PRJ-2026-031On track11Benefits RealizationScrum

Court Appointment Booking Service

Add to watchlist

One booking service for beneficiary desks in the courts, with reminders and instant feedback.

Budget (BAC)

SAR 8.2M

Actual cost

SAR 8M

⁦97%⁩ of budget

Progress

⁦100%⁩

Planned ⁦100%⁩

Estimate at completion

SAR 8M

SPI · CPI

1.00Schedule performance index · 1.001.03Cost performance index · 1.03

Forecast finish

⁦2025-07-20⁩

20 days behind baseline

Benefits RealizationPhase ⁦11⁩ of ⁦11⁩

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate20 October 2023Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate7 February 2024Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate7 April 2024Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate29 April 2024Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate13 May 2024Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionGoDate18 June 2024Execution · CompleteExecution · Complete
  8. Gate into «Monitoring & Control»DecisionGoDate28 April 2025Monitoring & Control · CompleteMonitoring & Control · Complete
  9. Gate into «Handover»DecisionGoDate25 May 2025Handover · CompleteHandover · Complete
  10. Gate into «Closure»DecisionGoDate30 June 2025Closure · CompleteClosure · Complete
  11. Gate into «Benefits Realization»DecisionGoDate29 August 2025Benefits Realization · Current phaseBenefits Realization · Current phase

Baselines

The original, the approved revised and the working baseline, with any two versions compared on dates and cost. An approved baseline is locked and moves only through a change request; every version is kept.

  1. Original

    Original baseline

    v1.0Approved & lockedVersion A
    Finish
    ⁦2025-06-30⁩
    Budget
    SAR 8.2M
    ⁦16⁩ activities

    Approved with the project plan at the planning gate.

    Approved ⁦2024-04-07⁩ · by Eng. Majed S. Al-Rasheed

  2. Working

    Working baseline

    v2.0-draftWorking draftVersion B
    Finish
    ⁦2025-07-20⁩
    ⁦+20⁩ days
    Budget
    SAR 8.2M
    ⁦16⁩ activities

    Follows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.

    Created ⁦2026-10-28⁩ · by Karim Haddad

    Edit in the schedule

Compare two versions

What changed from version A to version B

Finish

⁦2025-06-30⁩⁦2025-07-20⁩

⁦+20⁩ days

Budget

SAR 8.2MSAR 8.2M

⁦0.00⁩ SAR M

Milestones moved

5 / 5

Milestones: A to B

Each line starts at the milestone’s date in A and ends at its date in B

2024-072025-012025-07
  • Project plan approved⁦+4⁩
  • Designs approved⁦+8⁩
  • Build complete⁦+13⁩
  • Testing & acceptance complete⁦+16⁩
  • Final handover⁦+20⁩

Version AVersion B

Cost by WBS element

Difference in SAR millions from A to B

  • 1Management & governance⁦−0.02⁩
  • 2Analysis & design⁦−0.02⁩
  • 3Build⁦+0.14⁩
  • 4Testing & acceptance⁦−0.02⁩
  • 5Launch & handover⁦−0.02⁩

Version history

Every saved version with its reason and reference

  1. Working baselinev2.0-draftWorking draftFollows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.⁦2026-10-28⁩by Karim Haddad
  2. Original baselinev1.0Approved & lockedApproved with the project plan at the planning gate.⁦2024-04-07⁩by Eng. Majed S. Al-Rasheed