Hail Administrative Court Building
Add to watchlistA new 18,000 m² building for the Hail administrative court, with 12 courtrooms and a video-hearing suite.
Budget (BAC)
Actual cost
53% of budget
Progress
Planned 56%
Estimate at completion
SAR +3.2M
SPI · CPI
Forecast finish
12 days behind baseline
ExecutionPhase 7 of 11
Next gate:Monitoring & Control20 November 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate27 September 2024Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionGoDate15 January 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate16 March 2025Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionConditional goDate21 April 2025Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate12 May 2025Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionGoDate8 July 2025Execution · Current phaseExecution · Current phase
- Gate into «Monitoring & Control»DecisionNot held yetDate20 November 2026Monitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2025-08-10 | 2025-11-04 | +86 days | Eng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiDirector, Design & Fit-outP-023f.alsulami@bog.gov.sa | Achieved | 1 | Approved |
| Designs approvedMS-G2 | Project | 2025-12-02 | 2026-05-02 | +151 days | Eng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiDirector, Design & Fit-outP-023f.alsulami@bog.gov.sa | Achieved | 1 | Approved |
| Build completeMS-G3 | Contractual | 2026-05-21 | 2026-11-26 | +189 days | Eng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiDirector, Design & Fit-outP-023f.alsulami@bog.gov.sa | Late | 0 | Not requested |
| Testing & acceptance completeMS-G4 | Regulatory | 2026-11-07 | 2027-01-28 | +82 days | Eng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiDirector, Design & Fit-outP-023f.alsulami@bog.gov.sa | At risk | 0 | Not requested |
| Final handoverMS-G5 | Payment | 2027-02-28 | 2027-03-11 | +11 days | Eng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiDirector, Design & Fit-outP-023f.alsulami@bog.gov.sa | On track | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Deliverable flow
Display options
| Deliverable: Project plan & baseline019-D1 | Approved | Eng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiDirector, Design & Fit-outP-023f.alsulami@bog.gov.sa | Eng. Abdulrahman S. Al-Harbi | 2025-06-15 | V1 | 2 of 2 |
| Deliverable: Monitoring & reporting019-D2 | Approved | Eng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDirector General, Engineering ProjectsP-014ab.alharbi@bog.gov.sa | Eng. Abdulrahman S. Al-Harbi | 2025-08-10 | V1 | 2 of 2 |
| Deliverable: Detailed design019-D3 | Approved | Eng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDirector General, Engineering ProjectsP-014ab.alharbi@bog.gov.sa | Eng. Abdulrahman S. Al-Harbi | 2025-10-06 | V1 | 2 of 2 |
| Deliverable: Permits & approvals019-D4 | Approved | Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziAssistant President, Projects & FacilitiesP-010t.alanazi@bog.gov.sa | Eng. Abdulrahman S. Al-Harbi | 2025-12-02 | V1 | 2 of 2 |
| Deliverable: Site works & excavation019-D5 | Approved | Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziAssistant President, Projects & FacilitiesP-010t.alanazi@bog.gov.sa | Eng. Abdulrahman S. Al-Harbi | 2026-01-27 | V1 | 2 of 2 |
| Deliverable: Structure019-D6 | Approved | Eng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiDirector, Design & Fit-outP-023f.alsulami@bog.gov.sa | Eng. Abdulrahman S. Al-Harbi | 2026-03-25 | V1 | 2 of 2 |