Board of GrievancesMunjaz10My actionsNotifications
PRJ-2026-031On track11Benefits RealizationScrum

Court Appointment Booking Service

Add to watchlist

One booking service for beneficiary desks in the courts, with reminders and instant feedback.

Budget (BAC)

SAR 8.2M

Actual cost

SAR 8M

⁦97%⁩ of budget

Progress

⁦100%⁩

Planned ⁦100%⁩

Estimate at completion

SAR 8M

SPI · CPI

1.00Schedule performance index · 1.001.03Cost performance index · 1.03

Forecast finish

⁦2025-07-20⁩

20 days behind baseline

Benefits RealizationPhase ⁦11⁩ of ⁦11⁩

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate20 October 2023Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate7 February 2024Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate7 April 2024Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate29 April 2024Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate13 May 2024Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionGoDate18 June 2024Execution · CompleteExecution · Complete
  8. Gate into «Monitoring & Control»DecisionGoDate28 April 2025Monitoring & Control · CompleteMonitoring & Control · Complete
  9. Gate into «Handover»DecisionGoDate25 May 2025Handover · CompleteHandover · Complete
  10. Gate into «Closure»DecisionGoDate30 June 2025Closure · CompleteClosure · Complete
  11. Gate into «Benefits Realization»DecisionGoDate29 August 2025Benefits Realization · Current phaseBenefits Realization · Current phase

Milestones

Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.

Milestone runway

5Achieved
0On track
0At risk
0Late
Average delay12 days
Jul 24Oct 24Jan 25Apr 25Jul 25
Contractual
Build completePlanned: ⁦2025-01-26⁩Forecast / actual: ⁦2025-02-08⁩Delay: 13 daysG3 +13
Executive
Project plan approvedPlanned: ⁦2024-07-17⁩Forecast / actual: ⁦2024-07-21⁩Delay: 4 daysG1 +4
Payment
Final handoverPlanned: ⁦2025-06-30⁩Forecast / actual: ⁦2025-07-20⁩Delay: 20 daysG5 +20
Regulatory
Testing & acceptance completePlanned: ⁦2025-04-14⁩Forecast / actual: ⁦2025-04-30⁩Delay: 16 daysG4 +16
Project
Designs approvedPlanned: ⁦2024-10-02⁩Forecast / actual: ⁦2024-10-10⁩Delay: 8 daysG2 +8

The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay

Milestone register

⁦5⁩ results
Export CSV
Project plan approvedMS-G1Executive⁦2024-07-17⁩⁦2024-07-21⁩⁦+4⁩ daysKarim HaddadKarim HaddadSenior Digital Delivery Consultant — EPMOP-041k.haddad@bog.gov.saAchieved1Approved
Designs approvedMS-G2Project⁦2024-10-02⁩⁦2024-10-10⁩⁦+8⁩ daysKarim HaddadKarim HaddadSenior Digital Delivery Consultant — EPMOP-041k.haddad@bog.gov.saAchieved1Approved
Build completeMS-G3Contractual⁦2025-01-26⁩⁦2025-02-08⁩⁦+13⁩ daysKarim HaddadKarim HaddadSenior Digital Delivery Consultant — EPMOP-041k.haddad@bog.gov.saAchieved1Approved
Testing & acceptance completeMS-G4Regulatory⁦2025-04-14⁩⁦2025-04-30⁩⁦+16⁩ daysKarim HaddadKarim HaddadSenior Digital Delivery Consultant — EPMOP-041k.haddad@bog.gov.saAchieved1Approved
Final handoverMS-G5Payment⁦2025-06-30⁩⁦2025-07-20⁩⁦+20⁩ daysKarim HaddadKarim HaddadSenior Digital Delivery Consultant — EPMOP-041k.haddad@bog.gov.saAchieved1Approved
⁦1⁩–⁦5⁩ of ⁦5⁩

Deliverables register

Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.

Deliverable flow

Pick a stage to filter the register
⁦6⁩ results
Export CSV
Deliverable: Project plan & baseline031-D1ApprovedKarim HaddadKarim HaddadSenior Digital Delivery Consultant — EPMOP-041k.haddad@bog.gov.saFaisal A. Al-Shehri⁦2024-06-08⁩V1⁦2⁩ of ⁦2⁩
Deliverable: Monitoring & reporting031-D2ApprovedFaisal A. Al-ShehriFaisal A. Al-ShehriDirector, Digital Judicial Services Centre & Digital Justice Portfolio ManagerP-003f.alshehri@bog.gov.saFaisal A. Al-Shehri⁦2024-07-17⁩V1⁦2⁩ of ⁦2⁩
Deliverable: Business requirements031-D3ApprovedFaisal A. Al-ShehriFaisal A. Al-ShehriDirector, Digital Judicial Services Centre & Digital Justice Portfolio ManagerP-003f.alshehri@bog.gov.saFaisal A. Al-Shehri⁦2024-08-24⁩V1⁦2⁩ of ⁦2⁩
Deliverable: Solution design031-D4ApprovedEng. Majed S. Al-RasheedEng. Majed S. Al-RasheedVice President, Judicial AffairsP-011m.alrasheed@bog.gov.saFaisal A. Al-Shehri⁦2024-10-02⁩V1⁦2⁩ of ⁦2⁩
Deliverable: Release 1031-D5ApprovedEng. Majed S. Al-RasheedEng. Majed S. Al-RasheedVice President, Judicial AffairsP-011m.alrasheed@bog.gov.saFaisal A. Al-Shehri⁦2024-11-10⁩V1⁦2⁩ of ⁦2⁩
Deliverable: Release 2031-D6ApprovedKarim HaddadKarim HaddadSenior Digital Delivery Consultant — EPMOP-041k.haddad@bog.gov.saFaisal A. Al-Shehri⁦2024-12-18⁩V1⁦2⁩ of ⁦2⁩
⁦1⁩–⁦6⁩ of ⁦6⁩
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close