RSK-0024Jeddah Administrative Courts Complex

Ground-improvement costs up after the geotechnical survey

16HighEscalated

A risk's detail, response, contingency and residual risk.

Risk statement

From cause to event to impact — with the preventive controls before the event and the contingency after it

Cause

The geotechnical survey found softer soil and higher groundwater than the design study assumed

Preventive controls

  • A change request for the extra ground improvement
  • Value engineering of the foundation solution with the consultant

1 / 2

Event

Ground-improvement costs up after the geotechnical survey

16HighTrigger

The change request is not approved at the next CCB session

Contingency

Treat the ground in two stages, the courtroom block first

Impact

SAR 22.5M of extra ground improvement and a 75-day extension

SAR 22.5M

Assessment

The level before and after the response

Inherent

5
4
3
2
1
1
2
3
4
5
16High

Residual

5
4
3
2
1
1
2
3
4
5
6Low

Exposure

SAR 22.5M

Residual

⁦63⁩% off the score

Score trend

Last six months

  • Score
  • Target residual

Escalation path

Escalation engine: a high risk unreviewed for 10 days notifies the PM, 15 the programme manager, 20 the EPMO director

Last reviewed 6 days ago

  1. Project manager

    Eng. Fahad T. Al-Sulami

    Currently followed up here
  2. Programme manager

    Current level

    Eng. Fahad T. Al-Sulami

    Automatically at 15 days unreviewed · in 9 days
  3. 3

    EPMO director

    Dr. Noura M. Al-Otaibi

    Automatically at 20 days unreviewed · in 14 days
  4. 4

    Executive committee

    Dr. Abdullah S. Al-Qahtani

    By the EPMO director’s decision

Mitigation plan

Each action with its owner and date — tick it off when complete

⁦1⁩ of ⁦2⁩ done
  • A change request for the extra ground improvement

    Eng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiDirector, Design & Fit-outP-023f.alsulami@bog.gov.sa
    Done⁦2026-10-06⁩2026-10-0625 Rabiʻ II 1448 AH
  • Value engineering of the foundation solution with the consultant

    Eng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiDirector, Design & Fit-outP-023f.alsulami@bog.gov.sa
    In progressIn 15 days2026-11-122 Jumada II 1448 AH

Trigger

The change request is not approved at the next CCB session

Contingency

Treat the ground in two stages, the courtroom block first