10My actionsNotifications

Higher visitor satisfaction

At risk

Beneficiary satisfaction · Unified e-Appointments Platform

Baseline

⁦64%⁩

At go-live, ⁦2025-09-30⁩

Latest reading

⁦82%⁩

12 mo reading

Target after 24 months

⁦85%⁩

On ⁦2027-09-30⁩

Target trajectory vs realised

Monthly readings up to the last measurement, then the forecast if performance keeps its current ratio to plan.

Target trajectory vs realised
  • Realised
  • Target trajectory
  • Forecast
Target trajectory vs realised
PeriodRealisedTarget trajectory
2025-09⁦64%⁩⁦64%⁩
2025-10⁦66.4%⁩⁦66.7%⁩
2025-11⁦68.6%⁩⁦69.3%⁩
2025-12⁦71%⁩⁦72%⁩
2026-01⁦73.2%⁩⁦74%⁩
2026-02⁦74.7%⁩⁦76%⁩
2026-03⁦77%⁩⁦78%⁩
2026-04⁦77.7%⁩⁦79.2%⁩
2026-05⁦78.4%⁩⁦80.3%⁩
2026-06⁦79.5%⁩⁦81.5%⁩
2026-07⁦80.4%⁩⁦82.7%⁩
2026-08⁦80.9%⁩⁦83.8%⁩
2026-09⁦82%⁩⁦85%⁩
2026-10 (Forecast)⁦82.2%⁩⁦85.3%⁩
2026-11 (Forecast)⁦82.4%⁩⁦85.5%⁩
2026-12 (Forecast)⁦82.6%⁩⁦85.8%⁩
2027-01 (Forecast)⁦82.9%⁩⁦86%⁩
2027-02 (Forecast)⁦83.1%⁩⁦86.3%⁩
2027-03 (Forecast)⁦83.3%⁩⁦86.5%⁩
2027-04 (Forecast)⁦83.5%⁩⁦86.8%⁩
2027-05 (Forecast)⁦83.7%⁩⁦87%⁩
2027-06 (Forecast)⁦83.9%⁩⁦87.3%⁩
2027-07 (Forecast)⁦84.1%⁩⁦87.5%⁩
2027-08 (Forecast)⁦84.4%⁩⁦87.8%⁩
2027-09 (Forecast)⁦84.6%⁩⁦88%⁩

Measurement schedule

Counted from go-live on ⁦2025-09-30⁩ · data read Monthly

  1. 3

    After 3 months

    2025-12-3010 Rajab 1447 AH·Expected ⁦72%⁩ ·Actual ⁦71%⁩

    to plan⁦88%⁩
  2. 6

    After 6 months

    2026-03-3011 Shawwal 1447 AH·Expected ⁦78%⁩ ·Actual ⁦77%⁩

    to plan⁦93%⁩
  3. 12

    After 12 months

    2026-09-3019 Rabiʻ II 1448 AH·Expected ⁦85%⁩ ·Actual ⁦82%⁩

    to plan⁦86%⁩
  4. 24

    After 24 months

    2027-09-3029 Rabiʻ II 1449 AH·Expected ⁦88%⁩

    In 337 days2027-09-3029 Rabiʻ II 1449 AH

Evidence

7 files backing the readings

  • Measurement data extract — 12 mo

    2026-09-30 · Eng. Reem K. Al-Dosari · ⁦180⁩ KB

  • Benefit measurement report — 12 mo

    2026-09-30 · Eng. Reem K. Al-Dosari · ⁦1,112⁩ KB

  • Measurement data extract — 6 mo

    2026-03-30 · Eng. Reem K. Al-Dosari · ⁦138⁩ KB

  • Benefit measurement report — 6 mo

    2026-03-30 · Eng. Reem K. Al-Dosari · ⁦986⁩ KB

  • Measurement data extract — 3 mo

    2025-12-30 · Eng. Reem K. Al-Dosari · ⁦117⁩ KB

  • Benefit measurement report — 3 mo

    2025-12-30 · Eng. Reem K. Al-Dosari · ⁦923⁩ KB

  • Approved benefit profile — BEN-002

    2025-07-30 · Karim Haddad · ⁦412⁩ KB

Corrective actions

What is being done to bring the benefit back to plan

No actions yet — add a plan to bring the benefit back on track.

Activity

30 September 2026

  1. Milestone: Eng. Reem K. Al-Dosari recorded the ⁦12⁩ mo reading: ⁦82%⁩

    2026-09-30 10:30

30 March 2026

  1. Milestone: Eng. Reem K. Al-Dosari recorded the ⁦6⁩ mo reading: ⁦77%⁩

    2026-03-30 10:30

30 December 2025

  1. Milestone: Eng. Reem K. Al-Dosari recorded the ⁦3⁩ mo reading: ⁦71%⁩

    2025-12-30 10:30

30 July 2025

  1. Approval: Karim Haddad approved the benefit profile and its baseline

    2025-07-30 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close