Board of Grievances Mobile App — Release 3
Add to watchlistA mobile app for the most-used judicial services, with instant hearing alerts and a digital wallet for judgments.
Budget (BAC)
Actual cost
62% of budget
Progress
Planned 63%
Estimate at completion
SPI · CPI
Forecast finish
On baseline
ExecutionPhase 7 of 11
Next gate:Monitoring & Control24 November 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionConditional goDate18 April 2025Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionGoDate6 August 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate5 October 2025Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionGoDate29 October 2025Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate13 November 2025Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionGoDate21 December 2025Execution · Current phaseExecution · Current phase
- Gate into «Monitoring & Control»DecisionNot held yetDate24 November 2026Monitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Project lifecycle and its gates
Current phase: Execution. Pick a gate on the track to review it.
- Gate into «Feasibility»DecisionConditional goDate18 April 2025Mandatory criteria met, with points to close during the next phase.IdeaComplete
- Gate into «Initiation»DecisionGoDate6 August 2025All criteria and required documents met.FeasibilityComplete
- Gate into «Planning»DecisionGoDate5 October 2025All criteria and required documents met.InitiationComplete
- Gate into «Approval»DecisionGoDate29 October 2025All criteria and required documents met.PlanningComplete
- Gate into «Procurement»DecisionGoDate13 November 2025All criteria and required documents met.ApprovalComplete
- Gate into «Execution»DecisionGoDate21 December 2025All criteria and required documents met.ProcurementComplete
- Gate into «Monitoring & Control»DecisionNot held yetDate24 November 2026ExecutionCurrent phaseCurrent phase
- Gate into «Handover»DecisionNot held yet8Monitoring & ControlNot started
- Gate into «Closure»DecisionNot held yet9HandoverNot started
- Gate into «Benefits Realization»DecisionNot held yet10ClosureNot started
- 11Benefits RealizationNot started
Operational readiness gate — into hypercare & monitoring
Gate readiness
Enough for a conditional go only
Automated control: no move until the criteria are met
- 3 mandatory checklist items open
- 4 required documents not approved
- 2 mandatory criteria under 70 points
- Weighted score 67 under the pass mark 75
Checklist
3 of 7 done
- All in-scope services builtMandatory
- User acceptance testing passedMandatory
- Penetration test passed — no critical/high findingsMandatory
- Data migrated and reconciledMandatory
- Operations & support plan, SLAMandatory
- Users trained — judges, clerks and staff
- Launch rollback plan
Required documents
0 of 4 approved
- UAT reportNot submitted
- Penetration test reportSubmitted — awaiting acceptance · V1
- Operations & support planNot submitted
- Data migration reconciliationSubmitted — awaiting acceptance · V1
Criteria and score
Go from 75, conditional from 60; a mandatory criterion is met from 70.
Deliverables completeweight 30%Met
Awaiting evidence from the project team.
Quality & securityweight 30%Not met
Awaiting evidence from the project team.
Operations & support readinessweight 20%Not met
Awaiting evidence from the project team.
User & change readinessweight 20%
Awaiting evidence from the project team.
Approvers
Projects Steering Committee
- Dr. Abdullah S. Al-QahtaniSteering Committee chairVote pending
- Eng. Majed S. Al-RasheedProject sponsorVote pending
- Dr. Noura M. Al-OtaibiEPMO directorVote pending
- Faisal A. Al-ShehriBusiness ownerVote pending