Riyadh Administrative Court Building
Remove from watchlistA 92,000 m² building for 42 judicial circuits — ending nine leased premises and bringing beneficiary services under one roof.
Budget (BAC)
Actual cost
70% of budget
Progress
Planned 82%
Estimate at completion
SAR +140.5M
SPI · CPI
Forecast finish
152 days behind baseline
ExecutionPhase 7 of 11
Next gate:Monitoring & Control4 August 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate18 August 2023Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionGoDate6 December 2023Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate4 February 2024Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionGoDate28 March 2024Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate29 April 2024Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionConditional goDate23 July 2024Execution · Current phaseExecution · Current phase
- Gate into «Monitoring & Control»DecisionNot held yetDate4 August 2026Monitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2024-09-10 | 2025-01-10 | +122 days | Eng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiDirector, Judicial Buildings & PremisesP-022s.almalki@bog.gov.sa | Achieved | 1 | Approved |
| Designs approvedMS-G2 | Project | 2025-02-25 | 2025-09-29 | +216 days | Eng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiDirector, Judicial Buildings & PremisesP-022s.almalki@bog.gov.sa | Achieved | 1 | Approved |
| Build completeMS-G3 | Contractual | 2025-11-05 | 2026-10-26 | +355 days | Eng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiDirector, Judicial Buildings & PremisesP-022s.almalki@bog.gov.sa | Achieved | 1 | Approved |
| Testing & acceptance completeMS-G4 | Regulatory | 2026-07-16 | 2027-04-15 | +273 days | Eng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiDirector, Judicial Buildings & PremisesP-022s.almalki@bog.gov.sa | Late | 0 | Not requested |
| Final handoverMS-G5 | Payment | 2026-12-31 | 2027-06-02 | +153 days | Eng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiDirector, Judicial Buildings & PremisesP-022s.almalki@bog.gov.sa | At risk | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Deliverable flow
Display options
| Deliverable: Project plan & baseline007-D1 | Approved | Eng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiDirector, Judicial Buildings & PremisesP-022s.almalki@bog.gov.sa | Eng. Abdulrahman S. Al-Harbi | 2024-06-18 | V1 | 2 of 2 |
| Deliverable: Monitoring & reporting007-D2 | Approved | Eng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDirector General, Engineering ProjectsP-014ab.alharbi@bog.gov.sa | Eng. Abdulrahman S. Al-Harbi | 2024-09-10 | V1 | 2 of 2 |
| Deliverable: Detailed design007-D3 | Approved | Eng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDirector General, Engineering ProjectsP-014ab.alharbi@bog.gov.sa | Eng. Abdulrahman S. Al-Harbi | 2024-12-03 | V1 | 2 of 2 |
| Deliverable: Permits & approvals007-D4 | Approved | Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziAssistant President, Projects & FacilitiesP-010t.alanazi@bog.gov.sa | Eng. Abdulrahman S. Al-Harbi | 2025-02-25 | V1 | 2 of 2 |
| Deliverable: Site works & excavation007-D5 | Approved | Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziAssistant President, Projects & FacilitiesP-010t.alanazi@bog.gov.sa | Eng. Abdulrahman S. Al-Harbi | 2025-05-21 | V1 | 2 of 2 |
| Deliverable: Structure007-D6 | Approved | Eng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiDirector, Judicial Buildings & PremisesP-022s.almalki@bog.gov.sa | Eng. Abdulrahman S. Al-Harbi | 2025-08-13 | V1 | 2 of 2 |