Late Nafath/SADAD readiness delays both the platform and the app
PRK-01-1·Mitigate·Eng. Reem K. Al-Dosari
Programme · PG-01 · Digital Transformation Portfolio
One beneficiary journey for every service — web, mobile, e-appointments and the investor portal.
incl. SAR 4M programme reserve
65% of budget
Estimate at completion
Planned 72%
Cost performance index 0.98
Manager
Eng. Reem K. Al-Dosari
Programme Manager, Digital Government Services
Sponsor
Eng. Majed S. Al-Rasheed
VP, Digital Transformation & Technology
Projects
4 projects
2024-04-07 — 2027-05-12
On track 3At risk 1
What the programme must achieve, and the strategic objectives it serves.
One beneficiary journey for every service on web and mobile, with a single digital identity
Lift fully-online services from 55% to 80% by the end of 2027
Cut service-centre visits by 40% by moving them to digital channels
From baseline to target
Beneficiary satisfaction with digital services
by 2027Average licence turnaround
by 2027Service-centre operating savings
by 2028One lane per project: start to forecast finish, with the progress earned and the baseline finish.
What waits on what. Red links are on the programme’s critical path.
Critical path
The appointments engine and booking logic are reused inside the platform
Investor journeys move into the unified platform after launch
Critical
The mobile app consumes the platform’s APIs and Nafath integration
Risks that hit more than one project, managed at programme level.
Late Nafath/SADAD readiness delays both the platform and the app
PRK-01-1·Mitigate·Eng. Reem K. Al-Dosari
One vendor integration team serves three projects in the programme
PRK-01-2·Escalate·Eng. Reem K. Al-Dosari
10 risks
Impact
| Probability \ Impact | 1 | 2 | 3 | 4 | 5 |
|---|---|---|---|---|---|
| 5 | 0 · Low | 0 · Medium | 0 · High | 0 · Critical | 0 · Critical |
| 4 | 0 · Low | 0 · Medium | 0 · Medium | 2 · High | 0 · Critical |
| 3 | 0 · Low | 0 · Low | 3 · Medium | 2 · Medium | 0 · High |
| 2 | 0 · Low | 0 · Low | 2 · Low | 1 · Medium | 0 · Medium |
| 1 | 0 · Low | 0 · Low | 0 · Low | 0 · Low | 0 · Low |
Shift from walk-in to digital channels
58%
+1
Target 60%97%
Average licence turnaround
9.5days
−1
Target 7.0
Beneficiary satisfaction with digital services
74%
0
Target 85%87%
Investment opportunities offered
37opportunities
+4
Target 4093%
Power against interest; click a person to see their role.
Keep satisfied2
Manage closely3
Monitor0
Keep informed1
Interest
What the committees decided on the programme’s projects, and what the programme raised to them.
Committees
Monthly · Quorum 5
Members
6 members
Fortnightly · Quorum 4
Members
7 members
Weekly · Quorum 4
Members
5 members
The programme’s performance is computed from these projects (§6).
Display options
| Manager | ||||||||
|---|---|---|---|---|---|---|---|---|
| Investor PortalPRJ-2026-008 | Karim Haddad | 8Monitoring & Control | On track | 91% | 18.4M | 18M−2.0% | 1.01Schedule performance index · 1.01 | 1.02Cost performance index · 1.02 |
| Unified Digital Services PlatformPRJ-2026-014 | Eng. Sultan F. Al-Ghamdi | 7Execution | At risk | 58% | 86.4M | 90M+4.2% | 0.87Schedule performance index · 0.87 | 0.96Cost performance index · 0.96 |
| Services Mobile AppPRJ-2026-015 | Karim Haddad | 7Execution | On track | 64% | 12.6M | 12.1M−3.8% | 1.02Schedule performance index · 1.02 | 1.04Cost performance index · 1.04 |
| Unified e-Appointments PlatformPRJ-2026-031 | Karim Haddad | 11Benefits Realization | On track | 100% | 8.2M | 8M−2.9% | 1.00Schedule performance index · 1.00 | 1.03Cost performance index · 1.03 |
| Total · 4 | 125.6M | 128.1M |
SAR 125.6M
Budget
| Category | Value | Share |
|---|---|---|
| Investor Portal | SAR 18.4M | 15% |
| Unified Digital Services Platform | SAR 86.4M | 69% |
| Services Mobile App | SAR 12.6M | 10% |
| Unified e-Appointments Platform | SAR 8.2M | 7% |
| Total | SAR 125.6M | 100% |