PRJ-2026-007Critical7ExecutionConstruction

Riyadh Administrative Court Building

Remove from watchlist

A 92,000 m² building for 42 judicial circuits — ending nine leased premises and bringing beneficiary services under one roof.

Early warning: ⁦97%⁩ chance of slipping within ⁦30⁩ days

Budget (BAC)

SAR 640M

Actual cost

SAR 444.9M

⁦70%⁩ of budget

Progress

⁦57%⁩

Planned ⁦82%⁩

Estimate at completion

SAR 780.5M

SAR +140.5M

SPI · CPI

0.70Schedule performance index · 0.700.82Cost performance index · 0.82

Forecast finish

⁦2027-06-01⁩

152 days behind baseline

ExecutionPhase ⁦7⁩ of ⁦11⁩

Next gate:Monitoring & Control4 August 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate18 August 2023Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate6 December 2023Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate4 February 2024Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate28 March 2024Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate29 April 2024Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionConditional goDate23 July 2024Execution · Current phaseExecution · Current phase
  8. Gate into «Monitoring & Control»DecisionNot held yetDate4 August 2026Monitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Baselines

The original, the approved revised and the working baseline, with any two versions compared on dates and cost. An approved baseline is locked and moves only through a change request; every version is kept.

  1. Original

    Original baseline

    v1.0Approved & lockedVersion A
    Finish
    ⁦2026-12-31⁩
    Budget
    SAR 640M
    ⁦17⁩ activities

    Approved with the project plan at the planning gate.

    Approved ⁦2024-02-04⁩ · by Eng. Turki A. Al-Anazi

  2. Working

    Working baseline

    v2.0-draftWorking draftVersion B
    Finish
    ⁦2027-06-02⁩
    ⁦+153⁩ days
    Budget
    SAR 640M
    ⁦17⁩ activities

    Follows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.

    Created ⁦2026-10-28⁩ · by Eng. Shahad M. Al-Malki

    Edit in the schedule

Compare two versions

What changed from version A to version B

Finish

⁦2026-12-31⁩⁦2027-06-02⁩

⁦+153⁩ days

Budget

SAR 640MSAR 640M

⁦0.00⁩ SAR M

Milestones moved

5 / 5

Milestones: A to B

Each line starts at the milestone’s date in A and ends at its date in B

2025-012025-072026-012026-072027-01
  • Project plan approved⁦+122⁩
  • Designs approved⁦+216⁩
  • Build complete⁦+355⁩
  • Testing & acceptance complete⁦+273⁩
  • Final handover⁦+153⁩

Version AVersion B

Cost by WBS element

Difference in SAR millions from A to B

  • 1Management & governance⁦+9.58⁩
  • 2Design & permits⁦+19.16⁩
  • 3Civil works⁦+73.48⁩
  • 4MEP works⁦+40.79⁩
  • 5Handover⁦+19.87⁩

Version history

Every saved version with its reason and reference

  1. Working baselinev2.0-draftWorking draftFollows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.⁦2026-10-28⁩by Eng. Shahad M. Al-Malki
  2. Original baselinev1.0Approved & lockedApproved with the project plan at the planning gate.⁦2024-02-04⁩by Eng. Turki A. Al-Anazi