The main contractor’s distress and claims stall both sites
PRK-05-1·Escalate·Eng. Shahad M. Al-Malki
Programme · PG-05 · Capital Projects Portfolio
Government complexes and emergency facilities that end leases and co-locate services.
incl. SAR 18M programme reserve
52% of budget
Estimate at completion
Planned 62%
Cost performance index 0.86
Manager
Eng. Shahad M. Al-Malki
Director, Government Buildings & Facilities
Sponsor
Eng. Abdulrahman S. Al-Harbi
Deputy, Capital Projects
Projects
2 projects
2024-02-04 — 2028-12-31
Critical 1On hold 1
What the programme must achieve, and the strategic objectives it serves.
End every government lease by 2028 with one complex
A regional emergency & safety centre ready for 24/7 operation
Co-locate service delivery in one point of access
From baseline to target
Annual lease savings
by 2028Agencies moved into the complex
by 2028One lane per project: start to forecast finish, with the progress earned and the baseline finish.
What waits on what. Red links are on the programme’s critical path.
Critical path
Critical
The emergency centre shares the complex’s substation and utilities
Risks that hit more than one project, managed at programme level.
The main contractor’s distress and claims stall both sites
PRK-05-1·Escalate·Eng. Shahad M. Al-Malki
4 risks
Impact
| Probability \ Impact | 1 | 2 | 3 | 4 | 5 |
|---|---|---|---|---|---|
| 5 | 0 · Low | 0 · Medium | 0 · High | 2 · Critical | 0 · Critical |
| 4 | 0 · Low | 0 · Medium | 0 · Medium | 1 · High | 0 · Critical |
| 3 | 0 · Low | 0 · Low | 0 · Medium | 0 · Medium | 1 · High |
| 2 | 0 · Low | 0 · Low | 0 · Low | 0 · Medium | 0 · Medium |
| 1 | 0 · Low | 0 · Low | 0 · Low | 0 · Low | 0 · Low |
Resident satisfaction with the urban landscape
71%
+1
Target 72%99%
Savings from spend rationalisation
61SAR M
+6
Target 8572%
Power against interest; click a person to see their role.
Keep satisfied0
Manage closely4
Monitor0
Keep informed0
Interest
What the committees decided on the programme’s projects, and what the programme raised to them.
Regional Emergency Centre on hold until the land is handed over
PMO Committee · 2026-10-22 · DEC-2026-041
Offices Complex extension deferred pending the independent engineer’s report
Change Control Board · 2026-10-21 · DEC-2026-040
Government Offices Complex claims referred to dispute resolution
Projects Steering Committee · 2026-10-13 · DEC-2026-037
Temporary office-building option cancelled in favour of the complex
Executive Committee · 2026-09-08 · DEC-2026-044
Committees
Monthly · Quorum 5
Members
6 members
Weekly · Quorum 4
Weekly · Quorum 4
Members
5 members
The programme’s performance is computed from these projects (§6).
Display options
| Manager | ||||||||
|---|---|---|---|---|---|---|---|---|
| Government Offices ComplexPRJ-2026-007 | Eng. Shahad M. Al-Malki | 7Execution | Critical | 57% | 640M | 780.5M+22.0% | 0.70Schedule performance index · 0.70 | 0.82Cost performance index · 0.82 |
| Regional Emergency & Safety CentrePRJ-2026-033 | Eng. Shahad M. Al-Malki | 4Planning | On hold | 2% | 210M | 210M0.0% | 1.00Schedule performance index · 1.00 | 1.00Cost performance index · 1.00 |
| Total · 2 | 850M | 990.5M |
SAR 850M
Budget
| Category | Value | Share |
|---|---|---|
| Government Offices Complex | SAR 640M | 75% |
| Regional Emergency & Safety Centre | SAR 210M | 25% |
| Total | SAR 850M | 100% |