RSK-0025Jeddah Administrative Courts Complex
Late building permits from the Jeddah municipality
A risk's detail, response, contingency and residual risk.
Risk statement
From cause to event to impact — with the preventive controls before the event and the contingency after it
Cause
Updated regulations and several permit authorities (municipalities, Civil Defence)
Preventive controls
- Early contact with the competent authorities
- A compliance checklist before every submission
2 / 2
Event
Late building permits from the Jeddah municipality
A permit application is refused or returned
Contingency
Submit a design alternative that meets the rules
Impact
Late permits and design changes
Assessment
The level before and after the response
Inherent
Residual
Exposure
SAR 6M
Residual
67% off the score
Score trend
Last six months
- Score
- Target residual
Escalation path
Escalation engine: a high risk unreviewed for 10 days notifies the PM, 15 the programme manager, 20 the EPMO director
Last reviewed 6 days ago · Outside the engine — below «high»
Project manager
Current levelEng. Fahad T. Al-Sulami
Currently followed up here- 2
Programme manager
Eng. Fahad T. Al-Sulami
- 3
EPMO director
Dr. Noura M. Al-Otaibi
- 4
Executive committee
Dr. Abdullah S. Al-Qahtani
By the EPMO director’s decision
Mitigation plan
Each action with its owner and date — tick it off when complete
Early contact with the competent authorities
Eng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiDirector, Design & Fit-outP-023f.alsulami@bog.gov.saIn progressIn 33 days2026-11-3020 Jumada II 1448 AHA compliance checklist before every submission
Eng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiDirector, Design & Fit-outP-023f.alsulami@bog.gov.saNot startedIn 33 days2026-11-3020 Jumada II 1448 AH
Trigger
A permit application is refused or returned
Contingency
Submit a design alternative that meets the rules