PRJ-2026-015On track7ExecutionScrum

Board of Grievances Mobile App — Release 3

Add to watchlist

A mobile app for the most-used judicial services, with instant hearing alerts and a digital wallet for judgments.

Budget (BAC)

SAR 12.6M

Actual cost

SAR 7.8M

⁦62%⁩ of budget

Progress

⁦64%⁩

Planned ⁦63%⁩

Estimate at completion

SAR 12.1M

SPI · CPI

1.02Schedule performance index · 1.021.04Cost performance index · 1.04

Forecast finish

⁦2027-01-28⁩

On baseline

ExecutionPhase ⁦7⁩ of ⁦11⁩

Next gate:Monitoring & Control24 November 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionConditional goDate18 April 2025Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate6 August 2025Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate5 October 2025Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate29 October 2025Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate13 November 2025Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionGoDate21 December 2025Execution · Current phaseExecution · Current phase
  8. Gate into «Monitoring & Control»DecisionNot held yetDate24 November 2026Monitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Scope statement

What the project delivers, what it does not, and when a deliverable counts as accepted.

A mobile app for the most-used judicial services, with instant hearing alerts and a digital wallet for judgments.

In scope

  • A mobile app for the most-used judicial services, with instant hearing alerts and a digital wallet for judgments.
  • Single sign-on through Nafath
  • Integration with internal systems

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

Acceptance criteria

  • Main deliverable — stage 1Meets the approved specification, signed off by the business owner
  • Main deliverable — final stageMeets the approved specification, signed off by the business owner

Scope baseline

Every approved change creates a new baseline

  1. 1

    SB-1Current⁦2025-10-27⁩

    Baseline approved at the planning gate

    Budget12.6MFinish⁦2027-01-31⁩

Requirements register

⁦6⁩ requirements of five kinds, with the trace status of each

By type

  • Business1
  • Functional2
  • Technical1
  • Regulatory1
  • Security1

Fully traced

⁦100%⁩

6/6 · linked to a deliverable, task and test

Test passed

⁦17%⁩

1/6 · test result is a pass

Accepted

⁦17%⁩

1/6 · signed off by the business owner

⁦6⁩ results
Export CSV
REQ-015-01An end-to-end digital journey, no walk-inBusinessMustApprovedFaisal A. Al-ShehriFaisal A. Al-ShehriDirector, Digital Judicial Services Centre & Digital Justice Portfolio ManagerP-003f.alshehri@bog.gov.saSB-1
REQ-015-02Nafath single sign-onFunctionalMustApprovedKarim HaddadKarim HaddadSenior Digital Delivery Consultant — EPMOP-041k.haddad@bog.gov.saSB-1
REQ-015-03A user dashboardFunctionalMustIn progressFaisal A. Al-ShehriFaisal A. Al-ShehriDirector, Digital Judicial Services Centre & Digital Justice Portfolio ManagerP-003f.alshehri@bog.gov.saSB-1
REQ-015-04Integration with internal systemsTechnicalShouldIn progressKarim HaddadKarim HaddadSenior Digital Delivery Consultant — EPMOP-041k.haddad@bog.gov.saSB-1
REQ-015-05WCAG ⁦2.1⁩ accessibilityRegulatoryCouldApprovedFaisal A. Al-ShehriFaisal A. Al-ShehriDirector, Digital Judicial Services Centre & Digital Justice Portfolio ManagerP-003f.alshehri@bog.gov.saSB-1
REQ-015-06Essential cybersecurity controlsSecurityCouldIn progressKarim HaddadKarim HaddadSenior Digital Delivery Consultant — EPMOP-041k.haddad@bog.gov.saSB-1
⁦1⁩–⁦6⁩ of ⁦6⁩

Traceability matrix

Requirement → deliverable → task → test → acceptance. No requirement has a gap.