsMunirah A. Al-KhalidiDeputy, Financial AffairsP-018m.alkhalidi@alwaha.gov.saNot voted
- Eng. Asma S. Al-HamdanEnterprise ArchitectEng. Asma S. Al-HamdanEnterprise ArchitectP-031a.alhamdan@alwaha.gov.saNot voted
- Eng. Ibrahim A. Al-GhamdiDirector, Engineering SupervisionEng. Ibrahim A. Al-GhamdiDirector, Engineering SupervisionP-036i.alghamdi@alwaha.gov.saNot voted
- Approve0
- Approve with conditions0
- Reject0
- Abstain0
4 short of quorum · Awaiting the board’s decision in session 42