PRJ-2026-015On track7ExecutionScrum

Services Mobile App

Add to watchlist

A mobile app for the most-used services, with push notifications and a digital document wallet.

Budget (BAC)

SAR 12.6M

Actual cost

SAR 7.8M

⁦62%⁩ of budget

Progress

⁦64%⁩

Planned ⁦63%⁩

Estimate at completion

SAR 12.1M

SPI · CPI

1.02Schedule performance index · 1.021.04Cost performance index · 1.04

Forecast finish

⁦2027-01-28⁩

On baseline

ExecutionPhase ⁦7⁩ of ⁦11⁩

Next gate:Monitoring & Control24 November 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionConditional goDate18 April 2025Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate6 August 2025Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate5 October 2025Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate29 October 2025Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate13 November 2025Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionGoDate21 December 2025Execution · Current phaseExecution · Current phase
  8. Gate into «Monitoring & Control»DecisionNot held yetDate24 November 2026Monitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Project health across eight dimensions

A weighted index, not just percent complete; each dimension leads to the tab that explains it.

Index over the last six reports

+4

May to October 2026

No material change in the health dimensions over the period.

Copilot summary

Generated from the live project data

The project is close to plan: ⁦64%⁩ done against ⁦63%⁩ planned.

SPI ⁦1.02⁩, CPI ⁦1.04⁩.

Progress & earned value

⁦3⁩ of ⁦5⁩ milestones complete

Earned-value curve

Planned, earned and actual to the data date, cumulative, with the forecast cost tail

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Budget & commitments

Commitments are ⁦87%⁩ of budget

7.8M/ 12.6M485Kprojected saving(⁦3.8%⁩)
Actual spend
7.8M
Committed
10.9M
Approved budget
12.6M
Estimate at completion
12.1M

Next milestones

  • Provisional acceptance⁦2026-12-21⁩was ⁦2026-12-23⁩On track
  • Closure⁦2027-01-28⁩was ⁦2027-01-31⁩On track

Waiting on someone

⁦0⁩ approvals and ⁦0⁩ open actions on this project

Approvals & requests

From «My actions» for this project

  • No approvals pending

Actions

⁦0⁩ open

  • No actions on this project

Risks & issues

0 open risks, exposure SAR 0

Risk map

Probability
5Probability: Almost certain · Impact: NegligibleLow · Score ⁦5⁩Probability: Almost certain · Impact: MinorMedium · Score ⁦10⁩Probability: Almost certain · Impact: ModerateHigh · Score ⁦15⁩Probability: Almost certain · Impact: MajorCritical · Score ⁦20⁩Probability: Almost certain · Impact: SevereCritical · Score ⁦25⁩
4Probability: Likely · Impact: NegligibleLow · Score ⁦4⁩Probability: Likely · Impact: MinorMedium · Score ⁦8⁩Probability: Likely · Impact: ModerateMedium · Score ⁦12⁩Probability: Likely · Impact: MajorHigh · Score ⁦16⁩Probability: Likely · Impact: SevereCritical · Score ⁦20⁩
3Probability: Possible · Impact: NegligibleLow · Score ⁦3⁩Probability: Possible · Impact: MinorLow · Score ⁦6⁩Probability: Possible · Impact: ModerateMedium · Score ⁦9⁩Probability: Possible · Impact: MajorMedium · Score ⁦12⁩Probability: Possible · Impact: SevereHigh · Score ⁦15⁩
2Probability: Unlikely · Impact: NegligibleLow · Score ⁦2⁩Probability: Unlikely · Impact: MinorLow · Score ⁦4⁩Probability: Unlikely · Impact: ModerateLow · Score ⁦6⁩Probability: Unlikely · Impact: MajorMedium · Score ⁦8⁩Probability: Unlikely · Impact: SevereMedium · Score ⁦10⁩
1Probability: Rare · Impact: NegligibleLow · Score ⁦1⁩Probability: Rare · Impact: MinorLow · Score ⁦2⁩Probability: Rare · Impact: ModerateLow · Score ⁦3⁩Probability: Rare · Impact: MajorLow · Score ⁦4⁩Probability: Rare · Impact: SevereLow · Score ⁦5⁩
12345

Impact

  • Critical0
  • High0
  • Medium0
  • Low0

Top risks

  • No open risks

Open issues

⁦0⁩ escalated

  • No open issues

Deliverables

⁦2⁩ of ⁦4⁩ approved

  • Project management planDLV-015-1 · V1Karim Haddad⁦2025-10-24⁩2025-10-242 Jumada I 1447 AHApproved
  • Main deliverable — stage 1DLV-015-2 · V1Faisal A. Al-Shehri⁦2026-06-08⁩2026-06-0822 Dhuʻl-Hijjah 1447 AHApproved
  • Main deliverable — final stageDLV-015-3 · V1Faisal A. Al-ShehriIn 27 days2026-11-2414 Jumada II 1448 AHIn progress
  • Final reportDLV-015-4 · V0Faisal A. Al-ShehriIn 95 days2027-01-3123 Shaʻban 1448 AHDraft

Team, contracts & documents

Team

6 members

Karim Haddad · Senior Digital Delivery ConsultantEng. Reem K. Al-Dosari · Programme Manager, Digital Government ServicesJoud N. Al-Ahmadi · QA & Testing SpecialistHussam T. Al-Qurashi · Senior Software Engineer – IntegrationLama S. Al-Harbi · Senior Business Analyst
  • Karim HaddadKarim HaddadSenior Digital Delivery ConsultantProject managerP-041k.haddad@alwaha.gov.sa⁦40%⁩
  • Eng. Reem K. Al-DosariEng. Reem K. Al-DosariProgramme Manager, Digital Government ServicesProgramme oversight, mobile appP-004r.aldosari@alwaha.gov.sa⁦15%⁩
  • Joud N. Al-AhmadiJoud N. Al-AhmadiQA & Testing SpecialistApp testingP-033j.alahmadi@alwaha.gov.sa⁦40%⁩
  • Hussam T. Al-QurashiHussam T. Al-QurashiSenior Software Engineer – IntegrationApp APIsP-030h.alqurashi@alwaha.gov.sa⁦35%⁩
  • Lama S. Al-HarbiLama S. Al-HarbiSenior Business AnalystApp service requirementsP-006l.alharbi@alwaha.gov.sa⁦25%⁩

Documents

  • No documents yet

Meetings

  • No meetings scheduled