Court Appointment Booking Service
Add to watchlistOne booking service for beneficiary desks in the courts, with reminders and instant feedback.
Budget (BAC)
Actual cost
97% of budget
Progress
Planned 100%
Estimate at completion
SPI · CPI
Forecast finish
20 days behind baseline
Benefits RealizationPhase 11 of 11
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate20 October 2023Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionGoDate7 February 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate7 April 2024Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionGoDate29 April 2024Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate13 May 2024Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionGoDate18 June 2024Execution · CompleteExecution · Complete
- Gate into «Monitoring & Control»DecisionGoDate28 April 2025Monitoring & Control · CompleteMonitoring & Control · Complete
- Gate into «Handover»DecisionGoDate25 May 2025Handover · CompleteHandover · Complete
- Gate into «Closure»DecisionGoDate30 June 2025Closure · CompleteClosure · Complete
- Gate into «Benefits Realization»DecisionGoDate29 August 2025Benefits Realization · Current phaseBenefits Realization · Current phase
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2024-07-17 | 2024-07-21 | +4 days | Karim HaddadKarim HaddadSenior Digital Delivery Consultant — EPMOP-041k.haddad@bog.gov.sa | Achieved | 1 | Approved |
| Designs approvedMS-G2 | Project | 2024-10-02 | 2024-10-10 | +8 days | Karim HaddadKarim HaddadSenior Digital Delivery Consultant — EPMOP-041k.haddad@bog.gov.sa | Achieved | 1 | Approved |
| Build completeMS-G3 | Contractual | 2025-01-26 | 2025-02-08 | +13 days | Karim HaddadKarim HaddadSenior Digital Delivery Consultant — EPMOP-041k.haddad@bog.gov.sa | Achieved | 1 | Approved |
| Testing & acceptance completeMS-G4 | Regulatory | 2025-04-14 | 2025-04-30 | +16 days | Karim HaddadKarim HaddadSenior Digital Delivery Consultant — EPMOP-041k.haddad@bog.gov.sa | Achieved | 1 | Approved |
| Final handoverMS-G5 | Payment | 2025-06-30 | 2025-07-20 | +20 days | Karim HaddadKarim HaddadSenior Digital Delivery Consultant — EPMOP-041k.haddad@bog.gov.sa | Achieved | 1 | Approved |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Deliverable flow
Display options
| Deliverable: Project plan & baseline031-D1 | Approved | Karim HaddadKarim HaddadSenior Digital Delivery Consultant — EPMOP-041k.haddad@bog.gov.sa | Faisal A. Al-Shehri | 2024-06-08 | V1 | 2 of 2 |
| Deliverable: Monitoring & reporting031-D2 | Approved | Faisal A. Al-ShehriFaisal A. Al-ShehriDirector, Digital Judicial Services Centre & Digital Justice Portfolio ManagerP-003f.alshehri@bog.gov.sa | Faisal A. Al-Shehri | 2024-07-17 | V1 | 2 of 2 |
| Deliverable: Business requirements031-D3 | Approved | Faisal A. Al-ShehriFaisal A. Al-ShehriDirector, Digital Judicial Services Centre & Digital Justice Portfolio ManagerP-003f.alshehri@bog.gov.sa | Faisal A. Al-Shehri | 2024-08-24 | V1 | 2 of 2 |
| Deliverable: Solution design031-D4 | Approved | Eng. Majed S. Al-RasheedEng. Majed S. Al-RasheedVice President, Judicial AffairsP-011m.alrasheed@bog.gov.sa | Faisal A. Al-Shehri | 2024-10-02 | V1 | 2 of 2 |
| Deliverable: Release 1031-D5 | Approved | Eng. Majed S. Al-RasheedEng. Majed S. Al-RasheedVice President, Judicial AffairsP-011m.alrasheed@bog.gov.sa | Faisal A. Al-Shehri | 2024-11-10 | V1 | 2 of 2 |
| Deliverable: Release 2031-D6 | Approved | Karim HaddadKarim HaddadSenior Digital Delivery Consultant — EPMOP-041k.haddad@bog.gov.sa | Faisal A. Al-Shehri | 2024-12-18 | V1 | 2 of 2 |