The project with the most weight on this KPI is “Unified Digital Services Platform”, with 87% of the linked investment, and it is At risk. Speeding it up is the fastest way to close the gap before December.
What we are doing to bring the KPI back on track, who owns it, and by when.
Speed up the Nafath integration with a dedicated integration squad
Hussam T. Al-QurashiHussam T. Al-QurashiSenior Software Engineer – IntegrationP-030·h.alqurashi@alwaha.gov.saDue 2026-10-226 days overdue2026-10-22·11 Jumada I 1448 AHUnified Digital Services Platform
Overdue
Fix the five biggest beneficiary-journey complaints, starting with re-keyed data
Eng. Sultan F. Al-GhamdiEng. Sultan F. Al-GhamdiProject Manager, Unified Digital Services PlatformP-005·s.alghamdi@alwaha.gov.saDue 2026-11-30In 33 days2026-11-30·20 Jumada II 1448 AHUnified Digital Services Platform
In progress
Comments
The owner, Performance Measurement and leadership discussing the readings.
Eng. Abdullah S. Al-QahtaniChief Executive Officer2026-10-27 08:10
Three flat months of satisfaction is not acceptable. I want a clear plan at the next executive committee.
Eng. Reem K. Al-DosariProgramme Manager, Digital Government Services2026-10-27 10:45
We analysed 1,240 ratings: 61% of comments are about re-keying data and slow Nafath checks. Both corrective actions are tied to the next release.
Tariq S. Al-YamiDirector, Corporate Performance Measurement2026-10-28 09:05
October’s reading is awaiting my approval; the survey sample is 312 beneficiaries, within the accepted minimum.