Riyadh Administrative Court Building
Remove from watchlistA 92,000 m² building for 42 judicial circuits — ending nine leased premises and bringing beneficiary services under one roof.
Budget (BAC)
Actual cost
70% of budget
Progress
Planned 82%
Estimate at completion
SAR +140.5M
SPI · CPI
Forecast finish
152 days behind baseline
ExecutionPhase 7 of 11
Next gate:Monitoring & Control4 August 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate18 August 2023Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionGoDate6 December 2023Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate4 February 2024Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionGoDate28 March 2024Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate29 April 2024Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionConditional goDate23 July 2024Execution · Current phaseExecution · Current phase
- Gate into «Monitoring & Control»DecisionNot held yetDate4 August 2026Monitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Project lifecycle and its gates
Current phase: Execution. Pick a gate on the track to review it.
- Gate into «Feasibility»DecisionGoDate18 August 2023All criteria and required documents met.IdeaComplete
- Gate into «Initiation»DecisionGoDate6 December 2023All criteria and required documents met.FeasibilityComplete
- Gate into «Planning»DecisionGoDate4 February 2024All criteria and required documents met.InitiationComplete
- Gate into «Approval»DecisionGoDate28 March 2024All criteria and required documents met.PlanningComplete
- Gate into «Procurement»DecisionGoDate29 April 2024All criteria and required documents met.ApprovalComplete
- Gate into «Execution»DecisionConditional goDate23 July 2024Mandatory criteria met, with points to close during the next phase.ProcurementComplete
- Gate into «Monitoring & Control»DecisionNot held yetDate4 August 2026ExecutionCurrent phaseCurrent phase
- Gate into «Handover»DecisionNot held yet8Monitoring & ControlNot started
- Gate into «Closure»DecisionNot held yet9HandoverNot started
- Gate into «Benefits Realization»DecisionNot held yet10ClosureNot started
- 11Benefits RealizationNot started
Operational readiness gate — into hypercare & monitoring
Gate readiness
Enough for a conditional go only
Automated control: no move until the criteria are met
- 1 mandatory checklist item open
- 2 required documents not approved
- 1 mandatory criterion under 70 points
- Weighted score 71 under the pass mark 75
Checklist
5 of 7 done
- All in-scope services builtMandatory
- User acceptance testing passedMandatory
- Penetration test passed — no critical/high findingsMandatory
- Data migrated and reconciledMandatory
- Operations & support plan, SLAMandatory
- Users trained — judges, clerks and staff
- Launch rollback plan
Required documents
2 of 4 approved
- UAT reportApproved · V1
- Penetration test reportApproved · V1
- Operations & support planNot submitted
- Data migration reconciliationNot submitted
Criteria and score
Go from 75, conditional from 60; a mandatory criterion is met from 70.
Deliverables completeweight 30%Not met
Awaiting evidence from the project team.
Quality & securityweight 30%Met
Awaiting evidence from the project team.
Operations & support readinessweight 20%Met
Awaiting evidence from the project team.
User & change readinessweight 20%
Awaiting evidence from the project team.
Approvers
Projects Steering Committee
- Dr. Abdullah S. Al-QahtaniSteering Committee chairVote pending
- Eng. Turki A. Al-AnaziProject sponsorVote pending
- Dr. Noura M. Al-OtaibiEPMO directorVote pending
- Eng. Abdulrahman S. Al-HarbiBusiness ownerVote pending