Programme · PG-05 · Capital Projects Portfolio

Government Buildings & Facilities Programme

Critical

Government complexes and emergency facilities that end leases and co-locate services.

Approved budget
SAR 868M

incl. SAR 18M programme reserve

Actual spend
SAR 449.1M

⁦52%⁩ of budget

EAC
SAR 990.5M+16.5%

Estimate at completion

Progress
⁦43%⁩

Planned ⁦62%⁩

Schedule performance index
0.77

Cost performance index 0.86

Manager

Eng. Shahad M. Al-Malki

Director, Government Buildings & Facilities

Sponsor

Eng. Abdulrahman S. Al-Harbi

Deputy, Capital Projects

Projects

2 projects

2024-02-04 — 2028-12-31

Critical 1On hold 1

Programme objectives

What the programme must achieve, and the strategic objectives it serves.

  1. 1

    End every government lease by 2028 with one complex

  2. 2

    A regional emergency & safety centre ready for 24/7 operation

  3. 3

    Co-locate service delivery in one point of access

Programme benefits

From baseline to target

  • Annual lease savings

    by ⁦2028⁩
    Baseline 0Current 0 SAR MTarget 64
  • Agencies moved into the complex

    by ⁦2028⁩
    Baseline 0Current 0 agenciesTarget 14

Roadmap

One lane per project: start to forecast finish, with the progress earned and the baseline finish.

EarnedRemainingBaseline finishSlip
20242025202620272028
2027-06-01
2028-12-31

Dependencies between projects

What waits on what. Red links are on the programme’s critical path.

Critical path

What each project needs from the one before

  • Critical

    The emergency centre shares the complex’s substation and utilities

Shared risks

Risks that hit more than one project, managed at programme level.

25

The main contractor’s distress and claims stall both sites

PRK-05-1·Escalate·Eng. Shahad M. Al-Malki

Affects

Open risks in the programme’s projects

4 risks

Open risks in the programme’s projects
  • Critical2
  • High2
  • Medium0
  • Low0
  • Risks 4
Probability
5
4
3
2
1
12345

Impact

Open risks in the programme’s projects
Probability \ Impact12345
50 · Low0 · Medium0 · High2 · Critical0 · Critical
40 · Low0 · Medium0 · Medium1 · High0 · Critical
30 · Low0 · Low0 · Medium0 · Medium1 · High
20 · Low0 · Low0 · Low0 · Medium0 · Medium
10 · Low0 · Low0 · Low0 · Low0 · Low

Programme KPIs · Stakeholders

Stakeholders

Power against interest; click a person to see their role.

Power

Keep satisfied0

Manage closely4

Monitor0

Keep informed0

Eng. Abdulrahman S. Al-HarbiManage closelyEng. Turki A. Al-AnaziManage closelyEng. Ibrahim A. Al-GhamdiManage closelyMunirah A. Al-KhalidiManage closely

Interest

Programme decisions

What the committees decided on the programme’s projects, and what the programme raised to them.

Committees

Projects Steering Committee

Monthly · Quorum ⁦5⁩

Dr. Mohammed I. Al-Subaie · VP, Planning & StrategyEng. Turki A. Al-Anazi · VP, Projects & InfrastructureEng. Majed S. Al-Rasheed · VP, Digital Transformation & Technology
Chair: Eng. Abdullah S. Al-QahtaniNext meeting 2026-11-03
Executive Committee

Weekly · Quorum ⁦4⁩

Dr. Mohammed I. Al-Subaie · VP, Planning & StrategyEng. Turki A. Al-Anazi · VP, Projects & InfrastructureEng. Majed S. Al-Rasheed · VP, Digital Transformation & TechnologySarah A. Al-Qarni · VP, Support Services
Chair: Eng. Abdullah S. Al-QahtaniNext meeting 2026-10-28
Change Control Board

Weekly · Quorum ⁦4⁩

Dr. Noura M. Al-Otaibi · Director, Enterprise PMOKhalid N. Al-Mutairi · Senior Finance & Contracts SpecialistMunirah A. Al-Khalidi · Deputy, Financial Affairs
Chair: Dr. Mohammed I. Al-SubaieNext meeting 2026-10-29

Programme projects

The programme’s performance is computed from these projects (§6).

⁦2⁩ results
Export CSV
Manager
Government Offices ComplexPRJ-2026-007Eng. Shahad M. Al-Malki7ExecutionCritical⁦57%⁩640M780.5M⁦+22.0%⁩0.70Schedule performance index · 0.700.82Cost performance index · 0.82
Regional Emergency & Safety CentrePRJ-2026-033Eng. Shahad M. Al-Malki4PlanningOn hold⁦2%⁩210M210M⁦0.0%⁩1.00Schedule performance index · 1.001.00Cost performance index · 1.00
Total · 2850M990.5M
⁦1⁩–⁦2⁩ of ⁦2⁩

Budget shares

Budget shares

SAR 850M

Budget

  • Government Offices ComplexSAR 640M⁦75%⁩
  • Regional Emergency & Safety CentreSAR 210M⁦25%⁩
Budget shares
CategoryValueShare
Government Offices ComplexSAR 640M⁦75%⁩
Regional Emergency & Safety CentreSAR 210M⁦25%⁩
TotalSAR 850M⁦100%⁩