Hail Administrative Court Building

Add to watchlist

A new 18,000 m² building for the Hail administrative court, with 12 courtrooms and a video-hearing suite.

Budget (BAC)

SAR 158M

Actual cost

SAR 83.8M

⁦53%⁩ of budget

Progress

⁦52%⁩

Planned ⁦56%⁩

Estimate at completion

SAR 161.2M

SAR +3.2M

SPI · CPI

0.93Schedule performance index · 0.930.98Cost performance index · 0.98

Forecast finish

⁦2027-03-12⁩

12 days behind baseline

ExecutionPhase ⁦7⁩ of ⁦11⁩

Next gate:Monitoring & Control20 November 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate27 September 2024Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate15 January 2025Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate16 March 2025Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionConditional goDate21 April 2025Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate12 May 2025Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionGoDate8 July 2025Execution · Current phaseExecution · Current phase
  8. Gate into «Monitoring & Control»DecisionNot held yetDate20 November 2026Monitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started