CR-2026-011Waterfront Rehabilitation

Re-route the promenade at the marina

ScopeApproved

Justification and the cost, schedule and risk impact, with a recommendation.

Impact analysis

Before and after — as it will show in the baseline if approved

Cost

+SAR 9.6M

Current budgetSAR 276.4M

After the changeSAR 286M

+3.5%

Schedule

+⁦20⁩ d
  • Baseline finish2027-03-11
  • New finish2027-03-31

Risk

−3
9Medium6Low

Removes an operational clash

Benefits

+6%

600 m more promenade

⁦+6⁩% of expected benefits

Reason for change

The promenade route clashed with the existing marina

Business justification

Re-routing keeps the marina and adds a viewpoint

PMO recommendation

Approve

The PMO recommends approval

Approval workflow

  1. Submitted

    Eng. Fahad T. Al-Sulami

    Done2026-04-12

  2. PM review

    Eng. Fahad T. Al-Sulami

    Done2026-04-13

  3. Impact analysis

    Karim Haddad

    Done2026-04-17

  4. Board decision

    Dr. Mohammed I. Al-Subaie

    Done2026-04-21

  5. Sponsor sign-off

    Eng. Turki A. Al-Anazi

    Done2026-04-23

  6. Baseline updated

    Eng. Fahad T. Al-Sulami

    Done2026-04-25

Board vote

Members vote before or during the session; the decision is taken once quorum is met

  • Dr. Mohammed I. Al-SubaieVP, Planning & StrategyDr. Mohammed I. Al-SubaieVP, Planning & StrategyP-009m.alsubaie@alwaha.gov.saChairApprove
  • Dr. Noura M. Al-OtaibiDirector, Enterprise PMODr. Noura M. Al-OtaibiDirector, Enterprise PMOP-002n.alotaibi@alwaha.gov.saYouApprove
  • Khalid N. Al-MutairiSenior Finance & Contracts SpecialistKhalid N. Al-MutairiSenior Finance & Contracts SpecialistP-007k.almutairi@alwaha.gov.saApprove
  • Munirah A. Al-KhalidiDeputy, Financial AffairsMunirah A. Al-KhalidiDeputy, Financial AffairsP-018m.alkhalidi@alwaha.gov.saApprove
  • Eng. Asma S. Al-HamdanEnterprise ArchitectEng. Asma S. Al-HamdanEnterprise ArchitectP-031a.alhamdan@alwaha.gov.saApprove
  • Eng. Ibrahim A. Al-GhamdiDirector, Engineering SupervisionEng. Ibrahim A. Al-GhamdiDirector, Engineering SupervisionP-036i.alghamdi@alwaha.gov.saApprove
6/6Quorum met
  • Approve6
  • Approve with conditions0
  • Reject0
  • Abstain0

Decided by the board on 21 April 2026The decision in the log · DEC-2026-033

Baseline

Baseline updated on 25 April 2026