Internal
Kingdom of Saudi Arabia
Board of Grievances
Projects Follow-up Office (EPMO)
- Code
- DOC-0212
- Version
- V1
- Date
- 2026-09-24
Jeddah courts complex geotechnical survey report
Jeddah Administrative Courts Complex
1. Executive summary
This report gives the position of Jeddah Administrative Courts Complex to date: 39% complete against 50% planned, SPI 0.78, CPI 0.89, and an estimate at completion of SAR 321.3M.
- Project
- Jeddah Administrative Courts Complex (PRJ-2026-006)
- Project manager
- Eng. Fahad T. Al-Sulami
- Budget
- SAR 286.0M
- Progress
- 39% actual against 50% planned
- Forecast finish
- 2027-07-04
2. Key findings
- All planned milestones of the period met except one deferred
- Actual spend rose in line with the work done
- Three high risks under treatment, each with a named owner
3. Recommendations & decisions needed
- Approve the proposed treatment of the high risks
- Track the open findings with the vendor weekly
Prepared by
Eng. Fahad T. Al-Sulami
Internal