Did it reach its goal?
Yes9/9
Yes. Unified booking went live in 9 centres; 410K bookings in year one.
One booking system for service-centre appointments, with reminders and instant feedback.
Budget (BAC)
Actual cost
97% of budget
Progress
Planned 100%
Estimate at completion
SPI · CPI
Forecast finish
20 days behind baseline
Benefits RealizationPhase 11 of 11
Closed project
All seven closure items are done, the post-implementation review was held, and the benefits passed to their owner to measure.
Seven mandatory items before any project closes.
Deliverables acceptedDone
Final acceptance of 9 deliverables, no open findings
Faisal A. Al-ShehriDone 2025-07-20
Financial closureDone
Actual SAR 7.96M of 8.2M — SAR 240K returned to budget
Khalid N. Al-MutairiDone 2025-09-10
Contract closureDone
Contract WRDA/2024/009 closed, retention released
Khalid N. Al-MutairiDone 2025-09-14Evidence
Documents archivedDone
64 documents archived with their classification
Karim HaddadDone 2025-09-18Evidence
Lessons learnedDone
3 lessons published, cited 13 times since
Karim HaddadDone 2025-08-30Evidence
Benefits owner assignedDone
Eng. Reem Al-Dosari owns two benefits with a 24-month plan
Eng. Reem K. Al-DosariDone 2025-09-21
Final report approvedDone
Final report approved by the sponsor and the PMO
Karim HaddadDone 2025-09-28
Did it reach its goal? Did it stay on budget? Were the benefits realised? What did we learn and improve?
Did it reach its goal?
Yes9/9
Yes. Unified booking went live in 9 centres; 410K bookings in year one.
Did it stay on budget?
Yes−2.9%
Delivered for SAR 7.96M against 8.2M, 20 days after baseline.
Were the benefits realised?
Partly82%
82% realised: satisfaction 82% vs 85% target, waits 18 minutes vs 15.
What did we learn?
Yes3
Three lessons: Nafath environments, payments tied to acceptance, the vendor team.
What should improve?
Partly2
An SMS reminder the day before, and linking booking into the unified services platform.
2 lessons — offered automatically to similar projects when they are created.
Each benefit moves from the project manager to an owner who measures it after closure.
baseline 42 · now 18 · target 15 minutes
baseline 64 · now 82 · target 85 %