Government Offices Complex
Remove from watchlistA 92,000 m² complex housing 14 agencies — ending leased buildings and co-locating services.
Budget (BAC)
Actual cost
70% of budget
Progress
Planned 82%
Estimate at completion
SAR +140.5M
SPI · CPI
Forecast finish
152 days behind baseline
ExecutionPhase 7 of 11
Next gate:Monitoring & Control4 August 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate18 August 2023Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionGoDate6 December 2023Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate4 February 2024Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionGoDate28 March 2024Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate29 April 2024Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionConditional goDate23 July 2024Execution · Current phaseExecution · Current phase
- Gate into «Monitoring & Control»DecisionNot held yetDate4 August 2026Monitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Team & roles
4 members, about 1.8 full-time equivalents
Leadership
2 members
- Eng. Shahad M. Al-MalkiProject manager90%Allocated 110% across all projectsA
- Eng. Abdulrahman S. Al-HarbiProject sponsor25%Allocated 110% across all projectsR
Specialists
1 member
- Khalid N. Al-MutairiComplex contract & certificates20%C
Vendor team & advisers
1 member
- Eng. Adel S. Al-AmoudiSite engineer (MEP)40%R
A AccountableR ResponsibleC ConsultedI Informed
Stakeholders
6 stakeholders, 4 of them below the engagement needed
Power / interest matrix
Pick one to see how they are handled
Keep satisfied1
high power, lower interest
Manage closely4
high power and interest
Monitor0
minimal effort
Keep informed1
high interest, lower power
Interest
Project sponsor
Eng. Turki A. Al-Anazi
Decisions and funding
Influence
Interest
Engagement level
Unaware
Resistant
Neutral
Supportive
Leading
A gap of 1 steps — needs an engagement plan.
- Impact on the project
- Approves gates and changes
- Engagement plan
- Monthly briefing
Display options
| Organisation | Role | Actions | ||||||
|---|---|---|---|---|---|---|---|---|
| Eng. Turki A. Al-Anazi | Project sponsor | Decisions and funding | SupportiveLeading | Eng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiDirector, Government Buildings & FacilitiesP-022s.almalki@alwaha.gov.sa | 2026-10-13 | |||
| Eng. Abdulrahman S. Al-Harbi | Business owner | Accepts deliverables, owns benefits | NeutralLeading | Eng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiDirector, Government Buildings & FacilitiesP-022s.almalki@alwaha.gov.sa | 2026-10-16 | |||
| Enterprise PMO | Governance | Compliance and data quality | Supportive | Eng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiDirector, Government Buildings & FacilitiesP-022s.almalki@alwaha.gov.sa | 2026-10-10 | |||
| Financial Affairs Agency | Internal department | Payment approval | NeutralSupportive | Haifa S. Al-RuwailiHaifa S. Al-RuwailiSenior Financial AnalystP-037h.alruwaili@alwaha.gov.sa | 2026-10-07 | |||
| Gulf General Contracting Co. | Main vendor | Delivers the contracted work | Leading | Eng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiDirector, Government Buildings & FacilitiesP-022s.almalki@alwaha.gov.sa | 2026-10-17 | |||
| End beneficiaries | Beneficiaries | Users of the outcome | NeutralSupportive | Eng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiDirector, Government Buildings & FacilitiesP-022s.almalki@alwaha.gov.sa | 2026-09-19 |
Communication plan
Who needs what, when, through which channel, and who owns it.
- Project sponsorStatus and decisions neededMonthlyMeetingEng. Shahad M. Al-Malki2026-11-08
- Business ownerDeliverable status and acceptance datesFortnightlyEmailEng. Shahad M. Al-Malki2026-10-27
- PMOData and indicator updatesWeeklyDashboardEng. Shahad M. Al-Malki2026-10-24
- BeneficiariesWhat changes and whenAt milestonesNewsletterEng. Shahad M. Al-MalkiAt launch
Coming up
By date
- 242026-10PMODashboard · Weekly
- 272026-10Business ownerEmail · Fortnightly
- 082026-11Project sponsorMeeting · Monthly