Original
Original baseline
- Finish
- 2027-02-28
- Budget
- SAR 158M
- 17 activities
Approved with the project plan at the planning gate.
Approved 2025-03-16 · by Eng. Turki A. Al-Anazi
A new 18,000 m² building for the Hail administrative court, with 12 courtrooms and a video-hearing suite.
Budget (BAC)
Actual cost
53% of budget
Progress
Planned 56%
Estimate at completion
SAR +3.2M
SPI · CPI
Forecast finish
12 days behind baseline
ExecutionPhase 7 of 11
Next gate:Monitoring & Control20 November 2026
The original, the approved revised and the working baseline, with any two versions compared on dates and cost. An approved baseline is locked and moves only through a change request; every version is kept.
Original
Approved with the project plan at the planning gate.
Approved 2025-03-16 · by Eng. Turki A. Al-Anazi
Working
Follows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.
Created 2026-10-28 · by Eng. Fahad T. Al-Sulami
What changed from version A to version B
Finish
2027-02-282027-03-11
+11 days
Budget
SAR 158MSAR 158M
0.00 SAR M
Milestones moved
5 / 5
Each line starts at the milestone’s date in A and ends at its date in B
Version AVersion B
Difference in SAR millions from A to B
Every saved version with its reason and reference