Hail Administrative Court Building
Add to watchlistA new 18,000 m² building for the Hail administrative court, with 12 courtrooms and a video-hearing suite.
Budget (BAC)
Actual cost
53% of budget
Progress
Planned 56%
Estimate at completion
SAR +3.2M
SPI · CPI
Forecast finish
12 days behind baseline
ExecutionPhase 7 of 11
Next gate:Monitoring & Control20 November 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate27 September 2024Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionGoDate15 January 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate16 March 2025Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionConditional goDate21 April 2025Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate12 May 2025Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionGoDate8 July 2025Execution · Current phaseExecution · Current phase
- Gate into «Monitoring & Control»DecisionNot held yetDate20 November 2026Monitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Scope statement
What the project delivers, what it does not, and when a deliverable counts as accepted.
A new 18,000 m² building for the Hail administrative court, with 12 courtrooms and a video-hearing suite.
In scope
- A new 18,000 m² building for the Hail administrative court, with 12 courtrooms and a video-hearing suite.
- Saudi Building Code compliance
- Consultant-approved drawings
Out of scope
- Operation and maintenance after the warranty period
- Work outside the approved site or system boundary
Acceptance criteria
- Main deliverable — stage 1Meets the approved specification, signed off by the business owner
- Main deliverable — final stageMeets the approved specification, signed off by the business owner
Scope baseline
Every approved change creates a new baseline
- 1
SB-1Current2025-04-17
Baseline approved at the planning gate
Budget158MFinish2027-02-28
Requirements register
6 requirements of five kinds, with the trace status of each
By type
- Business1
- Functional1
- Technical1
- Regulatory2
- Security1
Fully traced
100%
6/6 · linked to a deliverable, task and test
Test passed
17%
1/6 · test result is a pass
Accepted
17%
1/6 · signed off by the business owner
Display options
| REQ-019-01 | A building ready for hearings | Business | Must | Approved | Eng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDirector General, Engineering ProjectsP-014ab.alharbi@bog.gov.sa | SB-1 | |
| REQ-019-02 | Match the approved drawings | Technical | Must | In progress | Eng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiDirector, Design & Fit-outP-023f.alsulami@bog.gov.sa | SB-1 | |
| REQ-019-03 | Smart building systems | Functional | Must | In progress | Eng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDirector General, Engineering ProjectsP-014ab.alharbi@bog.gov.sa | SB-1 | |
| REQ-019-04 | Saudi Building Code | Regulatory | Could | Approved | Eng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiDirector, Design & Fit-outP-023f.alsulami@bog.gov.sa | SB-1 | |
| REQ-019-05 | Health & safety | Regulatory | Could | Approved | Eng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDirector General, Engineering ProjectsP-014ab.alharbi@bog.gov.sa | SB-1 | |
| REQ-019-06 | CCTV and access control | Security | Should | In progress | Eng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiDirector, Design & Fit-outP-023f.alsulami@bog.gov.sa | SB-1 |
Traceability matrix
Requirement → deliverable → task → test → acceptance. No requirement has a gap.