Board of GrievancesMunjaz10My actionsNotifications
PRJ-2026-007Critical7ExecutionConstruction

Riyadh Administrative Court Building

Remove from watchlist

A 92,000 m² building for 42 judicial circuits — ending nine leased premises and bringing beneficiary services under one roof.

Early warning: ⁦97%⁩ chance of slipping within ⁦30⁩ days

Budget (BAC)

SAR 640M

Actual cost

SAR 444.9M

⁦70%⁩ of budget

Progress

⁦57%⁩

Planned ⁦82%⁩

Estimate at completion

SAR 780.5M

SAR +140.5M

SPI · CPI

0.70Schedule performance index · 0.700.82Cost performance index · 0.82

Forecast finish

⁦2027-06-01⁩

152 days behind baseline

ExecutionPhase ⁦7⁩ of ⁦11⁩

Next gate:Monitoring & Control4 August 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate18 August 2023Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate6 December 2023Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate4 February 2024Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate28 March 2024Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate29 April 2024Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionConditional goDate23 July 2024Execution · Current phaseExecution · Current phase
  8. Gate into «Monitoring & Control»DecisionNot held yetDate4 August 2026Monitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Closure readiness

Closure planned after the forecast finish on ⁦2027-06-01⁩

A preview of what closure will need, with the planned dates, and the lessons captured so far.

0/7

Closure checklist

Seven mandatory items before any project closes.

  1. 1

    Deliverables acceptedNot started

    Final acceptance of every deliverable

    Eng. Abdulrahman S. Al-HarbiPlanned ⁦2027-05-22⁩

  2. 2

    Financial closureNot started

    Spend reconciled, commitments closed

    Khalid N. Al-MutairiPlanned ⁦2027-06-21⁩

  3. 3

    Contract closureNot started

    Contracts closed, retention released

    Khalid N. Al-MutairiPlanned ⁦2027-07-01⁩

  4. 4

    Documents archivedNot started

    Documents archived with classification

    Eng. Shahad M. Al-MalkiPlanned ⁦2027-06-26⁩

  5. 5

    Lessons learnedNot started

    Lessons-learned session

    Eng. Shahad M. Al-MalkiPlanned ⁦2027-06-16⁩

  6. 6

    Benefits owner assignedNot started

    Benefits handed to their owner with a measurement plan

    Eng. Abdulrahman S. Al-HarbiPlanned ⁦2027-06-11⁩

  7. 7

    Final report approvedNot started

    Final report and its approval

    Eng. Shahad M. Al-MalkiPlanned ⁦2027-07-06⁩

Post-implementation review

Did it reach its goal? Did it stay on budget? Were the benefits realised? What did we learn and improve?

The review comes after closure

About three months after the forecast finish (⁦2027-06-01⁩), with the sponsor and the benefits owner.

Lessons learned

0 lessons — offered automatically to similar projects when they are created.

Knowledge base

No lessons captured yet

Capture what the team learned during delivery; closure needs at least one.

Benefits handover

Each benefit moves from the project manager to an owner who measures it after closure.

No benefits recorded for this project.