PRJ-2026-031On track11Benefits RealizationScrum

Unified e-Appointments Platform

Add to watchlist

One booking system for service-centre appointments, with reminders and instant feedback.

Budget (BAC)

SAR 8.2M

Actual cost

SAR 8M

⁦97%⁩ of budget

Progress

⁦100%⁩

Planned ⁦100%⁩

Estimate at completion

SAR 8M

SPI · CPI

1.00Schedule performance index · 1.001.03Cost performance index · 1.03

Forecast finish

⁦2025-07-20⁩

20 days behind baseline

Benefits RealizationPhase ⁦11⁩ of ⁦11⁩

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate20 October 2023Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate7 February 2024Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate7 April 2024Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate29 April 2024Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate13 May 2024Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionGoDate18 June 2024Execution · CompleteExecution · Complete
  8. Gate into «Monitoring & Control»DecisionGoDate28 April 2025Monitoring & Control · CompleteMonitoring & Control · Complete
  9. Gate into «Handover»DecisionGoDate25 May 2025Handover · CompleteHandover · Complete
  10. Gate into «Closure»DecisionGoDate30 June 2025Closure · CompleteClosure · Complete
  11. Gate into «Benefits Realization»DecisionGoDate29 August 2025Benefits Realization · Current phaseBenefits Realization · Current phase

Closed project

Project closed on ⁦2025-09-28⁩

All seven closure items are done, the post-implementation review was held, and the benefits passed to their owner to measure.

7/7

Closure checklist

Seven mandatory items before any project closes.

  1. 1

    Deliverables acceptedDone

    Final acceptance of ⁦9⁩ deliverables, no open findings

    Faisal A. Al-ShehriDone ⁦2025-07-20⁩

  2. 2

    Financial closureDone

    Actual SAR ⁦7.96M⁩ of ⁦8.2M⁩ — SAR ⁦240K⁩ returned to budget

    Khalid N. Al-MutairiDone ⁦2025-09-10⁩

  3. 3

    Contract closureDone

    Contract ⁦WRDA/2024/009⁩ closed, retention released

    Khalid N. Al-MutairiDone ⁦2025-09-14⁩Evidence

  4. 4

    Documents archivedDone

    ⁦64⁩ documents archived with their classification

    Karim HaddadDone ⁦2025-09-18⁩Evidence

  5. 5

    Lessons learnedDone

    ⁦3⁩ lessons published, cited ⁦13⁩ times since

    Karim HaddadDone ⁦2025-08-30⁩Evidence

  6. 6

    Benefits owner assignedDone

    Eng. Reem Al-Dosari owns two benefits with a ⁦24-month⁩ plan

    Eng. Reem K. Al-DosariDone ⁦2025-09-21⁩

  7. 7

    Final report approvedDone

    Final report approved by the sponsor and the PMO

    Karim HaddadDone ⁦2025-09-28⁩

Post-implementation review

Did it reach its goal? Did it stay on budget? Were the benefits realised? What did we learn and improve?

Held on ⁦2025-10-22⁩Review score 84/100· Facilitated by Dr. Noura M. Al-Otaibi

Did it reach its goal?

Yes

9/9

Yes. Unified booking went live in ⁦9⁩ centres; ⁦410K⁩ bookings in year one.

Did it stay on budget?

Yes

−2.9%

Delivered for SAR ⁦7.96M⁩ against ⁦8.2M⁩, ⁦20⁩ days after baseline.

Were the benefits realised?

Partly

82%

⁦82%⁩ realised: satisfaction ⁦82%⁩ vs ⁦85%⁩ target, waits ⁦18⁩ minutes vs ⁦15⁩.

What did we learn?

Yes

3

Three lessons: Nafath environments, payments tied to acceptance, the vendor team.

What should improve?

Partly

2

An SMS reminder the day before, and linking booking into the unified services platform.

Lessons learned

2 lessons — offered automatically to similar projects when they are created.

LL-041Integrationcited ⁦6⁩ times

Book Nafath test environments three months before build

Context
The e-appointments platform needed single sign-on through Nafath.
What happened
The test environment arrived seven weeks late because it was requested after build started.
Impact
Launch slipped five weeks; SAR ⁦340K⁩ extra vendor time.
Recommendation
Request the environment when the charter is approved and make it a planning-gate item.
Karim Haddad · ⁦2025-08-20⁩
LL-021Financecited ⁦3⁩ times

Tie payments to accepted deliverables, not elapsed time

Context
The e-appointments build contract.
What happened
A ⁦20%⁩ payment was released before the stage passed acceptance.
Impact
Hard to hold the vendor to ⁦37⁩ open defects.
Recommendation
A payment schedule tied to deliverable acceptance in every digital contract.
Khalid N. Al-Mutairi · ⁦2025-08-30⁩

Benefits handover

Each benefit moves from the project manager to an owner who measures it after closure.