10My actionsNotifications
PRJ-2026-007Critical7ExecutionConstruction

Government Offices Complex

Remove from watchlist

A 92,000 m² complex housing 14 agencies — ending leased buildings and co-locating services.

Early warning: ⁦97%⁩ chance of slipping within ⁦30⁩ days

Budget (BAC)

SAR 640M

Actual cost

SAR 444.9M

⁦70%⁩ of budget

Progress

⁦57%⁩

Planned ⁦82%⁩

Estimate at completion

SAR 780.5M

SAR +140.5M

SPI · CPI

0.70Schedule performance index · 0.700.82Cost performance index · 0.82

Forecast finish

⁦2027-06-01⁩

152 days behind baseline

ExecutionPhase ⁦7⁩ of ⁦11⁩

Next gate:Monitoring & Control4 August 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate18 August 2023Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate6 December 2023Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate4 February 2024Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate28 March 2024Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate29 April 2024Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionConditional goDate23 July 2024Execution · Current phaseExecution · Current phase
  8. Gate into «Monitoring & Control»DecisionNot held yetDate4 August 2026Monitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Team & roles

4 members, about ⁦1.8⁩ full-time equivalents

Leadership

2 members

  • Eng. Shahad M. Al-MalkiProject manager⁦90%⁩Allocated ⁦110%⁩ across all projectsA
  • Eng. Abdulrahman S. Al-HarbiProject sponsor⁦25%⁩Allocated ⁦110%⁩ across all projectsR

Specialists

1 member

  • Khalid N. Al-MutairiComplex contract & certificates⁦20%⁩C

Vendor team & advisers

1 member

  • Eng. Adel S. Al-AmoudiSite engineer (MEP)⁦40%⁩R

A AccountableR ResponsibleC ConsultedI Informed

Stakeholders

⁦6⁩ stakeholders, ⁦4⁩ of them below the engagement needed

Power / interest matrix

Pick one to see how they are handled

Power & influence

Keep satisfied1

high power, lower interest

Manage closely4

high power and interest

Monitor0

minimal effort

Keep informed1

high interest, lower power

Eng. Turki A. Al-AnaziManage closelyEng. Abdulrahman S. Al-HarbiManage closelyEnterprise PMOManage closelyEnd beneficiariesKeep informedFinancial Affairs AgencyKeep satisfiedGulf General Contracting Co.Manage closely

Interest

Project sponsor

Eng. Turki A. Al-Anazi

Decisions and funding

Influence

Interest

Engagement level

Unaware

Resistant

Neutral

Now

Supportive

Target

Leading

A gap of ⁦1⁩ steps — needs an engagement plan.

Impact on the project
Approves gates and changes
Engagement plan
Monthly briefing
Last contact⁦2026-10-13⁩
⁦6⁩ results
Export CSV
OrganisationRoleActions
Eng. Turki A. Al-AnaziProject sponsorDecisions and fundingSupportiveLeadingEng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiDirector, Government Buildings & FacilitiesP-022s.almalki@alwaha.gov.sa⁦2026-10-13⁩
Eng. Abdulrahman S. Al-HarbiBusiness ownerAccepts deliverables, owns benefitsNeutralLeadingEng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiDirector, Government Buildings & FacilitiesP-022s.almalki@alwaha.gov.sa⁦2026-10-16⁩
Enterprise PMOGovernanceCompliance and data qualitySupportiveEng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiDirector, Government Buildings & FacilitiesP-022s.almalki@alwaha.gov.sa⁦2026-10-10⁩
Financial Affairs AgencyInternal departmentPayment approvalNeutralSupportiveHaifa S. Al-RuwailiHaifa S. Al-RuwailiSenior Financial AnalystP-037h.alruwaili@alwaha.gov.sa⁦2026-10-07⁩
Gulf General Contracting Co.Main vendorDelivers the contracted workLeadingEng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiDirector, Government Buildings & FacilitiesP-022s.almalki@alwaha.gov.sa⁦2026-10-17⁩
End beneficiariesBeneficiariesUsers of the outcomeNeutralSupportiveEng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiDirector, Government Buildings & FacilitiesP-022s.almalki@alwaha.gov.sa⁦2026-09-19⁩
⁦1⁩–⁦6⁩ of ⁦6⁩

Communication plan

Who needs what, when, through which channel, and who owns it.

  • Project sponsorStatus and decisions neededMonthlyMeetingEng. Shahad M. Al-Malki⁦2026-11-08⁩
  • Business ownerDeliverable status and acceptance datesFortnightlyEmailEng. Shahad M. Al-Malki⁦2026-10-27⁩
  • PMOData and indicator updatesWeeklyDashboardEng. Shahad M. Al-Malki⁦2026-10-24⁩
  • BeneficiariesWhat changes and whenAt milestonesNewsletterEng. Shahad M. Al-MalkiAt launch

Coming up

By date

  1. 242026-10PMODashboard · Weekly
  2. 272026-10Business ownerEmail · Fortnightly
  3. 082026-11Project sponsorMeeting · Monthly
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close