PRJ-2026-015On track7ExecutionScrum

Board of Grievances Mobile App — Release 3

Add to watchlist

A mobile app for the most-used judicial services, with instant hearing alerts and a digital wallet for judgments.

Budget (BAC)

SAR 12.6M

Actual cost

SAR 7.8M

⁦62%⁩ of budget

Progress

⁦64%⁩

Planned ⁦63%⁩

Estimate at completion

SAR 12.1M

SPI · CPI

1.02Schedule performance index · 1.021.04Cost performance index · 1.04

Forecast finish

⁦2027-01-28⁩

On baseline

ExecutionPhase ⁦7⁩ of ⁦11⁩

Next gate:Monitoring & Control24 November 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionConditional goDate18 April 2025Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate6 August 2025Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate5 October 2025Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate29 October 2025Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate13 November 2025Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionGoDate21 December 2025Execution · Current phaseExecution · Current phase
  8. Gate into «Monitoring & Control»DecisionNot held yetDate24 November 2026Monitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Board of Grievances

Project charter

Board of Grievances Mobile App — Release 3

APPROVEDV2Approved ⁦2025-10-03⁩

1Project identity

Project name
Board of Grievances Mobile App — Release 3
Project code
PRJ-2026-015
Sponsor
Eng. Majed S. Al-RasheedEng. Majed S. Al-RasheedVice President, Judicial AffairsP-011m.alrasheed@bog.gov.sa
Project manager
Karim HaddadKarim HaddadSenior Digital Delivery Consultant — EPMOP-041k.haddad@bog.gov.sa
Business owner
Faisal A. Al-ShehriFaisal A. Al-ShehriDirector, Digital Judicial Services Centre & Digital Justice Portfolio ManagerP-003f.alshehri@bog.gov.sa
Portfolio & programme
Digital Justice PortfolioDigital Judicial Services Programme
Type & methodology
Digital · Scrum
Current phase
7Execution

2Background & rationale

A mobile app for the most-used judicial services, with instant hearing alerts and a digital wallet for judgments.

3Objectives

  1. 1Deliver integrated, beneficiary-centred digital judicial services

4Scope

In scope

  • A mobile app for the most-used judicial services, with instant hearing alerts and a digital wallet for judgments.
  • Single sign-on through Nafath
  • Integration with internal systems

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

5High-level requirements

  1. 1Single sign-on through Nafath
  2. 2Integration with internal systems
  3. 3Digital Government Authority standards

6Deliverables

1Project management plan⁦2025-10-24⁩
2Main deliverable — stage 1⁦2026-06-08⁩
3Main deliverable — final stage⁦2026-11-24⁩
4Final report⁦2027-01-31⁩

7Key milestones

  1. Charter approved⁦2025-10-03⁩
  2. Contract signed⁦2025-12-21⁩
  3. 50% of works complete⁦2026-06-08⁩
  4. Provisional acceptance⁦2026-12-23⁩
  5. Closure⁦2027-01-31⁩

8Budget

  • Main contract⁦72.2%⁩9.1M
  • Supervision & consulting⁦14.3%⁩1.8M
  • Internal team⁦8.7%⁩1.1M
  • Contingency reserve (⁦5%⁩)⁦4.8%⁩600K
The owning sector’s approved budgetTotal12.6M

9Timeline

Start
2025-10-0513 Rabiʻ II 1447 AH
Baseline finish
2027-01-3123 Shaʻban 1448 AH
Duration
⁦16⁩ months

10Key risks

  • No risks recorded yet.

11Constraints

  • Stay within the approved budget
  • Comply with the Government Tenders & Procurement Law

12Assumptions

  • Named internal staff available throughout
  • Approvals land within workflow SLAs

13Stakeholders

  • Project sponsorDecisions and funding
  • Business ownerAccepts deliverables, owns benefits
  • Projects Follow-up Office (EPMO)Governance and compliance

14Success criteria

  1. 1Delivered within the approved budget
  2. 2On the approved date ⁦±5%⁩
  3. 3Target benefits within ⁦12⁩ months

15Governance structure

  • Change Control BoardApproves scope, cost and schedule changesWeekly
  • EPMO CommitteeMethodology compliance, data quality, stage gatesFortnightly
  • Project management teamDay-to-day control, risks, issues, weekly statusWeekly
Version V2 · ⁦4⁩ of ⁦4⁩ signaturesInternal — not for circulation outside the Board