PRJ-2026-019At risk7ExecutionConstruction

Al-Waha Central Park

Add to watchlist

A 420,000 m² central park with walking trails, cultural venues and a lake.

Budget (BAC)

SAR 158M

Actual cost

SAR 83.8M

⁦53%⁩ of budget

Progress

⁦52%⁩

Planned ⁦56%⁩

Estimate at completion

SAR 161.2M

SAR +3.2M

SPI · CPI

0.93Schedule performance index · 0.930.98Cost performance index · 0.98

Forecast finish

⁦2027-03-12⁩

12 days behind baseline

ExecutionPhase ⁦7⁩ of ⁦11⁩

Next gate:Monitoring & Control20 November 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate27 September 2024Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate15 January 2025Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate16 March 2025Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionConditional goDate21 April 2025Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate12 May 2025Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionGoDate8 July 2025Execution · Current phaseExecution · Current phase
  8. Gate into «Monitoring & Control»DecisionNot held yetDate20 November 2026Monitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Project health across eight dimensions

A weighted index, not just percent complete; each dimension leads to the tab that explains it.

Index over the last six reports

−11

May to October 2026

No material change in the health dimensions over the period.

Copilot summary

Generated from the live project data

The project is close to plan: ⁦52%⁩ done against ⁦56%⁩ planned.

SPI ⁦0.93⁩, CPI ⁦0.98⁩.

Progress & earned value

⁦3⁩ of ⁦5⁩ milestones complete

Earned-value curve

Planned, earned and actual to the data date, cumulative, with the forecast cost tail

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Budget & commitments

Commitments are ⁦83%⁩ of budget

83.8M/ 158M3.2Mprojected overrun(⁦2.0%⁩)
Actual spend
83.8M
Committed
131M
Approved budget
158M
Estimate at completion
161.2M

Next milestones

  • Provisional acceptance⁦2027-01-11⁩was ⁦2027-01-02⁩At risk
  • Closure⁦2027-03-12⁩was ⁦2027-02-28⁩At risk

Waiting on someone

⁦0⁩ approvals and ⁦0⁩ open actions on this project

Approvals & requests

From «My actions» for this project

  • No approvals pending

Actions

⁦0⁩ open

  • No actions on this project

Change requests

Cost and schedule impact

  • No change requests

Risks & issues

1 open risk, exposure SAR 2.1M

Risk map

Probability
5Probability: Almost certain · Impact: NegligibleLow · Score ⁦5⁩Probability: Almost certain · Impact: MinorMedium · Score ⁦10⁩Probability: Almost certain · Impact: ModerateHigh · Score ⁦15⁩Probability: Almost certain · Impact: MajorCritical · Score ⁦20⁩Probability: Almost certain · Impact: SevereCritical · Score ⁦25⁩
4Probability: Likely · Impact: NegligibleLow · Score ⁦4⁩Probability: Likely · Impact: MinorMedium · Score ⁦8⁩Probability: Likely · Impact: ModerateMedium · Score ⁦12⁩Probability: Likely · Impact: MajorHigh · Score ⁦16⁩Probability: Likely · Impact: SevereCritical · Score ⁦20⁩
3Probability: Possible · Impact: NegligibleLow · Score ⁦3⁩Probability: Possible · Impact: MinorLow · Score ⁦6⁩1Probability: Possible · Impact: ModerateMedium · Score ⁦9⁩RSK-0039Late supply of mature trees from approved nurseriesProbability: Possible · Impact: MajorMedium · Score ⁦12⁩Probability: Possible · Impact: SevereHigh · Score ⁦15⁩
2Probability: Unlikely · Impact: NegligibleLow · Score ⁦2⁩Probability: Unlikely · Impact: MinorLow · Score ⁦4⁩Probability: Unlikely · Impact: ModerateLow · Score ⁦6⁩Probability: Unlikely · Impact: MajorMedium · Score ⁦8⁩Probability: Unlikely · Impact: SevereMedium · Score ⁦10⁩
1Probability: Rare · Impact: NegligibleLow · Score ⁦1⁩Probability: Rare · Impact: MinorLow · Score ⁦2⁩Probability: Rare · Impact: ModerateLow · Score ⁦3⁩Probability: Rare · Impact: MajorLow · Score ⁦4⁩Probability: Rare · Impact: SevereLow · Score ⁦5⁩
12345

Impact

  • Critical0
  • High0
  • Medium1
  • Low0

Open issues

⁦0⁩ escalated

  • No open issues

Deliverables

⁦2⁩ of ⁦4⁩ approved

  • Project management planDLV-019-1 · V1Eng. Fahad T. Al-Sulami⁦2025-04-14⁩2025-04-1416 Shawwal 1446 AHApproved
  • Main deliverable — stage 1DLV-019-2 · V1Eng. Abdulrahman S. Al-Harbi⁦2026-03-15⁩2026-03-1526 Ramadan 1447 AHApproved
  • Main deliverable — final stageDLV-019-3 · V1Eng. Abdulrahman S. Al-HarbiIn 23 days2026-11-2010 Jumada II 1448 AHIn progress
  • Final reportDLV-019-4 · V0Eng. Abdulrahman S. Al-HarbiIn 123 days2027-02-2821 Ramadan 1448 AHDraft

Team, contracts & documents

Team

1 member

Eng. Fahad T. Al-Sulami · Director, Urban Development
  • Eng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiDirector, Urban DevelopmentProject managerP-023f.alsulami@alwaha.gov.sa⁦45%⁩

Documents

  • No documents yet

Meetings

  • No meetings scheduled
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close